What is the National Housing Strategy?
In 2017 the federal Liberal government announced Canada’s National Housing Strategy which allocated $15 billion of new federal funding to build primarily non-market housing including affordable and social housing, repair and maintain existing social housing to address the pre-COVID lack of rental housing for lower-income households in Canada and new market apartments. Provincial cost sharing was expected to add another $7B.
Post-Covid, there’s a shortage of market housing as well, affecting younger people and renters all the way up the income scale, which is where the $4B 2023 Housing Accelerator Fund comes into play.
The National Housing Strategy is often referred to as a $82+ billion, 10-year plan, but that figure is the total of both new and existing federal program funding.
NHS goals
- Build 160,000 new affordable housing units.
- Repair 300,000 affordable housing units.
- Protect 385,000 community housing units and expand by 50,000
- Provide 300,000 households with financial assistance through the Canada Housing Benefit.
- Remove or reduce 540,000 households’ housing need.
- Cut chronic homelessness by 50%
NHS funding breakdown
NHS program performance: project locations, funding and status
Between August 2017 and October 13, 2023, contributing $4B and loaning $9.5B to support over 141,000 units (almost 59,000 in Toronto).
Program | Purpose | Goal (units) | Status (units) | Funding committed | Total funding | Cost per unit |
---|---|---|---|---|---|---|
Apartment Construction Loan Program | New supply | 71000 | 46968 | 17.6B | 25.8B | $374,936.13 |
Affordable Housing Fund: New | New supply | 60000 | 31589 | 7.5B | 13.2B | $237,107.85 |
Rapid Housing Initiative (RHI) | New supply | 12000 | 15612 | 3.8B | 4.0B | $245,964.64 |
Federal Lands Initiative | New supply | 4000 | 3393 | 120.4M | 202.0M | $35,484.82 |
Housing Accelerator Fund | New supply | 1814 | 75.1M | $41,378.17 | ||
Affordable Housing Innovation Fund | New, renovate | 14,800 | 28,639 | 294.3M | 759.1M | $10,277.59 |
Affordable Housing Fund: Renovate | Renovate supply | 240000 | 128959 | 7.5B | 13.2B | $58,080.48 |
Federal Community Housing Initiative (FCHI) | Support existing | 55000 | 47211 | 162.7M | 618.2M | $3,446.23 |
Community-Based Tenant Initiative | Support existing | 171 applications | 10.0M | |||
Community Housing Transformation Centre | Increase efficiency | 249 applications | 28.0M | |||
Reaching Home (Infrastructure Canada) | Reducing chronic homelessness | 50% | 6% | 4.0B |
The specific locations, descriptions and status of National Housing Strategy projects are shown on the Housing and Infrastructure Project Map by Infrastructure Canada, which provides:
- Project location
- Program name
- Project description
- Federal funding
- Estimated total cost
- Status
For additional details, you can download a spreadsheet of National Housing Strategy data from:
Programs have different definitions of “affordable”
The definition of the “affordable” units varies:
- National Housing Co-Investment Fund only requires that 30% of units be offered at 80% of median market rent. And, its prioritization and incentivization scoring provides no reward for offering more than 51% of units at 80% of median market rent.
- Apartment Construction Loan Program/Rental Construction Financing Initiative (RCFi) requires that 20% of units meet a benchmark of rent at less than 30% of median family income (as determined for each city), as opposed to median market rent.
Oversight
The 2019 National Housing Strategy Act recognizes housing as a human right and commits the federal government to help make this a reality. The Act established several bodies:​
- National Housing Council (National Housing Strategy Act requirements)
- Advisory body to further the housing policy of the Government of Canada and provide advice on the on the effectiveness of the National Housing Strategy to the Minister of Housing, Infrastructure and Communities.
- Federal Housing Advocate​ (National Housing Strategy Act requirements)
- Monitor progress in meeting the goals and timelines and in achieving the desired outcomes set out in the National Housing Strategy.
- Receive submissions from the public on systemic housing issues and unmet housing needs across Canada.
- Review Panels​
The National Housing Strategy consists of a number of programs and initiatives:
NHS project locations, funding and status
Enter your municipality or province or a funding program to see what projects are in development in your community:
Location | Province | Project Name | Number of Units | Number of "Affordable" Units | Number of Accessible Units | Program | Proponent Organization | Date Announced | Project Type | Proponent Type | Total Federal Funding | Contribution Amount | Loan Amount | Construction Status | Latitude | Longitude |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Brantford | Ontario | 416 Kingscourt | 73 | 42 | 19 | National Housing Co-Investment Fund | The Regional Municipality of Waterloo | 2/10/2023 | New Construction | Municipality | $ 5,475,000.00 | $ 5,475,000.00 | $ - | Under Construction | 43.4940 | -80.523985 |
Brantford | Ontario | Trillium Way | 49 | 21 | 10 | National Housing Co-Investment Fund | The Corporation of the City of Brantford | 6/27/2023 | New Construction | Municipality | $ 2,450,000.00 | $ 2,450,000.00 | $ - | Under Construction | 43.2093 | -80.389277 |
105 Mile Post 2 | Nova Scotia | Potlotek Housing Project | 10 | 10 | 0 | Rapid Housing Initiative 2 | Potlotek First Nation | 5/23/2023 | New Construction | Indigenous Governing Body | $ 2,739,586.00 | $ 2,739,586.00 | $ - | Built | 45.7067 | -60.827893 |
Abbotsford | British Columbia | Sumas Village Homes - Building A, B and C | 6 | 6 | 0 | Rapid Housing Initiative 2 | Sumas First Nation | 3/27/2023 | New Construction | Indigenous Governing Body | $ 1,504,555.00 | $ 1,504,555.00 | $ - | Built | 49.1256 | -122.195997 |
Abbotsford | British Columbia | Sumas Village Homes - Building D and E | 6 | 6 | 0 | Rapid Housing Initiative 2 | Sumas First Nation | 3/27/2023 | New Construction | Indigenous Governing Body | $ 863,726.00 | $ 863,726.00 | $ - | Built | 49.1256 | -122.195997 |
Abbotsford | British Columbia | Elliott House | 60 | 30 | 0 | National Housing Co-Investment Fund | Connective Support Society | 10/24/2022 | New Construction | Not-for-profit housing org/Co-op | $ 138,128.00 | $ 138,128.00 | $ - | Built | 49.0457 | -122.2860453 |
Afton | Nova Scotia | Paqtnkek "What does a home feel like"? | 12 | 12 | 12 | Rapid Housing Initiative | Paqtnkek Mi'kmaw Nation | 4/16/2021 | New Construction | Indigenous Group | $ 1,020,000.00 | $ 1,020,000.00 | $ - | Built | 45.6012 | -61.737941 |
Ajax | Ontario | Bayly Square Phasse 2 | 551 | 121 | 83 | Rental Construction Financing Initiative | Medallion Developments (Bayly Square) C Limited | 8/4/2021 | New Construction | Private Enterprise/Builder/Developer | $ 168,500,000.00 | $ - | $ 168,500,000.00 | Under Construction | 43.8433 | -79.0219334 |
Ajax | Ontario | Phase 1 of Vision at Pat Bayly Square | 308 | 308 | 49 | Rental Construction Financing Initiative | Medallion Corporation | 11/2/2019 | New Construction | Private Enterprise/Builder/Developer | $ 59,923,500.00 | $ - | $ 59,923,500.00 | Built | 43.8448 | -79.0141645 |
Alberni-Clayoquot A | British Columbia | Uchucklesaht Tribe Government Housing Replacement Project | 8 | 8 | 0 | Rapid Housing Initiative | Uchucklesaht Tribe Government | 5/14/2021 | New Construction | Indigenous Group | $ 3,301,260.00 | $ 3,301,260.00 | $ - | Built | 49.0040 | -124.991681 |
Alert Bay | British Columbia | Namgis: Affordable Rental Housing Project 2021-2022 | 8 | 8 | 0 | Rapid Housing Initiative 2 | Namgis First Nation | 5/9/2023 | New Construction | Indigenous Governing Body | $ 2,070,323.17 | $ 2,070,323.17 | $ - | Built | 50.5826 | -126.925313 |
Allison Bay 219 | Alberta | Allison Bay Ten Tiny Homes Village Project | 10 | 10 | 0 | Rapid Housing Initiative 2 | Mikisew Cree First Nation | 2/16/2023 | New Construction | Indigenous Governing Body | $ 2,535,416.10 | $ 2,535,416.10 | $ - | Under Construction | 58.7196 | -111.140697 |
Anacla 12 | British Columbia | Huuayaht Indigenous Citizen Housing | 11 | 0 | 0 | Rapid Housing Initiative | Huu-ay-aht First Nations | 5/14/2021 | New Construction | Indigenous Group | $ 3,622,138.00 | $ 3,622,138.00 | $ - | Built | 48.8030 | -125.1189262 |
Antigonish | Nova Scotia | Appleseed Drive Build | 12 | 15 | 4 | National Housing Co-Investment Fund | Antigonish Affordable Housing Society | 7/19/2022 | New Construction | Not-for-profit housing org/Co-op | $ 2,329,251.00 | $ 721,000.00 | $ 1,608,251.00 | Built | 45.6167 | -62.0094137 |
Arctic Bay | Nunavut | Qikiqtani - Arctic Bay Single Family - High Arctic Affordable Housing Project | 1 | 1 | 0 | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,025,320.00 | $ 1,025,320.00 | $ - | Financial Commitments | 73.0351 | -85.172327 |
Arctic Bay | Nunavut | Qikiqtani - Arctic Bay Semi Detached - High Arctic Affordable Housing Project | 4 | 4 | 0 | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 3,214,938.00 | $ 3,214,938.00 | $ - | Financial Commitments | 73.0351 | -85.172327 |
Aylmer | Quebec | The British Square | 84 | 85 | 13 | Rental Construction Financing Initiative | Belmont Assets management | 6/2/2021 | New Construction | Private Enterprise/Builder/Developer | $ 24,630,000.00 | $ - | $ 24,630,000.00 | Built | 45.3952 | -75.8472517 |
Banff | Alberta | YWCA of Banff Affordable Housing Courtyard Project | 51 | 33 | 5 | National Housing Co-Investment Fund | YWCA of Banff | 10/23/2018 | New Construction | Not-for-profit housing org/Co-op | $ 5,400,000.00 | $ - | $ 5,400,000.00 | Built | 51.1716 | -115.5690429 |
Barrie | Ontario | Transitional Housing | 12 | 12 | 4 | National Housing Co-Investment Fund | Redwood Park Communities Inc. | 10/13/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,372,200.00 | $ 1,372,200.00 | $ - | Built | 44.4044 | -79.720852 |
Barrie | Ontario | Dunlop Street West Apartments | 94 | 86 | 27 | Rental Construction Financing Initiative | MUSKOKA D & M CORP. | 5/28/2021 | New Construction | Private Enterprise/Builder/Developer | $ 25,950,000.00 | $ - | $ 25,950,000.00 | Built | 44.3842 | -79.7014031 |
Barrie | Ontario | Allanview Place | 11 | 11 | 10 | National Housing Co-Investment Fund | The Barrie Municipal Non Profit Housing Corporation | 4/24/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,605,279.00 | $ 705,279.00 | $ 1,900,000.00 | Under Construction | 44.3621 | -79.6839329 |
Barrie | Ontario | Allanview Place | 23 | 23 | 0 | National Housing Co-Investment Fund | The Barrie Municipal Non Profit Housing Corporation | 4/24/2019 | Repairs | Not-for-profit housing org/Co-op | $ 250,736.00 | $ 100,736.00 | $ 150,000.00 | Under Construction | 44.3621 | -79.6839329 |
Beardy's and Okemasis 96 and 97B | Saskatchewan | Humble Homes Beardy's Okemasis | 14 | 0 | 0 | Rapid Housing Initiative | Beardy's and Okemasis First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 3,607,164.90 | $ 3,607,164.90 | $ - | Built | 52.8159 | -106.223105 |
Bedford | Nova Scotia | Northwoodcare Realty Incorporated | 73 | 73 | 8 | Rental Construction Financing Initiative | Northwoodcare Realty Inc. | 2/28/2020 | New Construction | Not-for-profit housing org/Co-op | $ 14,754,000.00 | $ - | $ 14,754,000.00 | Built | 44.7231 | -63.7068666 |
Behchokò | Northwest Territories | (M) Habitat for Humanity NWT 10 unit Portfolio | 10 | 10 | 2 | National Housing Co-Investment Fund | HABITAT FOR HUMANITY - NORTH WEST TERRITORIES | 5/27/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,437,000.00 | $ 3,437,000.00 | $ - | Under Construction | 62.4423 | -114.411015 |
Belleville | Ontario | POQ apartments | 7 | 5 | 0 | National Housing Co-Investment Fund | The Pentecostals of Quinte | 1/11/2023 | New Construction | Faith-based organization | $ 64,279.00 | $ 64,279.00 | $ - | Built | 44.1466 | -77.4145079 |
Belleville | Ontario | KGF Capital Realty | 103 | 104 | 15 | Rental Construction Financing Initiative | KGF Capital Realty | 5/27/2021 | New Construction | Private Enterprise/Builder/Developer | $ 23,000,000.00 | $ - | $ 23,000,000.00 | Built | 44.1746 | -77.378688 |
Bertrand | New Brunswick | Nouveaux logements abordables à Bertrand | 5 | 5 | 1 | National Housing Co-Investment Fund | LES RESIDENCES LEONCE MARSOLIAU DE BERTRAND INC. | 5/25/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,095,540.53 | $ 412,071.66 | $ 683,469.00 | Under Construction | 47.7488 | -65.07588 |
Big Horn 144A | Alberta | Wesley First Nation - 2021 - Bighorn Modular Project | 5 | 5 | - | Rapid Housing Initiative 2 | Wesley First Nation | 2/3/2023 | New Construction | Indigenous Governing Body | $ 1,034,650.00 | $ 1,034,650.00 | $ - | Built | 52.4680 | -116.081488 |
Big Lakes County | Alberta | EPMS RHI 2 | 12 | 12 | - | Rapid Housing Initiative 2 | East Prairie Metis Settlement | 4/27/2023 | New Construction | Indigenous Governing Body | $ 4,180,034.66 | $ 4,180,034.66 | $ - | Under Construction | 55.4330 | -116.488177 |
Blood 148 | Alberta | Blood Tribe Rehabilitation Project | 50 | 50 | - | Rapid Housing Initiative | Blood Tribe | 4/21/2023 | Renewals | Indigenous Group | $ 4,192,000.00 | $ 4,192,000.00 | $ - | Built | 49.4680 | -113.30541 |
Bonnyville No. 87 | Alberta | Shelter | 30 | - | - | Rapid Housing Initiative | Fishing Lake Metis Settlement | 4/28/2023 | New Construction | Indigenous Group | $ 5,171,125.00 | $ 5,171,125.00 | $ - | Built | 54.2681 | -110.73028 |
Bowan Island | British Columbia | Â 510 Bowen Island Trunk Road | 27 | 13 | 7 | Rental Construction Financing Initiative | Bandon Holdings Limited Partnership | 10/13/2023 | New Construction | Private Enterprise/Builder/Developer | $ 8,750,000.00 | $ - | $ 8,750,000.00 | Built | 49.4164 | -123.319801 |
Bradford West Gwillimbury | Ontario | County of Simcoe - City Stream | 32 | 32 | - | Rapid Housing Initiative 3 | The Corporation of the County of Simcoe | 6/1/2023 | New Construction | Municipality | $ 8,621,715.00 | $ 8,621,715.00 | $ - | Financial Commitments | 44.1115 | -79.562196 |
Brampton | Ontario | Mount Pleasant Village | 302 | 71 | 46 | Rental Construction Financing Initiative | Daniels Choice Mount Pleasant Corporation | 7/19/2021 | New Construction | Private Enterprise/Builder/Developer | $ 120,000,000.00 | $ - | $ 120,000,000.00 | Under Construction | 43.6724 | -79.8297694 |
Brampton | Ontario | Stream A Peel Region Comfort Inn Acquisition and Conversion | 67 | 67 | - | Rapid Housing Initiative | The Regional Municipality of Peel | 6/25/2021 | Repairs | Municipality | $ 30,394,076.00 | $ 30,394,076.00 | $ - | Under Construction | 43.7315 | -79.762418 |
Brampton | Ontario | BBCFR 6-storey Affordable Housing Building | 90 | 45 | 2 | National Housing Co-Investment Fund | Brampton Bramalea Christian Fellowship Residences Ltd. | 4/22/2019 | New Construction | Not-for-profit housing org/Co-op | $ 15,491,775.00 | $ 750,000.00 | $ 14,741,775.00 | Built | 43.7691 | -79.7775177 |
Brampton/Missisauga/Caledon | Ontario | Shelter | 2180 | 813 | - | National Housing Co-Investment Fund | Peel Housing Corporation (PHC) | 8/7/2020 | New Construction | Not-for-profit housing org/Co-op | $ 276,368,753.00 | $ 89,474,127.00 | $ 186,894,626.00 | Under Construction | 43.7315 | -79.7624 |
Brandon | Manitoba | John Howard Society of Brandon (in partnership with Westman Youth for Christ) Transitional Housing Project | 24 | - | - | Rapid Housing Initiative 3 | City of Brandon | 5/30/2023 | New Construction | Municipality | $ 5,000,000.00 | $ 5,000,000.00 | $ - | Financial Commitments | 49.8562 | -99.959246 |
Brandon | Manitoba | Common Space | 30 | 30 | 8 | National Housing Co-Investment Fund | Brandon and Area Youth for Christ, Inc. | 3/31/2021 | New Construction | Faith-based organization | $ 3,311,250.00 | $ 880,000.00 | $ 2,431,250.00 | Built | 49.8454 | -99.9476887 |
Bridge River 1 | British Columbia | XwÃsten (Five-plex) | 5 | 5 | - | Rapid Housing Initiative 2 | Bridge River Indian Band | 3/22/2023 | New Construction | Indigenous Governing Body | $ 1,674,000.00 | $ 1,674,000.00 | $ - | Built | 50.4711 | -121.5838 |
Burnaby | British Columbia | 6889 Royal Oak | 134 | 134 | 27 | National Housing Co-Investment Fund | Catalyst Community Developments Society | 3/14/2023 | New Construction | Not-for-profit housing org/Co-op | $ 49,000,529.00 | $ 10,050,000.00 | $ 38,950,529.00 | Under Construction | 49.2212 | -122.9891356 |
Burnaby | British Columbia | Shelter | 203 | 96 | 41 | National Housing Co-Investment Fund | Catalyst Community Developments Society | 3/14/2023 | New Construction | Not-for-profit housing org/Co-op | $ 63,948,358.00 | $ 15,225,000.00 | $ 48,723,358.00 | Under Construction | 49.2432 | -122.9741895 |
Burnaby | British Columbia | Aunt Leah's House Redevelopment | 5 | 5 | - | National Housing Co-Investment Fund | Aunt Leah's Foundation | 1/12/2023 | New Construction | Not-for-profit housing org/Co-op | $ 416,748.00 | $ 416,748.00 | $ - | Built | 49.2419 | -123.0232063 |
Burnaby | British Columbia | 8305 11th - Cities Stream | 28 | - | - | Rapid Housing Initiative 2 | City of Burnaby | 11/16/2021 | New Construction | Municipality | $ 11,043,309.00 | $ 11,043,309.00 | $ - | Under Construction | 49.2259 | -122.917723 |
Burnaby | British Columbia | Kathleen | 324 | 101 | 92 | National Housing Co-Investment Fund | Bosa4Rent Metrotown Inc. | 4/16/2021 | New Construction | Private Enterprise/Builder/Developer | $ 100,173,200.00 | $ 2,671,200.00 | $ 97,502,000.00 | Under Construction | 49.2294 | -123.0072568 |
Calgary | Alberta | Shelter | 252 | 117 | - | Innovation Fund | Kanas Corporation | 11/22/2018 | New Construction | Private Enterprise/Builder/Developer | $ 2,000,000.00 | $ - | $ 2,000,000.00 | Under Construction | 51.0447 | -114.0719 |
Calgary | Alberta | Shelter | 19 | 19 | - | Rapid Housing Initiative 2 | Calgary Young Women's Christian Association | 1/25/2023 | New Construction | Not-for-profit housing org/Co-op | $ 7,105,280.00 | $ 7,105,280.00 | $ - | Under Construction | 51.0447 | -114.0719 |
Calgary | Alberta | Shelter | 80 | - | 16 | National Housing Co-Investment Fund | Calgary Young Women's Christian Association | 1/25/2023 | New Construction | Not-for-profit housing org/Co-op | $ 10,461,425.00 | $ 10,461,425.00 | $ - | Under Construction | 51.0447 | -114.0719 |
Calgary | Alberta | Livingston Terrace/ Silvera/ The City of Calgary/ Projects Stream | 41 | 35 | - | Rapid Housing Initiative 2 | The City of Calgary | 9/3/2022 | New Construction | Municipality | $ 7,037,323.51 | $ 7,037,323.51 | $ - | Under Construction | 51.1842 | -114.0528309 |
Calgary | Alberta | Seton Project (AB) | 45 | 45 | 14 | National Housing Co-Investment Fund | HomeSpace Society | 8/10/2022 | New Construction | Not-for-profit housing org/Co-op | $ 8,673,116.00 | $ 1,463,063.00 | $ 7,210,053.00 | Under Construction | 50.8779 | -113.9565059 |
Calgary | Alberta | Horizon South - Affordable Rental Homes in Currie | 72 | 72 | 15 | Federal Lands Initiative | Horizon Housing Society | 4/1/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,509,420.00 | $ 3,509,420.00 | $ - | Under Construction | 51.0202 | -114.1236227 |
Calgary | Alberta | Silvera for Seniors - Glamorgan Affordable Housing Project for Seniors | 200 | 200 | 9 | National Housing Co-Investment Fund | Silvera for Seniors | 3/9/2022 | New Construction | Not-for-profit housing org/Co-op | $ 15,204,041.00 | $ 656,250.00 | $ 14,547,791.00 | Under Construction | 51.0092 | -114.1562543 |
Calgary | Alberta | Sierra/ Cities Stream/ The City of Calgary | 82 | 82 | - | Rapid Housing Initiative 2 | The City of Calgary | 1/26/2022 | Repairs | Municipality | $ 16,588,794.00 | $ 16,588,794.00 | $ - | Built | 51.0470 | -114.0766468 |
Calgary | Alberta | Sunalta Heights | 207 | 207 | 21 | Rental Construction Financing Initiative | Housing One 10th Avenue Corp | 6/16/2021 | New Construction | Private Enterprise/Builder/Developer | $ 74,700,000.00 | $ - | $ 74,700,000.00 | Under Construction | 51.0444 | -114.0963925 |
Calgary | Alberta | Beltline 2 | 51 | 50 | 11 | National Housing Co-Investment Fund | HomeSpace Society | 6/4/2021 | New Construction | Not-for-profit housing org/Co-op | $ 6,656,924.00 | $ 847,500.00 | $ 5,809,424.00 | Built | 51.0384 | -114.0877764 |
Calgary | Alberta | Columbus Court | 104 | 104 | 14 | Rental Construction Financing Initiative | Forward Housing Association | 4/15/2021 | New Construction | Not-for-profit housing org/Co-op | $ 16,000,000.00 | $ - | $ 16,000,000.00 | Built | 51.0502 | -114.0336357 |
Calgary | Alberta | Templemont | 120 | 120 | 85 | National Housing Co-Investment Fund | Trinity Place Foundation of Alberta | 4/7/2021 | New Construction | Not-for-profit housing org/Co-op | $ 13,164,000.00 | $ 2,518,000.00 | $ 10,646,000.00 | Under Construction | 51.0934 | -113.9520688 |
Calgary | Alberta | Downtown 5 Avenue Site | 74 | 74 | 16 | National Housing Co-Investment Fund | HomeSpace Society | 2/16/2021 | New Construction | Not-for-profit housing org/Co-op | $ 9,770,000.00 | $ 5,000,000.00 | $ 4,770,000.00 | Built | 51.0488 | -114.0828286 |
Calgary | Alberta | Shelter | 33 | 33 | - | Rapid Housing Initiative | The City of Calgary | 12/17/2020 | Repairs | Municipality | $ 8,296,500.00 | $ 8,296,500.00 | $ - | Built | 51.0447 | -114.0719 |
Calgary | Alberta | Stream A Calgary - HomeSpace - 2404 50 St SE | 25 | 25 | - | Rapid Housing Initiative | The City of Calgary | 12/17/2020 | Renewals | Municipality | $ 800,000.00 | $ 800,000.00 | $ - | Built | 51.0331 | -113.9608525 |
Calgary | Alberta | Stream A Calgary - Silvera: Lakeview Hotel Conversion | 120 | 120 | - | Rapid Housing Initiative | The City of Calgary | 12/17/2020 | Repairs | Municipality | $ 15,503,500.00 | $ 15,503,500.00 | $ - | Built | 51.0894 | -113.9989193 |
Calgary | Alberta | Truman Homes | 96 | 28 | 10 | Rental Construction Financing Initiative | Mulberry 77 Street Inc. | 11/2/2020 | New Construction | Private Enterprise/Builder/Developer | $ 24,500,000.00 | $ - | $ 24,500,000.00 | Built | 51.0642 | -114.1996259 |
Calgary | Alberta | Pineridge | 65 | 65 | 7 | Rental Construction Financing Initiative | Horizon Housing Society | 10/16/2020 | New Construction | Not-for-profit housing org/Co-op | $ 15,025,000.00 | $ - | $ 15,025,000.00 | Built | 51.0753 | -113.9388057 |
Calgary | Alberta | Centre 4800 | 79 | 79 | 8 | National Housing Co-Investment Fund | Calgary Drop-In & Rehab Centre Society | 7/16/2019 | New Construction | Not-for-profit housing org/Co-op | $ 8,784,626.00 | $ 3,773,207.00 | $ 5,011,419.00 | Built | 51.0950 | -114.0537044 |
Calgary | Alberta | YW Calgary Hub Facility | 100 | 100 | 20 | National Housing Co-Investment Fund | Calgary Young Women's Christian Association | 1/22/2019 | New Construction | Not-for-profit housing org/Co-op | $ 4,742,981.00 | $ 4,742,981.00 | $ - | Built | 51.0377 | -114.0220082 |
Calgary | Alberta | Horizon Housing Society project | 161 | 161 | 17 | Rental Construction Financing Initiative | Horizon Housing Society | 6/28/2018 | New Construction | Not-for-profit housing org/Co-op | $ 13,561,000.00 | $ - | $ 13,561,000.00 | Built | 51.0753 | -113.9388057 |
Cambridge | Ontario | Kirkwood Apartments phase 2 | 21 | 11 | - | National Housing Co-Investment Fund | Ayr and District Citizens Association | 8/6/2022 | New Construction | Not-for-profit housing org/Co-op | $ 2,072,049.00 | $ 309,431.00 | $ 1,762,618.00 | Built | 43.2854 | -80.4468312 |
Cambridge | Ontario | 195 Hespeler Road | 55 | 17 | 2 | National Housing Co-Investment Fund | Home Concept Property Management | 8/2/2022 | New Construction | Municipality | $ 11,699,429.00 | $ 1,625,261.00 | $ 10,074,168.00 | Under Construction | 43.3835 | -80.319588 |
Cambridge | Ontario | KWUNWP | 30 | - | - | Rapid Housing Initiative 2 | The Regional Municipality of Waterloo | 1/28/2022 | New Construction | Municipality | $ 2,548,717.00 | $ 2,548,717.00 | $ - | Under Construction | 43.3618 | -80.312404 |
Cambridge | Ontario | Stream A Waterloo - Bechtel Alternative Housing | 6 | 6 | - | Rapid Housing Initiative | The Regional Municipality of Waterloo | 12/16/2020 | New Construction | Municipality | $ 1,333,677.00 | $ 1,333,677.00 | $ - | Built | 43.4226 | -80.319307 |
Campbell River | British Columbia | Linda's Place | 27 | 27 | 6 | National Housing Co-Investment Fund | The Westcoast Native Health Care Society Campbell River Head Injury Support Society | 4/15/2019 | New Construction | Not-for-profit housing org/Co-op | $ 830,000.00 | $ 830,000.00 | $ - | Built | 50.0228 | -125.247095 |
Cape Breton | Nova Scotia | Ainsley Street Sydney NS | 5 | - | - | Rapid Housing Initiative 2 | Cape Breton Community Housing Association | 5/23/2023 | New Construction | Not-for-profit housing org/Co-op | $ 1,507,038.00 | $ 1,507,038.00 | $ - | Under Construction | 46.1348 | -60.19208 |
Cape Breton | Nova Scotia | 2020-21 RHI 10 3-bedroom Unit Project | 10 | 10 | - | Rapid Housing Initiative 2 | Eskasoni | 5/23/2023 | New Construction | Indigenous Governing Body | $ 1,619,049.26 | $ 1,619,049.26 | $ - | Under Construction | 45.9288 | -60.638024 |
Cape Breton | Nova Scotia | New Dawn - Harm Reduction Supportive Housing in CBRM - | 24 | 20 | - | Rapid Housing Initiative 3 | CAPE BRETON REGIONAL MUNICIPALITY | 5/23/2023 | New Construction | Municipality | $ 5,000,000.00 | $ 5,000,000.00 | $ - | Financial Commitments | 46.1429 | -60.197591 |
Cape Breton | Nova Scotia | Parkview Seniors Complex - Phase 2 | 22 | 22 | 5 | National Housing Co-Investment Fund | Future Growth Cooperative Ltd. | 3/17/2023 | New Construction | Not-for-profit housing org/Co-op | $ 2,299,145.00 | $ 449,145.00 | $ 1,850,000.00 | Under Construction | 46.2485 | -60.2215686 |
Cape Breton | Nova Scotia | A Plan to End Homelessness in CBRM | 20 | - | 14 | National Housing Co-Investment Fund | Cape Breton Community Housing Association | 8/9/2019 | New Construction | Not-for-profit housing org/Co-op | $ 858,209.00 | $ 463,209.00 | $ 395,000.00 | Built | 46.1347 | -60.192064 |
Capilano 5 | British Columbia | Xwmelch'stn Affordable Housing Project | 95 | 95 | 19 | National Housing Co-Investment Fund | HIYAM TA SKWXWU7MESH HOUSING SOCIETY | 8/4/2023 | New Construction | Indigenous Non-Profit Organization | $ 4,429,393.00 | $ 4,429,393.00 | $ - | Built | 49.3220 | -123.124983 |
Capilano 5 | British Columbia | Capilano Modular Rapid Housing Project | 50 | 55 | - | Rapid Housing Initiative 2 | Squamish Nation | 2/2/2022 | New Construction | Indigenous Governing Body | $ 17,048,512.27 | $ 17,048,512.27 | $ - | Under Construction | 49.3239 | -123.121323 |
Carcross | Yukon | C/TFN Rapid Housing for the Homeless Project | 10 | - | - | Rapid Housing Initiative | Carcross Tagish First Nation | 6/25/2021 | New Construction | Indigenous Group | $ 2,469,346.51 | $ 2,469,346.51 | $ - | Built | 60.1646 | -134.707709 |
Castlegar | British Columbia | Eagle Estates | 13 | 5 | 4 | National Housing Co-Investment Fund | Kootenay Society For Community Living | 7/20/2023 | New Construction | Not-for-profit housing org/Co-op | $ 650,000.00 | $ 650,000.00 | $ - | Under Construction | 49.3275 | -117.664849 |
Chambly | Quebec | Maison Simonne-Monet-Chartrand RHI2 | 15 | 15 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,900,000.00 | $ 4,900,000.00 | $ - | Under Construction | 45.4686 | -73.288726 |
Chandler | Quebec | SHQ - Habitations des Aînés de Chandler | 30 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,625,000.00 | $ 1,625,000.00 | $ - | Built | 48.3436 | -64.6806245 |
Charlottetown | Prince Edward Island | City of Charlottetown RHI | 82 | - | - | Rapid Housing Initiative 3 | City of Charlottetown | 7/12/2023 | New Construction | Municipality | $ 5,000,000.00 | $ 5,000,000.00 | $ - | Financial Commitments | 46.2900 | -63.171333 |
Charlottetown | Prince Edward Island | Accessible Home Complex | 10 | 10 | 7 | National Housing Co-Investment Fund | Queens County Residential Services Inc. | 7/13/2022 | New Construction | Not-for-profit housing org/Co-op | $ 971,700.00 | $ 101,275.00 | $ 870,425.00 | Built | 46.2545 | -63.1703407 |
Charlottetown | Prince Edward Island | 203 Fitzroy | 28 | 20 | - | Rapid Housing Initiative 2 | Canadian Mental Health Association Prince Edward Island Division | 4/25/2022 | New Construction | Not-for-profit housing org/Co-op | $ 7,857,996.80 | $ 7,857,996.80 | $ - | Built | 46.2395 | -63.1251008 |
Charlottetown | Prince Edward Island | Kensington Road Apartment Development | 60 | 60 | 16 | Rental Construction Financing Initiative | 11350102 Canada Inc. | 7/19/2021 | New Construction | Private Enterprise/Builder/Developer | $ 12,900,000.00 | $ - | $ 12,900,000.00 | Built | 46.2497 | -63.1165807 |
Charlottetown | Prince Edward Island | Kensington Road Apartment Development | 30 | 30 | 8 | Rental Construction Financing Initiative | 11350102 Canada Inc. | 7/19/2021 | New Construction | Private Enterprise/Builder/Developer | $ 6,317,000.00 | $ - | $ 6,317,000.00 | Built | 46.2497 | -63.1165807 |
Charlottetown | Prince Edward Island | Geneva Place | 60 | 60 | 6 | Rental Construction Financing Initiative | Geneva Place Inc. | 3/18/2021 | New Construction | Private Enterprise/Builder/Developer | $ 13,746,000.00 | $ - | $ 13,746,000.00 | Built | 46.2335 | -63.1215415 |
Charlottetown | Prince Edward Island | Martha Place | 60 | 50 | 18 | National Housing Co-Investment Fund | Kings Square Affordable Housing Corporation | 7/29/2019 | New Construction | Not-for-profit housing org/Co-op | $ 11,885,056.00 | $ 905,730.00 | $ 10,979,326.00 | Built | 46.2598 | -63.0960872 |
Châteauguay | Quebec | Conversion d’un hôtel sur la Rive-sud de Montréal RHI2 | 31 | 31 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 6,000,000.00 | $ 6,000,000.00 | $ - | Under Construction | 45.3682 | -73.71032 |
Châteauguay | Quebec | SHQ - Élan des jeunes | 6 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Renewals | Province | $ 423,667.00 | $ 423,667.00 | $ - | Built | 45.3604 | -73.7269632 |
Chatham-Kent | Ontario | Villaview Seniors | 13 | 7 | 3 | National Housing Co-Investment Fund | Villaview Community Corporation | 8/29/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,834,857.00 | $ 370,073.00 | $ 1,464,784.00 | Built | 42.5952 | -82.3809234 |
Chatham-Kent | Ontario | Shelter | 27 | 27 | - | Rapid Housing Initiative 2 | Municipality of Chatham Kent | 12/16/2021 | New Construction | Municipality | $ 4,988,687.00 | $ 4,988,687.00 | $ - | Under Construction | 42.4078 | -82.191 |
Chelsea | Quebec | SHQ - Corporation d'Habitation de Chelsea | 12 | - | - | Rapid Housing Initiative | Société d'habitation du Québec SHQ | 1/22/2021 | New Construction | Province | $ 300,000.00 | $ 300,000.00 | $ - | Financial Commitments | 45.5920 | -75.88522 |
Chiliwack | British Columbia | Webb Avenue Apartments | 67 | 25 | 7 | Rental Construction Financing Initiative | 0993829 BC Ltd. | 1/25/2019 | New Construction | Private Enterprise/Builder/Developer | $ 11,800,000.00 | $ - | $ 11,800,000.00 | Built | 49.1344 | -121.9576008 |
Chilliwack | British Columbia | Shelter | 7 | 7 | - | National Housing Co-Investment Fund | Xolhemet Society - Wilma's Transition Society | 7/28/2022 | Repairs | Indigenous Group | $ 757,260.00 | $ 757,260.00 | $ - | Under Construction | 49.1579 | -121.9515 |
Chilliwack | British Columbia | Shelter | 18 | 18 | - | National Housing Co-Investment Fund | Xolhemet Society - Wilma's Transition Society | 7/28/2022 | New Construction | Indigenous Non-Profit Organization | $ 10,175,272.00 | $ 1,843,827.00 | $ 8,331,445.00 | Under Construction | 49.1579 | -121.9515 |
Chilliwack | British Columbia | The Locale | 28 | 28 | 28 | Rental Construction Financing Initiative | Karvin Properties LLP | 1/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 5,000,000.00 | $ - | $ 5,000,000.00 | Built | 49.1689 | -121.9616233 |
Chippewas of the Thames First Nation 42 | Ontario | Chippewas of the Thames First Nation Housing Six | 6 | - | - | Rapid Housing Initiative | Chippewas of the Thames First Nation | 4/13/2021 | New Construction | Indigenous Group | $ 1,799,245.00 | $ 1,799,245.00 | $ - | Built | 42.8118 | -81.4621825 |
Chisasibi | Quebec | Portfolio Cree - Chisasibi | 10 | 30 | - | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 3,167,110.00 | $ 3,167,110.00 | $ - | Built | 53.7736 | -78.893467 |
Clearwater River Dene 222 | Saskatchewan | Clearwater River Dene Nation - 20 Unit Affordable Housing Project | 20 | 20 | - | Rapid Housing Initiative 2 | Clearwater River Dene Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 1,452,000.00 | $ 1,452,000.00 | $ - | Built | 56.5288 | -109.474507 |
Clinton | British Columbia | 300 Smith Ave | 20 | 20 | 20 | National Housing Co-Investment Fund | Clinton and District Assisted Living Society | 11/24/2021 | New Construction | Not-for-profit housing org/Co-op | $ 721,056.00 | $ 721,056.00 | $ - | Built | 51.0894 | -121.5885365 |
Clyde River | Nunavut | Qikiqtani - Clyde River Single Family - High Arctic Affordable Housing Project | 1 | 1 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,025,320.00 | $ 1,025,320.00 | $ - | Financial Commitments | 70.4697 | -68.5991 |
Clyde River | Nunavut | Qikiqtani - Clyde River Semi Detached - High Arctic Affordable Housing Project | 4 | 4 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 3,214,938.00 | $ 3,214,938.00 | $ - | Financial Commitments | 70.4697 | -68.5991 |
Cobourg | Ontario | Northumberland County Housing Corporation (NCHC) – Elgin Park Redevelopment Project | 40 | 28 | 8 | National Housing Co-Investment Fund | Corporation of the County of Northumberland | 8/16/2022 | New Construction | Municipality | $ 2,400,000.00 | $ 2,400,000.00 | $ - | Built | 43.9794 | -78.163206 |
Coquitlam | British Columbia | Dogwood | 126 | 94 | 13 | Rental Construction Financing Initiative | Marcon Dogwood Limited Partnership | 10/11/2023 | New Construction | Private Enterprise/Builder/Developer | $ 50,350,000.00 | $ - | $ 50,350,000.00 | Under Construction | 49.2612 | -122.883536 |
Coquitlam | British Columbia | Meridian | 267 | 267 | 33 | Rental Construction Financing Initiative | Townline Cottonwood Holdings Ltd. | 10/11/2023 | New Construction | Private Enterprise/Builder/Developer | $ 121,442,000.00 | $ - | $ 121,442,000.00 | Under Construction | 49.2590 | -122.892443 |
Coquitlam | British Columbia | Ozada Pinetree Court Family Housing Project | 164 | 164 | 35 | National Housing Co-Investment Fund | Affordable Housing Management Association. | 3/7/2022 | New Construction | Not-for-profit housing org/Co-op | $ 46,167,519.00 | $ 1,888,074.00 | $ 44,279,445.00 | Under Construction | 49.2854 | -122.784031 |
Coquitlam | British Columbia | Burquitlam Park Rental Tower | 308 | 222 | 31 | Rental Construction Financing Initiative | Concert Properties | 7/21/2021 | New Construction | Private Enterprise/Builder/Developer | $ 109,000,000.00 | $ - | $ 109,000,000.00 | Built | 49.2620 | -122.8866162 |
Courtenay | British Columbia | Naut'sa mawt | 40 | 25 | 9 | National Housing Co-Investment Fund | Wachiay Friendship Centre Society | 5/4/2023 | New Construction | Indigenous Non-Profit Organization | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Under Construction | 49.6819 | -124.998833 |
Dartmouth | Nova Scotia | The Terrace of Kings Grove | 148 | 148 | 24 | Rental Construction Financing Initiative | The Armour Group Holdings Limited | 5/28/2021 | New Construction | Private Enterprise/Builder/Developer | $ 44,600,000.00 | $ - | $ 44,600,000.00 | Built | 44.6858 | -63.5630266 |
Dawson | Yukon | Shelter | 10 | 10 | 6 | National Housing Co-Investment Fund | Tr’ondëk Hwëch’in | 5/31/2023 | New Construction | Indigenous Group | $ 4,930,000.00 | $ 4,930,000.00 | $ - | Built | 64.0599 | -139.411 |
Debden | Saskatchewan | Big River First Nation Housing Project | 10 | - | - | Rapid Housing Initiative | Big River First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 1,062,174.52 | $ 1,062,174.52 | $ - | Built | 58.4407 | -104.7892743 |
Deer Lake | Ontario | Deer Lake First Nation Community Safe House Village | 25 | - | - | Rapid Housing Initiative | Deer Lake First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 6,466,000.00 | $ 6,466,000.00 | $ - | Financial Commitments | 51.8042 | -93.992708 |
Déline | Northwest Territories | Deline Got'ine Government Housing Project | 10 | 10 | - | Rapid Housing Initiative 2 | Deline Got'ine Government | 5/24/2022 | Repairs | Indigenous Group | $ 2,674,589.26 | $ 2,674,589.26 | $ - | Under Construction | 65.1876 | -123.424983 |
Delta | British Columbia | Affordable Evergreen | 130 | 130 | 38 | National Housing Co-Investment Fund | Affordable Housing Non Profit Rental Association | 10/28/2022 | New Construction | Not-for-profit housing org/Co-op | $ 34,705,359.00 | $ 4,020,858.00 | $ 30,684,501.00 | Under Construction | 49.0870 | -123.0814813 |
Denare Beach | Saskatchewan | PBCN Denare Beach | 3 | 3 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 771,727.50 | $ 771,727.50 | $ - | Under Construction | 54.6490 | -102.08467 |
Detah | Northwest Territories | YKDFN Submission | 19 | 19 | - | National Housing Co-Investment Fund | Yellowknives Dene First Nation | 5/31/2021 | New Construction | Indigenous Group | $ 18,855,021.00 | $ 18,855,021.00 | $ - | Built | 62.4394 | -114.36171 |
Deux-Montagnes | Quebec | SHQ - Coopérative de solidarité du train de la vie | 35 | 23 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 5,800,750.00 | $ 5,800,750.00 | $ - | Under Construction | 45.5513 | -73.8951242 |
Dog Creek 46 | Manitoba | Shelter | 10 | 10 | 10 | National Housing Co-Investment Fund | Lake Manitoba | 6/15/2023 | New Construction | Indigenous Group | $ 3,815,838.00 | $ 3,815,838.00 | $ - | Under Construction | 50.9165 | -98.5815 |
Drummondville | Quebec | Îlot de solidarité RHI2 | 23 | 23 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,488,000.00 | $ 3,488,000.00 | $ - | Built | 45.9023 | -72.475479 |
Duncan | British Columbia | Sustainable Housing for the Future of Cowichan Tribes | 32 | - | - | Rapid Housing Initiative | Cowichan Tribes | 5/21/2021 | New Construction | Indigenous Group | $ 4,016,683.44 | $ 4,016,683.44 | $ - | Built | 48.7828 | -123.70787 |
Eagle Lake 27 | Ontario | Eagle Lake First Nation - 10 New Homes | 10 | - | - | Rapid Housing Initiative | Eagle Lake First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 2,680,707.00 | $ 2,680,707.00 | $ - | Built | 49.7385 | -93.0568994 |
East Angus | Quebec | SHQ - Han-Logement 4 | 8 | 8 | - | Rapid Housing Initiative | Société d'habitation du Québec | 5/31/2022 | New Construction | Province | $ 360,000.00 | $ 360,000.00 | $ - | Built | 45.4962 | -71.642203 |
Eastmain | Quebec | Portfolio Cree - Eastmain | 5 | 10 | - | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,583,555.00 | $ 1,583,555.00 | $ - | Built | 52.2463 | -78.500426 |
Edmonton | Alberta | Holyrood Permanent Supportive Housing | 63 | - | - | Rapid Housing Initiative 3 | The City of Edmonton | 9/8/2023 | New Construction | Municipality | $ 12,533,074.00 | $ 12,533,074.00 | $ - | Financial Commitments | 53.5312 | -113.455473 |
Edmonton | Alberta | City of Edmonton Repairs | 1955 | 1,955 | 391 | National Housing Co-Investment Fund | The City of Edmonton | 4/20/2023 | Repairs | Municipality | $ 19,550,000.00 | $ 19,550,000.00 | $ - | Under Construction | 53.5670 | -113.517 |
Edmonton | Alberta | Homes for Heroes | 40 | 20 | - | Innovation Fund | Homes For Heroes Foundation | 11/25/2021 | New Construction | 0 | $ 1,000,000.01 | $ 1,000,000.01 | $ - | Under Construction | 53.5670 | -113.517 |
Edmonton | Alberta | Edgemont Apartments | 334 | 209 | 71 | National Housing Co-Investment Fund | 12621665 Canada Association | 6/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 79,354,787.00 | $ 4,134,463.00 | $ 75,220,324.00 | Under Construction | 53.4687 | -113.67671 |
Edmonton | Alberta | Grace Village | 175 | 175 | 175 | National Housing Co-Investment Fund | The Governing Council of The Salvation Army in Canada | 6/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 10,000,000.00 | $ 10,000,000.00 | $ - | Built | 53.6022 | -113.538231 |
Edmonton | Alberta | (Top-up) Heritage Valley Apartments phase 2 | - | - | National Housing Co-Investment Fund | 12621665 Canada Association | 6/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 4,343,315.00 | $ - | $ 4,343,315.00 | Under Construction | 53.4104 | -113.537778 | |
Edmonton | Alberta | Heritage Valley Apartments phase 2 | 169 | 85 | 42 | National Housing Co-Investment Fund | 12621665 Canada Association | 6/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 10,066,435.00 | $ 3,951,964.00 | $ 6,114,471.00 | Under Construction | 53.4104 | -113.537778 |
Edmonton | Alberta | Griesbach 2 Métis Capital Housing Corp | 127 | 127 | 42 | Federal Lands Initiative | Metis Capital Housing Corporation | 5/26/2022 | New Construction | Indigenous Group | $ 1,514,690.00 | $ 1,514,690.00 | $ - | Under Construction | 53.6054 | -113.5155241 |
Edmonton | Alberta | Griesbach 3 HomeEd | 85 | 43 | 36 | Federal Lands Initiative | The City of Edmonton Non Profit Housing Corporation | 5/26/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,480,050.00 | $ 1,480,050.00 | $ - | Under Construction | 53.6048 | -113.5137645 |
Edmonton | Alberta | Heritage Valley Apartments | 102 | 90 | 24 | National Housing Co-Investment Fund | 12621665 Canada Association | 3/15/2022 | New Construction | Not-for-profit housing org/Co-op | $ 19,226,119.00 | $ 1,098,391.00 | $ 18,127,728.00 | Built | 53.4049 | -113.5389467 |
Edmonton | Alberta | City of Edmonton - Days Inn - University Ave | 85 | - | - | Rapid Housing Initiative 2 | City of Edmonton | 1/12/2022 | Repairs | Municipality | $ 9,168,007.77 | $ 9,168,007.77 | $ - | Built | 53.5109 | -113.4964371 |
Edmonton | Alberta | City of Edmonton - Sands Hotel | 60 | - | - | Rapid Housing Initiative 2 | City of Edmonton | 1/12/2022 | Repairs | Municipality | $ 5,716,522.23 | $ 5,716,522.23 | $ - | Under Construction | 53.5802 | -113.4551468 |
Edmonton | Alberta | Riverview Residences | 248 | 87 | 25 | Rental Construction Financing Initiative | Riverview Crossing Residences GP Ltd. | 5/20/2021 | New Construction | Not-for-profit housing org/Co-op | $ 46,500,000.00 | $ - | $ 46,500,000.00 | Under Construction | 53.5713 | -113.3903687 |
Edmonton | Alberta | Inglewood Modular | 30 | 30 | - | Rapid Housing Initiative | City of Edmonton | 3/17/2021 | New Construction | Municipality | $ 5,981,603.00 | $ 5,981,603.00 | $ - | Under Construction | 53.5607 | -113.5354136 |
Edmonton | Alberta | Lauderdale Terrace | 37 | - | - | Rapid Housing Initiative | GEF Seniors Housing | 3/17/2021 | New Construction | Not-for-profit housing org/Co-op | $ 6,909,480.70 | $ 6,909,480.70 | $ - | Under Construction | 53.5876 | -113.496928 |
Edmonton | Alberta | Terrace Heights Modular | 46 | 46 | - | Rapid Housing Initiative | City of Edmonton | 3/17/2021 | New Construction | Municipality | $ 7,452,162.00 | $ 7,452,162.00 | $ - | Built | 53.5395 | -113.4297943 |
Edmonton | Alberta | Westmount Modular | 54 | 54 | - | Rapid Housing Initiative | City of Edmonton | 3/17/2021 | New Construction | Municipality | $ 651,585.00 | $ 651,585.00 | $ - | Under Construction | 53.5584 | -113.5457535 |
Edmonton | Alberta | Stream A Edmonton - King Edward Park Modular | 30 | 30 | - | Rapid Housing Initiative | City of Edmonton | 12/15/2020 | New Construction | Municipality | $ 9,043,883.00 | $ 9,043,883.00 | $ - | Under Construction | 53.5151 | -113.4728019 |
Edmonton | Alberta | Stream A Edmonton - McArthur / Wellington Modular | 50 | 50 | - | Rapid Housing Initiative | City of Edmonton | 12/15/2020 | New Construction | Municipality | $ 12,014,935.00 | $ 12,014,935.00 | $ - | Under Construction | 53.5988 | -113.5647125 |
Edmonton | Alberta | 787 Lewis Greens Dr. NW | 40 | 41 | 4 | Rental Construction Financing Initiative | Sierra Holdings (Alberta) Inc. | 7/25/2019 | New Construction | Private Enterprise/Builder/Developer | $ 9,700,000.00 | $ - | $ 9,700,000.00 | Built | 53.5313 | -113.6759174 |
Eel Ground 2 | New Brunswick | NSMDC Portfolio - Eel Ground | 4 | 4 | 4 | Rapid Housing Initiative | Eel Ground First Nation | 5/24/2023 | New Construction | Indigenous Group | $ 436,923.00 | $ 436,923.00 | $ - | Built | 46.9666 | -65.633723 |
Eel River 3 | New Brunswick | RHI 2021 Eel River Bar | 27 | - | - | Rapid Housing Initiative | Eel River Bar First Nation | 3/3/2023 | New Construction | Indigenous Group | $ 5,363,542.80 | $ 5,363,542.80 | $ - | Built | 48.0358 | -66.375189 |
Enderby 2 | British Columbia | Rapid Housing Initiative | 10 | - | - | Rapid Housing Initiative | Splatsin | 5/4/2021 | New Construction | Indigenous Group | $ 2,957,500.00 | $ 2,957,500.00 | $ - | Under Construction | 50.5452 | -119.140879 |
Eskasoni 3 | Nova Scotia | 2020-21 RHI 5 2-bedroom Unit Project | 5 | 5 | - | Rapid Housing Initiative 2 | Eskasoni | 5/23/2023 | New Construction | Indigenous Governing Body | $ 682,793.66 | $ 682,793.66 | $ - | Under Construction | 45.9288 | -60.638024 |
Esquimalt | British Columbia | 874 Fleming Street | 137 | 137 | 7 | National Housing Co-Investment Fund | Greater Victoria Housing Society | 7/6/2022 | New Construction | Not-for-profit housing org/Co-op | $ 6,403,421.00 | $ 6,403,421.00 | $ - | Under Construction | 48.4403 | -123.3998415 |
Fernie | British Columbia | North End Court | 35 | 7 | 5 | National Housing Co-Investment Fund | Fernie Family Housing Society | 10/27/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,414,394.00 | $ 1,414,394.00 | $ - | Under Construction | 49.5090 | -115.0533141 |
Fisher River 44 | Manitoba | First Nation Healing Centre Renovations | 19 | - | 4 | National Housing Co-Investment Fund | Fisher River Cree Nation | 6/15/2023 | Repairs | Indigenous Group | $ 512,696.96 | $ 512,696.96 | $ - | Under Construction | 51.1860 | -96.255628 |
Forestville | Quebec | Villa Forestville - Phase III - RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 1,610,000.00 | $ 1,610,000.00 | $ - | Financial Commitments | 48.7581 | -69.088027 |
Fort Erie | Ontario | Transitional Housing | 18 | 18 | - | National Housing Co-Investment Fund | Niagara Regional Housing | 6/15/2023 | New Construction | Municipality | $ 5,923,674.00 | $ 5,923,674.00 | $ - | Under Construction | 42.9018 | -78.972176 |
Indian Brook 14 | Nova Scotia | Sipekne'katik First Nation Repairs | 6 | 3 | 1 | National Housing Co-Investment Fund | Sipekne'katik | 1/25/2023 | Repairs | Indigenous Governing Body | $ 45,000.00 | $ 45,000.00 | $ - | Built | 45.0911 | -63.496408 |
Antigonish | Nova Scotia | Paqtnkek Mi'kmaw Nation Repairs | 18 | 2 | 1 | National Housing Co-Investment Fund | Paqtnkek Mi’kmaw Nation | 1/25/2023 | Repairs | Indigenous Governing Body | $ 30,000.00 | $ 30,000.00 | $ - | Built | 45.6040 | -61.659428 |
Fort Saskatchewan | Alberta | 83 Unit Heartland Housing Project | 83 | 83 | 17 | National Housing Co-Investment Fund | Heartland Housing Foundation | 1/19/2022 | New Construction | Not-for-profit housing org/Co-op | $ 6,463,427.00 | $ 871,808.00 | $ 5,591,619.00 | Built | 53.7021 | -113.2234509 |
Fort St. James | British Columbia | Connexus Fort St. James Seniors Housing Project | 36 | 25 | 8 | National Housing Co-Investment Fund | Connexus Community Resources Society | 1/26/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,000,000.00 | $ 3,000,000.00 | $ - | Under Construction | 54.4414 | -124.2419647 |
Fountain 1 | British Columbia | Xaxlip RHI | 5 | - | - | Rapid Housing Initiative | Xaxli'p | 4/9/2021 | New Construction | Indigenous Group | $ 1,659,000.00 | $ 1,659,000.00 | $ - | Built | 50.6833 | -121.93333 |
Fox Creek | Alberta | Iosegun Manor Addition | 12 | - | - | Rapid Housing Initiative 2 | Heart River Housing | 4/27/2023 | New Construction | Not-for-profit housing org/Co-op | $ 2,001,054.00 | $ 2,001,054.00 | $ - | Built | 54.4030 | -116.806666 |
Fredericton | New Brunswick | 12 Neighbours Community - Tiny Homes | 96 | 96 | 20 | National Housing Co-Investment Fund | 12 Neighbours Community | 2/28/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,822,844.00 | $ 3,822,844.00 | $ - | Built | 45.9734 | -66.545361 |
Fredericton | New Brunswick | John Howard Society of Fredericton | 8 | - | - | Rapid Housing Initiative 3 | City of Fredericton | 5/24/2023 | 0 | Municipality | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Financial Commitments | 45.9750 | -66.625428 |
Fredericton | New Brunswick | Mahsus Lane Development - Skigin Elnoog | 17 | - | - | Rapid Housing Initiative 3 | City of Fredericton | 5/24/2023 | New Construction | Municipality | $ 3,000,000.00 | $ 3,000,000.00 | $ - | Financial Commitments | 46.0109 | -66.632221 |
Gaspé | Quebec | Demeure Toi RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 3,650,000.00 | $ 3,650,000.00 | $ - | Financial Commitments | 48.8301 | -64.487133 |
Gaspé | Quebec | Shelter | 4 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Repairs | Province | $ 694,564.00 | $ 694,564.00 | $ - | Under Construction | 48.8316 | -64.4869 |
Gaspé | Quebec | SHQ - Projet Petit-Cap | 12 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 3,580,300.00 | $ 3,580,300.00 | $ - | Under Construction | 49.0292 | -64.4419324 |
Gatineau | Quebec | Square Urbania | 50 | 90 | - | Rapid Housing Initiative | Société d'habitation du Québec | 6/20/2023 | New Construction | Province | $ 1,400,000.00 | $ 1,400,000.00 | $ - | Built | 45.4863 | -75.676576 |
Gatineau | Quebec | SHQ - Le toît d'Érica | 20 | 14 | - | Rapid Housing Initiative | Société d'habitation du Québec SHQ | 1/22/2021 | New Construction | Province | $ 730,000.00 | $ 730,000.00 | $ - | Financial Commitments | 45.5456 | -75.418405 |
Gatineau | Quebec | Les Apprentis RHI2 | 21 | 25 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 1,400,000.00 | $ 1,400,000.00 | $ - | Under Construction | 45.4851 | -75.644202 |
Gatineau | Quebec | Lemieux-Tremblay Projet RHI2 | 24 | 24 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Financial Commitments | 45.4262 | -75.71725 |
Gatineau | Quebec | Braves du Coin RHI2 / Habitations Morin | 40 | 40 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 1,600,000.00 | $ 1,600,000.00 | $ - | Built | 45.4221 | -75.84334 |
Gatineau | Quebec | SHQ - St-Étienne | 15 | 15 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 3/27/2023 | New Construction | Province | $ 670,000.00 | $ 670,000.00 | $ - | Under Construction | 45.4339 | -75.71396 |
Gatineau | Quebec | Zibi | 519 | 105 | 74 | Innovation Fund | Dream Unlimited Corp. | 7/2/2021 | New Construction | Private Enterprise/Builder/Developer | $ 10,000,000.00 | $ - | $ 10,000,000.00 | Under Construction | 45.4235 | -75.718595 |
Gatineau | Quebec | Zibi Block 10 | 162 | 149 | 17 | Rental Construction Financing Initiative | Windmill Dream Quebec 10 LP | 7/2/2021 | New Construction | Private Enterprise/Builder/Developer | $ 60,000,000.00 | $ - | $ 60,000,000.00 | Under Construction | 45.4232 | -75.7190344 |
Gatineau | Quebec | SHQ - Coopérative de Solidarité du Vieux Clocher | 9 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 503,450.00 | $ 503,450.00 | $ - | Built | 46.3017 | -75.866366 |
Gatineau | Quebec | SHQ - Plateau | 73 | 72 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 4,708,800.00 | $ 4,708,800.00 | $ - | Under Construction | 45.4366 | -75.7993191 |
Gatineau | Quebec | SHQ - Saint-Antoine de Mon Chez Nous | 14 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,035,000.00 | $ 2,035,000.00 | $ - | Under Construction | 45.4833 | -75.6141738 |
Gatineau | Quebec | 150 Jeannine Domaine La Baie | 80 | 80 | 8 | Rental Construction Financing Initiative | DevCore / JF Labrecque (Broker) | 5/25/2021 | New Construction | Private Enterprise/Builder/Developer | $ 20,690,000.00 | $ - | $ 20,690,000.00 | Built | 45.5289 | -73.565533 |
Gesgapegiag | Quebec | Micmacs of Gesgapegiag | 14 | - | - | Rapid Housing Initiative | Micmacs of Gesgapegiag | 1/22/2021 | New Construction | Indigenous Group | $ 1,278,235.00 | $ 1,278,235.00 | $ - | Built | 48.2025 | -65.9202821 |
Gibsons | British Columbia | Shelter | 40 | 16 | 9 | National Housing Co-Investment Fund | Sunshine Coast Affordable Housing Society | 11/8/2022 | New Construction | Not-for-profit housing org/Co-op | $ 2,578,723.00 | $ 2,578,723.00 | $ - | Financial Commitments | 49.3974 | -123.5152 |
Gjoa Haven | Nunavut | Nunavut portfolio A - Lot 481 and Lots 2-3 Gjoa Haven | 10 | - | - | Rapid Housing Initiative | Nunavut Housing Corporation | 3/8/2021 | New Construction | Territory | $ 3,454,800.00 | $ 3,454,800.00 | $ - | Built | 68.6356 | -95.849722 |
Grande Prairie | Alberta | Shelter | 70 | 70 | 16 | National Housing Co-Investment Fund | 340715 Alberta Society | 3/27/2023 | Repairs | Not-for-profit housing org/Co-op | $ 256,451.00 | $ 256,451.00 | $ - | Built | 55.1708 | -118.794722 |
Grande-Vallée | Quebec | SHQ - Maison des Aînés de Grande-Vallée | 10 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,527,200.00 | $ 2,527,200.00 | $ - | Under Construction | 49.2188 | -65.1284305 |
Gravenhurst | Ontario | Alexander Muskoka (The Alexander Retirement Care Facility) | 95 | 32 | 30 | National Housing Co-Investment Fund | Alexander Muskoka Investments I LP | 3/3/2022 | New Construction | Private Enterprise/Builder/Developer | $ 23,170,478.00 | $ - | $ 23,170,478.00 | Under Construction | 44.9222 | -79.3821923 |
Greater Sudbury / Grand Sudbury | Ontario | Coniston Non-Profit Seniors Housing Corporation | 55 | 48 | 9 | Rental Construction Financing Initiative | Coniston Non-Profit Seniors Housing Corporation | 8/3/2021 | New Construction | Not-for-profit housing org/Co-op | $ 17,950,000.00 | $ - | $ 17,950,000.00 | Under Construction | 46.4927 | -80.852848 |
Gregoire Lake 176 | Alberta | Fort McMurray 468 First Nation RHI 2021 | 10 | 10 | - | Rapid Housing Initiative 2 | Fort McMurray #468 First Nation | 2/16/2023 | New Construction | Indigenous Governing Body | $ 2,474,307.00 | $ 2,474,307.00 | $ - | Under Construction | 56.6694 | -111.331675 |
Grise Fiord | Nunavut | Qikiqtani - Grise Fiord Single Family - High Arctic Affordable Housing Project | 1 | 1 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,025,320.00 | $ 1,025,320.00 | $ - | Financial Commitments | 76.4172 | -82.893034 |
Grise Fiord | Nunavut | Qikiqtani - Grise Fiord Semi Detached - High Arctic Affordable Housing Project | 2 | 2 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,607,469.00 | $ 1,607,469.00 | $ - | Financial Commitments | 76.4172 | -82.893034 |
Guelph | Ontario | Kindle Communities Supportive Housing | 32 | 32 | 8 | National Housing Co-Investment Fund | Kindle Communities Organization | 9/28/2022 | New Construction | Not-for-profit housing org/Co-op | $ 2,512,901.23 | $ 2,512,901.23 | $ - | Under Construction | 43.5443 | -80.2749498 |
Guelph | Ontario | Grace Gardens | 32 | - | - | Rapid Housing Initiative 2 | County of Wellington | 2/9/2022 | Repairs | Municipality | $ 6,416,189.00 | $ 6,416,189.00 | $ - | Under Construction | 43.5623 | -80.2731947 |
Guelph | Ontario | Silver Maple Seniors Community | 115 | 65 | 23 | National Housing Co-Investment Fund | St. Joseph's Housing Corporation Inc. Guelph | 3/18/2021 | New Construction | Not-for-profit housing org/Co-op | $ 37,436,051.25 | $ 2,320,395.00 | $ 35,115,656.00 | Built | 43.5502 | -80.2751504 |
Halifax | Nova Scotia | True North | 12 | 12 | - | Rapid Housing Initiative 2 | Affordable Housing Association of Nova Scotia | 12/20/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,705,543.00 | $ 3,705,543.00 | $ - | Built | 44.6896 | -63.5826481 |
Halifax | Nova Scotia | City of Halifax- Souls Harbour | 12 | 12 | - | Rapid Housing Initiative 2 | Halifax Regional Municipality | 1/28/2022 | New Construction | Municipality | $ 3,384,537.75 | $ 3,384,537.75 | $ - | Built | 44.7117 | -63.2597391 |
Halifax | Nova Scotia | City of Halifax-AKOMA | 8 | 8 | - | Rapid Housing Initiative 2 | Halifax Regional Municipality | 1/28/2022 | New Construction | Municipality | $ 3,100,343.25 | $ 3,100,343.25 | $ - | Under Construction | 44.6240 | -63.5111967 |
Halifax | Nova Scotia | City of Halifax-AHANS | 65 | 65 | - | Rapid Housing Initiative 2 | Halifax Regional Municipality | 1/27/2022 | Repairs | Municipality | $ 6,494,140.00 | $ 6,494,140.00 | $ - | Built | 44.6482 | -63.7247904 |
Halifax | Nova Scotia | Interchange Place - 3514 Joseph Howe Drive | 324 | 323 | 37 | Rental Construction Financing Initiative | BANC Investments Ltd. | 6/16/2021 | New Construction | Private Enterprise/Builder/Developer | $ 115,500,000.00 | $ - | $ 115,500,000.00 | Under Construction | 44.6560 | -63.6304497 |
Halifax | Nova Scotia | Shelter | 51 | 51 | 11 | Federal Lands Initiative | Compass Nova Scotia Co-operative Homes Ltd. | 4/3/2021 | New Construction | Not-for-profit housing org/Co-op | $ 1,534,955.00 | $ 1,534,955.00 | $ - | Under Construction | 44.8857 | -63.1005 |
Halifax | Nova Scotia | 2095-2219 Maitland Street, Halifax | 57 | 57 | 6 | National Housing Co-Investment Fund | Compass Nova Scotia Co-operative Homes Ltd. | 3/4/2021 | New Construction | Not-for-profit housing org/Co-op | $ 20,679,325.00 | $ 5,905,162.00 | $ 14,774,163.00 | Under Construction | 44.6519 | -63.581629 |
Halifax | Nova Scotia | Stream A Halifax - College Street Project | 21 | 21 | - | Rapid Housing Initiative | Halifax Regional Municipality | 12/21/2020 | New Construction | Municipality | $ 3,206,442.22 | $ 3,206,442.22 | $ - | Under Construction | 44.6400 | -63.5843536 |
Halifax | Nova Scotia | Stream A Halifax - Pam's Honour | 25 | 25 | - | Rapid Housing Initiative | Halifax Regional Municipality | 12/21/2020 | New Construction | Municipality | $ 4,168,816.78 | $ 4,168,816.78 | $ - | Built | 44.6335 | -63.7025534 |
Halifax | Nova Scotia | Stream A Halifax - The Blue Building | 10 | - | - | Rapid Housing Initiative | Halifax Regional Municipality | 12/21/2020 | Renewals | Municipality | $ 1,284,268.75 | $ 1,284,268.75 | $ - | Built | 44.6530 | -63.5835981 |
Halifax | Nova Scotia | Shelter | 24 | - | 24 | National Housing Co-Investment Fund | Halifax Transition House Association | 3/4/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,223,398.00 | $ 3,223,398.00 | $ - | Built | 44.8857 | -63.1005 |
Hall Beach | Nunavut | Nunavut portfolio - Hall Beach - 2 x 5-plex 2020-2021 | 10 | 10 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 4,495,823.54 | $ 4,495,823.54 | $ - | Built | 68.7727 | -81.235208 |
Hamilton | Ontario | Emergency Brickwork | 46 | 46 | - | National Housing Co-Investment Fund | Women's Community Co-operative Inc. | 7/31/2023 | Repairs | Not-for-profit housing org/Co-op | $ 353,541.00 | $ 353,541.00 | $ - | Under Construction | 43.2282 | -79.770627 |
Hamilton | Ontario | CHH RHI-3 [1620 Main St. E] | 42 | - | - | Rapid Housing Initiative 3 | City of Hamilton | 5/24/2023 | New Construction | Municipality | $ 10,898,100.00 | $ 10,898,100.00 | $ - | Financial Commitments | 43.2377 | -79.800045 |
Hamilton | Ontario | Roxborough - CO | 103 | 58 | 12 | National Housing Co-Investment Fund | CityHousing Hamilton Corporation | 5/24/2023 | New Construction | Municipality | $ 7,166,020.00 | $ 7,166,020.00 | $ - | Built | 43.2168 | -79.841643 |
Hamilton | Ontario | Roxborough Affordable Rentals | 310 | 310 | 76 | Rental Construction Financing Initiative | RPI Apartments Inc. | 5/24/2023 | New Construction | Private Enterprise/Builder/Developer | $ 115,000,000.00 | $ - | $ 115,000,000.00 | Under Construction | 43.2348 | -79.787544 |
Hamilton | Ontario | 256 Parkdale | 50 | 50 | 10 | National Housing Co-Investment Fund | Indwell Community Homes | 8/5/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,057,193.00 | $ 3,057,193.00 | $ - | Built | 43.2438 | -79.7884936 |
Hamilton | Ontario | Arkeldun Good Shepherd | 73 | - | - | Rapid Housing Initiative 2 | City of Hamilton | 1/25/2022 | Repairs | Municipality | $ 12,945,935.00 | $ 12,945,935.00 | $ - | Built | 43.2472 | -79.8682363 |
Hamilton | Ontario | Shelter | 24 | 24 | - | Rapid Housing Initiative 2 | City of Hamilton | 1/25/2022 | New Construction | Municipality | $ 6,475,844.00 | $ 6,475,844.00 | $ - | Under Construction | 43.2557 | -79.8711 |
Hamilton | Ontario | St. Matt's - 412 Barton East | 12 | 12 | - | Rapid Housing Initiative 2 | City of Hamilton | 1/25/2022 | New Construction | Municipality | $ 3,850,000.00 | $ 3,850,000.00 | $ - | Under Construction | 43.2593 | -79.8477663 |
Hamilton | Ontario | Ken Soble Tower Transformation | 146 | 74 | 31 | National Housing Co-Investment Fund | CityHousing Hamilton Corporation | 9/24/2021 | Repairs | Municipality | $ 13,300,000.00 | $ 6,000,000.00 | $ 7,300,000.00 | Built | 43.2731 | -79.8633573 |
Hamilton | Ontario | Stream A Hamilton - 137 George - OFILD | 6 | 6 | - | Rapid Housing Initiative | City of Hamilton | 12/15/2020 | New Construction | Municipality | $ 2,260,585.00 | $ 2,260,585.00 | $ - | Under Construction | 43.2585 | -79.8799512 |
Hamilton | Ontario | Stream A Hamilton - 195 Ferguson N | 12 | 12 | - | Rapid Housing Initiative | City of Hamilton | 12/15/2020 | Repairs | Municipality | $ 2,250,000.00 | $ 2,250,000.00 | $ - | Built | 43.2609 | -79.8592016 |
Hamilton | Ontario | Stream A Hamilton - 350 King St. E - CityHousing Hamilton | 15 | 15 | - | Rapid Housing Initiative | City of Hamilton | 12/15/2020 | Repairs | Municipality | $ 2,250,000.00 | $ 2,250,000.00 | $ - | Built | 43.2533 | -79.8589391 |
Hamilton | Ontario | 500 James Street | 45 | 34 | 9 | National Housing Co-Investment Fund | INCORPORATED | 8/27/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,281,034.00 | $ 2,281,034.00 | $ - | Built | 43.2699 | -79.8627507 |
Hamilton | Ontario | Ken Soble Tower Transformation | 146 | 146 | - | Innovation Fund | CityHousing Hamilton Corporation | 5/21/2019 | Renewals | Municipality | $ 3,650,000.00 | $ 1,000,000.00 | $ 2,650,000.00 | Under Construction | 43.2731 | -79.863361 |
Hamilton | Ontario | Shelter | 50 | 35 | 10 | National Housing Co-Investment Fund | The Hamilton Young Women's Christian Associatio | 1/22/2019 | New Construction | Not-for-profit housing org/Co-op | $ 10,808,235.00 | $ 3,700,000.00 | $ 7,108,235.00 | Built | 43.2557 | -79.8711 |
Hampton | New Brunswick | Demille Place | 21 | 8 | 5 | National Housing Co-Investment Fund | DeMille Place Inc | 5/21/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,976,480.00 | $ 183,916.00 | $ 2,792,564.00 | Built | 45.5198 | -65.8458601 |
Happy Valley-Goose Bay | Newfoundland and Labrador | Happy Valley-Goose Bay RHI 3 Cities Stream | 16 | 16 | - | Rapid Housing Initiative 3 | Town of Happy Valley-Goose Bay | 6/12/2023 | New Construction | Municipality | $ 5,000,000.00 | $ 5,000,000.00 | $ - | Financial Commitments | 53.3186 | -60.324513 |
Hay River | Northwest Territories | Shelter | 14 | 10 | 4 | National Housing Co-Investment Fund | Family Support Centre | 2/3/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,161,894.00 | $ 3,161,894.00 | $ - | Under Construction | 60.8162 | -115.7854 |
Hazelton | British Columbia | Bringing Our Children Home | 15 | 15 | 6 | National Housing Co-Investment Fund | Gitxsan Child and Family Services Society | 10/10/2023 | New Construction | Indigenous Group | $ 1,255,579.00 | $ 1,255,579.00 | $ - | Under Construction | 55.2995 | -127.681659 |
Hébertville | Quebec | Pionnier nouvelle génération - RHI2 | 20 | 20 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 6,258,813.00 | $ 6,258,813.00 | $ - | Financial Commitments | 48.3911 | -71.679847 |
Hinton | Alberta | Boultin Avenue Modular Homes | 8 | 10 | - | Rapid Housing Initiative 2 | Town of Hinton | 1/25/2022 | New Construction | Municipality | $ 2,258,000.00 | $ 2,258,000.00 | $ - | Under Construction | 53.4251 | -117.536138 |
Hope | British Columbia | Anhart Community Housing Society | 40 | 40 | 4 | Rental Construction Financing Initiative | Anhart Community Housing Society | 9/16/2020 | New Construction | Not-for-profit housing org/Co-op | $ 5,100,000.00 | $ - | $ 5,100,000.00 | Built | 49.3742 | -121.4304274 |
Hopedale | Newfoundland and Labrador | Nunatsiavut Communities RHI | 20 | 20 | 14 | Rapid Housing Initiative | Nunatsiavut Government | 5/20/2021 | New Construction | Indigenous Group | $ 5,933,639.00 | $ 5,933,639.00 | $ - | Under Construction | 56.5512 | -61.6834846 |
Horse Lakes 152B | Alberta | Horse Lake First Nation | 10 | 10 | - | Rapid Housing Initiative 2 | Horse Lake First Nation | 4/27/2023 | New Construction | Indigenous Governing Body | $ 3,959,925.00 | $ 3,959,925.00 | $ - | Under Construction | 55.3307 | -119.556393 |
Hudson | Quebec | Villa Wyman RHI2 | 18 | 18 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,255,326.00 | $ 4,255,326.00 | $ - | Financial Commitments | 45.4421 | -74.106404 |
Indian Brook 14 | Nova Scotia | New Burma Rd Cul-de-sac - 20 units | 20 | - | - | Rapid Housing Initiative | Sipekne'katik First Nation | 5/13/2021 | New Construction | Indigenous Group | $ 2,725,360.00 | $ 2,725,360.00 | $ - | Under Construction | 45.1011 | -63.4970015 |
Iqaluit | Nunavut | 5104 Qajisarvik Road | 6 | 6 | - | National Housing Co-Investment Fund | YWCA Agvik Nunavut | 11/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 700,000.00 | $ 700,000.00 | $ - | Built | 63.7571 | -68.5201706 |
Iqaluit | Nunavut | Shelter | 8 | - | - | National Housing Co-Investment Fund | YWCA Agvik Nunavut | 11/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 520,000.00 | $ 520,000.00 | $ - | Built | 63.7467 | -68.517 |
Iqaluit | Nunavut | YWCA Agvik Supportive Womens Affordable Housing 4035 | 7 | 1 | - | National Housing Co-Investment Fund | YWCA Agvik Nunavut | 11/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 775,000.00 | $ 775,000.00 | $ - | Built | 63.7522 | -68.4955893 |
Iqaluit | Nunavut | Nunavut portfolio Iqaluit - Joamie Court & Tundra Ridge | 46 | 46 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 21,520,316.51 | $ 21,520,316.51 | $ - | Built | 63.7467 | -68.516967 |
Iqaluit | Nunavut | Transitional Housing | 71 | 28 | 7 | National Housing Co-Investment Fund | Uquutaq Society | 10/22/2020 | New Construction | Not-for-profit housing org/Co-op | $ 8,045,000.00 | $ 2,095,000.00 | $ 5,950,000.00 | Built | 63.7492 | -68.5313758 |
Joliette | Quebec | Maison Latraverse RHI2 | 8 | 8 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,100,000.00 | $ 2,100,000.00 | $ - | Financial Commitments | 46.0761 | -73.501191 |
Joliette | Quebec | PAX Habitat | 102 | 50 | - | National Housing Co-Investment Fund | Corporation PAX - Habitat | 4/21/2023 | New Construction | Faith-based organization | $ 21,823,310.00 | $ 5,000,000.00 | $ 16,823,310.00 | Under Construction | 46.0353 | -73.4409902 |
Juan de Fuca | British Columbia | Pacheedaht Village Homes | 6 | 6 | - | Rapid Housing Initiative 2 | Pacheedaht First Nation | 5/8/2023 | New Construction | Indigenous Governing Body | $ 666,710.00 | $ 666,710.00 | $ - | Built | 48.5332 | -124.315607 |
Juan de Fuca | British Columbia | Pacheedaht Village Homes | 6 | 6 | - | Rapid Housing Initiative 2 | Pacheedaht First Nation | 5/8/2023 | New Construction | Indigenous Governing Body | $ 921,690.00 | $ 921,690.00 | $ - | Built | 48.5530 | -124.422299 |
Kahkewistahaw 72 | Saskatchewan | Homelessness Diversion | 15 | - | - | Rapid Housing Initiative | Kahkewistahaw First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 2,065,298.75 | $ 2,065,298.75 | $ - | Under Construction | 50.3781 | -102.579043 |
Kamloops 1 | British Columbia | Tyee Elders Housing | 10 | 10 | 10 | Rapid Housing Initiative | Tk'emlúps te Secwépemc | 5/4/2021 | New Construction | Indigenous Group | $ 3,526,783.00 | $ 3,526,783.00 | $ - | Built | 50.7068 | -120.32641 |
Kamploops | British Columbia | Kikekyelc: A Place of Belonging | 31 | 31 | 2 | National Housing Co-Investment Fund | Provincial Rental Housing Corporation (PRHC) | 11/16/2020 | New Construction | Province | $ 1,663,478.00 | $ 1,663,478.00 | $ - | Built | 50.7066 | -120.38431 |
Kanaka Bar | British Columbia | The Crossing Place | 24 | 24 | 5 | National Housing Co-Investment Fund | The Crossing Place Housing Society | 8/15/2022 | New Construction | Indigenous Non-Profit Organization | $ 1,440,000.00 | $ 1,440,000.00 | $ - | Built | 50.2333 | -121.581404 |
Kaslo | British Columbia | Penny Lane Apartments | 10 | 7 | 2 | National Housing Co-Investment Fund | Kaslo Housing Society | 1/10/2023 | New Construction | Not-for-profit housing org/Co-op | $ 686,251.00 | $ 686,251.00 | $ - | Built | 49.9112 | -116.908976 |
Kawartha Lakes | Ontario | Shelter | 6 | 6 | 2 | National Housing Co-Investment Fund | Women's Resources of Kawartha Lakes | 1/12/2023 | New Construction | Not-for-profit housing org/Co-op | $ 1,471,343.00 | $ 1,471,343.00 | $ - | Under Construction | 44.5337 | -78.9006 |
Kelowna | British Columbia | Cawston Ave | 40 | 28 | 2 | National Housing Co-Investment Fund | New Opportunities for Women (NOW) Canada Society | 1/30/2020 | New Construction | Not-for-profit housing org/Co-op | $ 3,915,675.00 | $ 3,915,675.00 | $ - | Built | 49.8917 | -119.478412 |
Kelowna | British Columbia | Pleasantvale 2 | 75 | 48 | 48 | National Housing Co-Investment Fund | Society of Housing Opportunities and Progressive Employment | 7/13/2023 | New Construction | Not-for-profit housing org/Co-op | $ 4,637,832.00 | $ 4,637,832.00 | $ - | Under Construction | 49.9034 | -119.489677 |
Kelowna | British Columbia | 555 Fuller Avenue Project | 68 | 26 | 8 | National Housing Co-Investment Fund | Pathways Abilities Society | 2/24/2021 | New Construction | Not-for-profit housing org/Co-op | $ 2,481,000.00 | $ 2,481,000.00 | $ - | Under Construction | 49.8898 | -119.4906705 |
Kimmirut | Nunavut | Nunavut portfolio - Kimmirut | 5 | 5 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 2,318,408.04 | $ 2,318,408.04 | $ - | Built | 62.8474 | -69.869203 |
Kimosom Pwatinahk 203 | Saskatchewan | PBCN Deschambault Lake | 10 | 10 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 2,438,937.00 | $ 2,438,937.00 | $ - | Under Construction | 54.9083 | -103.377254 |
Kingston | Ontario | 1316-1318 Princess Street | 38 | 38 | 8 | National Housing Co-Investment Fund | Kingston Co-Operative Homes Inc. | 12/9/2022 | New Construction | Not-for-profit housing org/Co-op | $ 9,432,862.00 | $ 4,258,451.00 | $ 5,174,411.00 | Under Construction | 44.2475 | -76.5271468 |
Kingston | Ontario | 1316-1318 Princess Street - Loan | 92 | 52 | 19 | National Housing Co-Investment Fund | Kingston & Frontenac Housing Corporation | 12/9/2022 | New Construction | Municipality | $ 19,536,237.00 | $ 6,264,091.00 | $ 13,272,146.00 | Under Construction | 44.2476 | -76.527335 |
Kingston | Ontario | 27 Wright Crescent | 40 | 20 | 8 | National Housing Co-Investment Fund | Kingston & Frontenac Housing Corporation | 4/29/2022 | New Construction | Municipality | $ 4,761,241.00 | $ 198,155.00 | $ 4,563,086.00 | Built | 44.2379 | -76.5153804 |
Kingston | Ontario | 1 Curtis Crescent - City of Kingston | 9 | 9 | - | Rapid Housing Initiative 2 | The Corporation of the City of Kingston | 11/26/2021 | New Construction | Municipality | $ 2,078,085.00 | $ 2,078,085.00 | $ - | Built | 44.2268 | -76.526151 |
Kingston | Ontario | 113 Lower Union St - City of Kingston | 19 | - | - | Rapid Housing Initiative 2 | The Corporation of the City of Kingston | 11/26/2021 | Renewals | Municipality | $ 655,001.00 | $ 655,001.00 | $ - | Built | 44.2269 | -76.487328 |
Kingston | Ontario | 3 Cassidy Street - City of Kingston | 7 | - | - | Rapid Housing Initiative 2 | The Corporation of the City of Kingston | 11/26/2021 | Renewals | Municipality | $ 1,154,880.00 | $ 1,154,880.00 | $ - | Built | 44.2556 | -76.4833212 |
Kingston | Ontario | Shelter | 12 | 12 | - | Rapid Housing Initiative 2 | The Corporation of the City of Kingston | 11/26/2021 | Renewals | Municipality | $ 3,530,362.00 | $ 3,530,362.00 | $ - | Built | 44.2312 | -76.486 |
Kinistin 91 | Saskatchewan | Kinistin First Nation | 5 | - | - | Rapid Housing Initiative | Kinistin Saulteaux Nation | 4/15/2021 | New Construction | Indigenous Group | $ 1,430,100.00 | $ 1,430,100.00 | $ - | Built | 52.6963 | -104.006843 |
Kitchener | Ontario | 55 Franklin - 1 | 60 | 60 | 12 | Rental Construction Financing Initiative | 55 Franklin GP Inc. | 8/3/2023 | New Construction | Private Enterprise/Builder/Developer | $ 16,200,000.00 | $ - | $ 16,200,000.00 | Built | 43.4328 | -80.447257 |
Kitchener | Ontario | The Working Centre - 97 Victoria | 44 | - | - | Rapid Housing Initiative 3 | The Regional Municipality of Waterloo | 6/14/2023 | New Construction | Municipality | $ 9,847,461.00 | $ 9,847,461.00 | $ - | Financial Commitments | 43.4544 | -80.494723 |
Kitchener | Ontario | King and Cameo | 304 | 300 | 42 | Rental Construction Financing Initiative | 3247 King Street East (Kitchener) Limited | 6/28/2023 | New Construction | Private Enterprise/Builder/Developer | $ 114,800,000.00 | $ - | $ 114,800,000.00 | Under Construction | 43.4261 | -80.425036 |
Kitchener | Ontario | OneROOF | 44 | - | - | Rapid Housing Initiative 2 | The Regional Municipality of Waterloo | 1/13/2022 | New Construction | Municipality | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Built | 43.4409 | -80.4672757 |
Kitchener | Ontario | Shelter | 8 | 8 | - | Rapid Housing Initiative 2 | The Regional Municipality of Waterloo | 12/13/2021 | New Construction | Municipality | $ 3,029,608.00 | $ 3,029,608.00 | $ - | Built | 43.4516 | -80.4925 |
Kitchener | Ontario | Working Centre - 58 Queen | 4 | - | - | Rapid Housing Initiative 2 | The Regional Municipality of Waterloo | 12/13/2021 | Repairs | Municipality | $ 243,710.00 | $ 243,710.00 | $ - | Under Construction | 43.4492 | -80.4899617 |
Kitchener | Ontario | Working Centre - Bricker Block | 14 | - | - | Rapid Housing Initiative 2 | The Regional Municipality of Waterloo | 12/13/2021 | Repairs | Municipality | $ 3,368,511.00 | $ 3,368,511.00 | $ - | Under Construction | 43.4494 | -80.4902054 |
Kitchener | Ontario | Stream A Waterloo - YWCA - Block Line | 41 | 36 | - | Rapid Housing Initiative | The Regional Municipality of Waterloo | 12/16/2020 | New Construction | Municipality | $ 6,858,456.00 | $ 6,858,456.00 | $ - | Built | 43.4189 | -80.4691443 |
Kitchener | Ontario | K-W Habilitation Services project | 22 | - | 22 | Rental Construction Financing Initiative | KW Habilitation Services | 6/28/2018 | New Construction | Not-for-profit housing org/Co-op | $ 2,075,500.00 | $ - | $ 2,075,500.00 | Built | 43.4390 | -80.4727159 |
Kitchenuhmaykoosib Aaki 84 (Big Trout Lake) | Ontario | KI CMHC Rapid Housing 2020 | 15 | - | - | Rapid Housing Initiative | Kitchenummaykoosib Inninuwug | 4/16/2021 | New Construction | Indigenous Group | $ 3,062,820.37 | $ 3,062,820.37 | $ - | Built | 53.8188 | -89.835093 |
Kugaaruk | Nunavut | Nunavut portfolio Kugaaruk - 2 x 5-plex 2020-2021 | 10 | 10 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 5,112,447.89 | $ 5,112,447.89 | $ - | Built | 68.5347 | -89.825 |
Kugluktuk | Nunavut | Nunavut portfolio B - Lots 4-5 Kugluktuk | 5 | - | - | Rapid Housing Initiative | Nunavut Housing Corporation | 3/8/2021 | New Construction | Territory | $ 1,447,150.00 | $ 1,447,150.00 | $ - | Built | 68.6356 | -95.849722 |
La Malbaie | Quebec | La Maison la Montée (ACL-00910) RHI2 | 10 | 10 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,400,000.00 | $ 2,400,000.00 | $ - | Under Construction | 47.6520 | -70.160189 |
La Tuque | Quebec | OH Maskoutains et d'Acton - 1400 Saint-Antoine RHI2 | 21 | 23 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 4,810,000.00 | $ 4,810,000.00 | $ - | Financial Commitments | 45.6243 | -72.944364 |
La Tuque | Quebec | Les Appartements Libère-Toit Projet RHI2 | 32 | 32 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 7,310,000.00 | $ 7,310,000.00 | $ - | Under Construction | 47.4372 | -72.780679 |
Labrador City | Newfoundland and Labrador | Shelter | 7 | 7 | 3 | National Housing Co-Investment Fund | Hope Haven Incorporated | 2/27/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,386,629.00 | $ 3,386,629.00 | $ - | Under Construction | 52.9500 | -66.916667 |
Langford | British Columbia | Glen Lake Apartments | 119 | 119 | 16 | Rental Construction Financing Initiative | Woodsmere Holdings Corp. | 3/23/2021 | New Construction | Private Enterprise/Builder/Developer | $ 34,500,000.00 | $ - | $ 34,500,000.00 | Built | 48.4339 | -123.5215027 |
Langford | British Columbia | Woodsmere Holdings Corp | 120 | 120 | 12 | Rental Construction Financing Initiative | Woodsmere Holdings Corp. | 3/2/2020 | New Construction | Private Enterprise/Builder/Developer | $ 31,500,000.00 | $ - | $ 31,500,000.00 | Built | 48.4475 | -123.505489 |
Lantzville | British Columbia | Nanoose First Nation - Rapid Housing Initiative 2 | 5 | 5 | - | Rapid Housing Initiative 2 | Nanoose First Nation | 5/8/2023 | New Construction | Indigenous Governing Body | $ 1,971,426.00 | $ 1,971,426.00 | $ - | Under Construction | 49.2495 | -124.086167 |
LaSalle | Quebec | Celeste | 226 | 52 | 31 | Rental Construction Financing Initiative | Medici Developments Ltd. | 4/1/2021 | New Construction | Private Enterprise/Builder/Developer | $ 67,800,000.00 | $ - | $ 67,800,000.00 | Built | 45.4256 | -73.6085264 |
Lasalle | Quebec | APERO Phase 3 | 199 | 178 | 20 | Rental Construction Financing Initiative | Apero | 12/2/2019 | New Construction | Private Enterprise/Builder/Developer | $ 41,750,000.00 | $ - | $ 41,750,000.00 | Built | 45.6964 | -73.7802719 |
L'Assomption | Quebec | Les Habitations Indigo - RHI2 | 26 | 27 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,885,791.00 | $ 5,885,791.00 | $ - | Financial Commitments | 45.8443 | -73.423196 |
Laval | Quebec | La Maison L'Esther RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,500,000.00 | $ 2,500,000.00 | $ - | Under Construction | 45.6037 | -73.781681 |
Laval | Quebec | La maison du peuple de Laval Projet RHI2 | 36 | 36 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 6,200,000.00 | $ 6,200,000.00 | $ - | Under Construction | 45.6153 | -73.782996 |
Laval | Quebec | OMH de Laval - Habitation Bousquet RHI2 | 24 | 26 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 11,390,000.00 | $ 11,390,000.00 | $ - | Financial Commitments | 45.5793 | -73.699404 |
Laval | Quebec | Val-Martin / Bâtiment D | 75 | 67 | 13 | National Housing Co-Investment Fund | Office Municipal D'Habitation De Laval | 3/10/2023 | New Construction | Municipality | $ 4,000,000.00 | $ 4,000,000.00 | $ - | Under Construction | 45.5424 | -73.7413874 |
Laval | Quebec | Val-Martin / Bâtiments E, F et G | 160 | 160 | 11 | National Housing Co-Investment Fund | Office Municipal D'Habitation De Laval | 3/10/2023 | New Construction | Municipality | $ 5,728,000.00 | $ 5,728,000.00 | $ - | Built | 45.5424 | -73.7417801 |
Laval | Quebec | Central Parc Laval | 193 | 49 | 22 | Rental Construction Financing Initiative | Le Central Parc de Laval 2 SEC | 3/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 66,294,000.00 | $ - | $ 66,294,000.00 | Built | 45.5628 | -73.7550759 |
Laval | Quebec | Le Central Parc de Laval 3 S.E.C. | 149 | 62 | 19 | Rental Construction Financing Initiative | Le Central Parc de Laval 3 S.E.C. | 3/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 51,000,000.00 | $ - | $ 51,000,000.00 | Built | 45.5628 | -73.7550759 |
Laval | Quebec | Shelter | 17 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 995,000.00 | $ 995,000.00 | $ - | Under Construction | 45.6066 | -73.7124 |
Laval | Quebec | SHQ - Avenir de femmes | 23 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,030,000.00 | $ 2,030,000.00 | $ - | Under Construction | 45.5702 | -73.7319601 |
Laval | Quebec | SHQ - La Maison du Pas Sage | 13 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,432,050.00 | $ 1,432,050.00 | $ - | Built | 45.6187 | -73.7810649 |
Laverlochere-Angliers | Quebec | É.L.A.N. Laverlochère | 16 | 8 | - | National Housing Co-Investment Fund | E.L.A.N. Laverlochère | 2/4/2021 | New Construction | Not-for-profit housing org/Co-op | $ 901,837.00 | $ 901,837.00 | $ - | Under Construction | 47.4256 | -79.3096408 |
Leamington | Ontario | City of Windsor - 310 Sherk, Leamington | 8 | - | - | Rapid Housing Initiative 2 | The Corporation of the City of Windsor | 10/27/2022 | New Construction | Municipality | $ 1,858,000.00 | $ 1,858,000.00 | $ - | Under Construction | 42.0360 | -82.6045517 |
Leamington | Ontario | Caldwell First Nation - Housing Project | 10 | 10 | 10 | Rapid Housing Initiative 2 | Caldwell First Nation | 3/17/2022 | New Construction | Indigenous Governing Body | $ 3,755,000.00 | $ 3,755,000.00 | $ - | Under Construction | 42.0065 | -82.566434 |
Leamington | Ontario | Caldwell First Nation - Housing Project | 16 | 16 | 16 | Rapid Housing Initiative 2 | Caldwell First Nation | 3/17/2022 | New Construction | Indigenous Governing Body | $ 6,090,800.00 | $ 6,090,800.00 | $ - | Under Construction | 42.0065 | -82.566434 |
Lennox Island 1 | Prince Edward Island | Rapid Housing | 10 | - | - | Rapid Housing Initiative | Lennox Island First Nation | 4/4/2022 | New Construction | Indigenous Group | $ 1,391,850.00 | $ 1,391,850.00 | $ - | Built | 46.6007 | -63.855921 |
Les Îles-de-la-Madeleine | Quebec | Le Phare des Îles RHI2 | 8 | 8 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,650,000.00 | $ 4,650,000.00 | $ - | Financial Commitments | 47.3732 | -61.868375 |
Lethbridge | Alberta | Transitional Housing | 20 | - | 4 | National Housing Co-Investment Fund | Streets Alive Family Support Association | 8/25/2022 | New Construction | Not-for-profit housing org/Co-op | $ 212,278.00 | $ 212,278.00 | $ - | Built | 49.6762 | -112.8271111 |
Lethbridge | Alberta | The Cottage's South | 64 | 32 | 20 | National Housing Co-Investment Fund | Lethbridge & Region Community Housing Corp. | 8/16/2022 | New Construction | Not-for-profit housing org/Co-op | $ 4,800,000.00 | $ 4,800,000.00 | $ - | Built | 49.6545 | -112.7899229 |
Lévis | Quebec | 41 Saint-Joseph RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,100,000.00 | $ 3,100,000.00 | $ - | Financial Commitments | 46.8239 | -71.168387 |
Lévis | Quebec | OMH de Lévis - Boisé des Filions RHI2 | 23 | 23 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 7,500,000.00 | $ 7,500,000.00 | $ - | Financial Commitments | 46.7578 | -71.231427 |
L'Islet | Quebec | SHQ - Les Habitations Au Fil du Fleuve - Phase II | 12 | 13 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,910,456.00 | $ 1,910,456.00 | $ - | Under Construction | 47.1257 | -70.3756819 |
L'Isle-Verte | Quebec | Villa Rose des Vents Projet RHI2 | 20 | 20 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,400,000.00 | $ 5,400,000.00 | $ - | Under Construction | 47.9947 | -69.479829 |
Little Grand Rapids 14 | Manitoba | Transitional Housing | 6 | - | - | Rapid Housing Initiative | Little Grand Rapids First Nation | 5/18/2021 | New Construction | Indigenous Group | $ 350,000.00 | $ 350,000.00 | $ - | Built | 52.0173 | -95.45707 |
Little Red River 106C | Saskatchewan | LLRIB 2020 RHI Multi-Unit Senior Living project | 8 | - | - | Rapid Housing Initiative | Lac La Ronge Indian Band | 4/15/2021 | New Construction | Indigenous Group | $ 1,479,356.87 | $ 1,479,356.87 | $ - | Built | 55.0995 | -105.2987966 |
London | Ontario | London - 345 Sylvan | 42 | - | - | Rapid Housing Initiative 3 | City of London | 8/30/2023 | New Construction | Municipality | $ 8,854,705.00 | $ 8,854,705.00 | $ - | Financial Commitments | 42.9618 | -81.234973 |
London | Ontario | Joan's Place | 35 | 35 | 21 | National Housing Co-Investment Fund | Youth Opportunities Unlimited | 9/8/2023 | New Construction | Not-for-profit housing org/Co-op | $ 4,069,000.00 | $ 4,069,000.00 | $ - | Under Construction | 42.9819 | -81.248892 |
London | Ontario | Embassy Commons | 72 | 67 | 19 | National Housing Co-Investment Fund | Indwell Community Homes | 3/18/2022 | New Construction | Not-for-profit housing org/Co-op | $ 13,187,779.00 | $ 4,320,000.00 | $ 8,867,779.00 | Built | 42.9905 | -81.2268856 |
London | Ontario | Shelter | 44 | - | - | Rapid Housing Initiative 2 | The Corporation of the City of London | 12/15/2021 | New Construction | Municipality | $ 10,794,247.00 | $ 10,794,247.00 | $ - | Built | 42.9849 | -81.2453 |
London | Ontario | Homes Unlimited | 110 | 78 | 44 | National Housing Co-Investment Fund | HOMES UNLIMITED (LONDON) INCORPORATION | 8/11/2021 | New Construction | Not-for-profit housing org/Co-op | $ 24,751,968.00 | $ 1,424,470.00 | $ 23,327,498.00 | Built | 42.9698 | -81.2047243 |
London | Ontario | Shelter | 65 | 33 | 21 | National Housing Co-Investment Fund | P.A.M. Gardens, Non-Profit Housing Inc. | 7/26/2021 | New Construction | Not-for-profit housing org/Co-op | $ 12,192,200.00 | $ 795,835.00 | $ 11,396,365.00 | Built | 42.9849 | -81.2453 |
London | Ontario | LMCH Recapitalization (M) | 2083 | 2,083 | 414 | National Housing Co-Investment Fund | London & Middlesex Community Housing | 3/11/2021 | Repairs | Municipality | $ 40,136,090.00 | $ 15,533,989.00 | $ 24,602,101.00 | Under Construction | 43.0113 | -81.2257427 |
London | Ontario | Shelter | 61 | 61 | - | Rapid Housing Initiative | The Corporation of the City of London | 12/16/2020 | Renewals | Municipality | $ 7,546,767.00 | $ 7,546,767.00 | $ - | Under Construction | 42.9849 | -81.2453 |
London | Ontario | Rygar Properties Inc. | 420 | 292 | 66 | Rental Construction Financing Initiative | Old Oak Properties Inc. | 1/8/2020 | New Construction | Private Enterprise/Builder/Developer | $ 130,000,000.00 | $ - | $ 130,000,000.00 | Under Construction | 42.9854 | -81.2533524 |
London | Ontario | 770 Whetter Avenue by Homes Unlimited | 54 | 50 | 6 | Rental Construction Financing Initiative | HOMES UNLIMITED (LONDON) INCORPORATION | 11/2/2019 | New Construction | Not-for-profit housing org/Co-op | $ 4,400,000.00 | $ - | $ 4,400,000.00 | Built | 42.9660 | -81.2266797 |
London | Ontario | Young Adults Affordable Housing Project | 6 | 6 | - | National Housing Co-Investment Fund | Youth Opportunities Unlimited | 8/22/2019 | Repairs | Not-for-profit housing org/Co-op | $ 559,463.00 | $ 559,463.00 | $ - | Built | 42.9818 | -81.2483525 |
London | Ontario | Italian Seniors Project (ISP) Residenza Ortona development | 60 | 54 | 19 | National Housing Co-Investment Fund | RESIDENZA AFFORDABLE HOUSING | 7/15/2019 | New Construction | Not-for-profit housing org/Co-op | $ 7,129,749.00 | $ 682,000.00 | $ 6,447,749.00 | Built | 42.9771 | -81.1832805 |
London | Ontario | Nightingale Place Project | 41 | 41 | 9 | National Housing Co-Investment Fund | London Affordable Housing Foundation | 5/24/2019 | New Construction | Not-for-profit housing org/Co-op | $ 4,188,850.00 | $ 405,950.00 | $ 3,782,900.00 | Built | 42.9930 | -81.2160794 |
London | Ontario | 356 Dundas | 69 | 69 | 12 | Rental Construction Financing Initiative | Yossef Lavie | 12/19/2018 | New Construction | Private Enterprise/Builder/Developer | $ 4,911,700.00 | $ - | $ 4,911,700.00 | Built | 42.9863 | -81.2418146 |
Longueuil | Quebec | St-Roch - Phase II RHI2 | 36 | 36 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,700,000.00 | $ 3,700,000.00 | $ - | Financial Commitments | 45.5056 | -73.487769 |
Longueuil | Quebec | SHQ - Les Chrysalides | 7 | - | - | Rapid Housing Initiative | Société d'habitation du Québec SHQ | 9/15/2023 | New Construction | Province | $ 375,000.00 | $ 375,000.00 | $ - | Built | 45.5061 | -73.494321 |
Longueuil | Quebec | Shelter | 7 | 7 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,900,000.00 | $ 2,900,000.00 | $ - | Financial Commitments | 45.5135 | -73.4329 |
Lower Post | British Columbia | Daylu Dena Council Housing Project | 5 | 5 | 2 | National Housing Co-Investment Fund | Daylu Dena Council | 10/3/2023 | New Construction | Indigenous Group | $ 1,674,488.00 | $ 1,674,488.00 | $ - | Under Construction | 59.9250 | -128.49272 |
Lower Post | British Columbia | Shelter | 16 | 16 | - | National Housing Co-Investment Fund | Provincial Rental Housing Corporation (PRHC) | 3/9/2023 | New Construction | Indigenous Group | $ 1,310,120.00 | $ 1,310,120.00 | $ - | Built | 59.9232 | -128.4981229 |
Nelson House 170 | Manitoba | Nisichawayasihk Cree Nation Repairs | 5 | 2 | 2 | National Housing Co-Investment Fund | Nisichawayasihk Cree Nation | 1/25/2022 | Repairs | Indigenous Governing Body | $ 90,000.00 | $ 90,000.00 | $ - | Built | 55.7919 | -98.884575 |
Lynn Lake | Manitoba | MCFN RHI | 15 | 15 | - | Rapid Housing Initiative 2 | Marcel Colomb First Nation | 5/29/2023 | New Construction | Indigenous Governing Body | $ 5,883,439.12 | $ 5,883,439.12 | $ - | Built | 56.8478 | -101.039492 |
Malartic | Quebec | Implantation d'un centre de crise régional à Malartic RHI2 | 6 | 6 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 980,000.00 | $ 980,000.00 | $ - | Under Construction | 48.1445 | -78.117865 |
Malartic | Quebec | SHQ - Les Habitations Tournesols au Soleil | 19 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,701,484.00 | $ 1,701,484.00 | $ - | Built | 48.1381 | -78.1250299 |
Manawan | Quebec | ICRL Manawan | 12 | 12 | - | Rapid Housing Initiative | Les Atikamekw de Manawan | 1/22/2021 | New Construction | Indigenous Group | $ 2,012,850.00 | $ 2,012,850.00 | $ - | Under Construction | 47.2236 | -74.3910049 |
Marcelin | Saskatchewan | Muskeg Lake Cree Nation RHI Project | 4 | 4 | - | Rapid Housing Initiative 2 | Muskeg Lake Cree Nation | 9/7/2023 | Renewals | Indigenous Governing Body | $ 302,286.20 | $ 302,286.20 | $ - | Built | 53.0009 | -106.90621 |
Markham | Ontario | Shelter | 31 | - | 8 | National Housing Co-Investment Fund | Project Hostel o/a Yellow Brick House | 12/12/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,220,900.00 | $ 1,220,900.00 | $ - | Under Construction | 43.8561 | -79.337 |
Marystown | Newfoundland and Labrador | Shelter | 20 | - | 20 | National Housing Co-Investment Fund | Grace Sparkes House Incorporated | 5/27/2022 | New Construction | Not-for-profit housing org/Co-op | $ 5,268,845.00 | $ 5,268,845.00 | $ - | Under Construction | 47.1670 | -55.167 |
Matimekosh | Quebec | Construction rapide de 11 maisons à Matimekush | 11 | 11 | - | Rapid Housing Initiative | La Nation Innu Matimekush-Lac John | 1/22/2021 | New Construction | Indigenous Group | $ 3,722,399.01 | $ 3,722,399.01 | $ - | Built | 54.8078 | -66.8141 |
Mayo | Yukon | Na-Cho Nyak Dun Fourplexes for Vulnerable Citizens | 8 | 8 | - | Rapid Housing Initiative 2 | First Nation of Na-cho Nyak Dun | 6/25/2021 | New Construction | Indigenous Governing Body | $ 1,139,000.00 | $ 1,139,000.00 | $ - | Built | 63.5943 | -135.896492 |
Meadow Lake | Saskatchewan | Meadow Lake KidsFirst | 4 | 4 | - | National Housing Co-Investment Fund | Meadow Lake Native Urban Housing Corp | 6/6/2022 | New Construction | Not-for-profit housing org/Co-op | $ 245,281.00 | $ 245,281.00 | $ - | Built | 54.1277 | -108.4400717 |
Meota No. 468 | Saskatchewan | Saulteaux 2020 RHI | 15 | - | - | Rapid Housing Initiative | Saulteaux First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 3,829,663.00 | $ 3,829,663.00 | $ - | Built | 53.0356 | -108.455365 |
Mercier | Quebec | Chez Nous solidaire RHI2 | 19 | 19 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,300,000.00 | $ 5,300,000.00 | $ - | Financial Commitments | 45.3094 | -73.746051 |
Messines | Quebec | Place St-Raphaël (Messines) UI560 | 8 | 8 | - | National Housing Co-Investment Fund | Communauté Autochtone de Maniwaki | 5/23/2023 | Repairs | Indigenous Group | $ 425,534.00 | $ 425,534.00 | $ - | Under Construction | 46.2815 | -76.010082 |
Milton | Ontario | 154 Bronte St | 24 | 24 | 3 | National Housing Co-Investment Fund | Victoria Park Community Homes Inc. | 5/21/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,551,320.00 | $ 367,320.00 | $ 3,184,000.00 | Built | 43.6613 | -79.4551131 |
Miramichi | New Brunswick | ESAH Development | 21 | 11 | 4 | National Housing Co-Investment Fund | Eastside Special Care Home Inc. | 2/3/2023 | New Construction | Private Enterprise/Builder/Developer | $ 2,421,853.00 | $ 148,667.00 | $ 2,273,186.00 | Under Construction | 47.0380 | -65.4528864 |
Miramichi | New Brunswick | Shelter | 20 | 14 | 2 | National Housing Co-Investment Fund | Belleterre Community Partners Incorporated | 2/3/2023 | New Construction | Not-for-profit housing org/Co-op | $ 2,461,100.00 | $ 213,476.00 | $ 2,247,624.00 | Under Construction | 47.0296 | -65.5059 |
Miramichi | New Brunswick | Shelter | 8 | 8 | 3 | National Housing Co-Investment Fund | Miramichi Emergency Centre for Women Inc | 2/3/2023 | New Construction | Not-for-profit housing org/Co-op | $ 1,744,677.00 | $ 1,744,677.00 | $ - | Built | 47.0296 | -65.5059 |
Mississauga | Ontario | Arbour Mill Expansion | 6 | 6 | - | Rapid Housing Initiative 2 | The Regional Municipality of Peel | 7/15/2022 | New Construction | Municipality | $ 2,044,049.00 | $ 2,044,049.00 | $ - | Under Construction | 43.5764 | -79.6224698 |
Mississauga | Ontario | Streetsville Supportive Housing | 40 | 40 | - | Rapid Housing Initiative 2 | The Regional Municipality of Peel | 7/15/2022 | New Construction | Municipality | $ 20,841,554.00 | $ 20,841,554.00 | $ - | Under Construction | 43.5794 | -79.7123834 |
Mississauga | Ontario | Shelter | 10 | - | - | Rapid Housing Initiative | The Regional Municipality of Peel | 6/25/2021 | New Construction | Municipality | $ 2,365,914.00 | $ 2,365,914.00 | $ - | Under Construction | 43.5890 | -79.6441 |
Mistissini | Quebec | Portfolio Cree - Mistissini | 10 | 30 | - | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 2,979,430.00 | $ 2,979,430.00 | $ - | Built | 50.4204 | -73.870214 |
Moncton | New Brunswick | Downtown City Housing Renovation Project | 47 | 47 | - | National Housing Co-Investment Fund | Downtown City Housing Inc. | 1/13/2023 | Repairs | Not-for-profit housing org/Co-op | $ 1,350,503.00 | $ - | $ 1,350,503.00 | Built | 46.0854 | -64.7803375 |
Moncton | New Brunswick | Northeast Moncton Community Hub & Housing | 20 | 20 | 4 | National Housing Co-Investment Fund | John Howard Society of Southeastern New Brunswick | 1/13/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,998,412.00 | $ 435,374.00 | $ 3,563,038.00 | Built | 46.1176 | -64.7801229 |
Moncton | New Brunswick | Birch Meadows | 76 | 50 | 12 | Rental Construction Financing Initiative | J.N. Lafford Realty Inc. | 3/30/2021 | New Construction | Private Enterprise/Builder/Developer | $ 15,890,000.00 | $ - | $ 15,890,000.00 | Built | 46.1059 | -64.7390179 |
Moncton | New Brunswick | Rising Tide Community Initiatives | 65 | - | - | Rapid Housing Initiative | City of Moncton | 3/26/2021 | New Construction | Municipality | $ 3,428,491.00 | $ 3,428,491.00 | $ - | Built | 46.0968 | -64.7953067 |
Moncton | New Brunswick | MacDonald Centre for Ind. Living | 40 | 40 | 10 | National Housing Co-Investment Fund | Le Centre de vie autonome MacDonald Inc/MacDonald Centre for Independent Living Inc. | 2/3/2020 | Repairs | Not-for-profit housing org/Co-op | $ 1,383,419.00 | $ 1,383,419.00 | $ - | Built | 46.0859 | -64.7898153 |
Montague | Prince Edward Island | Montague Place Apt | 45 | 30 | 9 | National Housing Co-Investment Fund | Pan American Properties Inc. | 3/3/2020 | New Construction | Private Enterprise/Builder/Developer | $ 9,337,986.00 | $ 329,837.00 | $ 9,008,149.00 | Built | 46.1733 | -62.6569027 |
Montana 139 | Alberta | Montana First Nation Rapid Housing Project | 20 | 20 | - | Rapid Housing Initiative 2 | Montana First Nation | 4/21/2023 | New Construction | Indigenous Governing Body | $ 5,650,740.00 | $ 5,650,740.00 | $ - | Under Construction | 52.8344 | -113.447207 |
Mont-Laurier | Quebec | Maison Lyse Beauchamp - Le Mirador RHI2 | 10 | 16 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Under Construction | 46.5493 | -75.49888 |
Mont-Laurier | Quebec | La Passe-R-Elle RHI2 | 6 | 7 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,200,000.00 | $ 3,200,000.00 | $ - | Financial Commitments | 46.5443 | -75.48949 |
Montréal | Quebec | ICRL - Pré-CARE RHI2 | 20 | 20 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,240,000.00 | $ 3,240,000.00 | $ - | Built | 45.5237 | -73.55356 |
Montréal | Quebec | Dauphinelle 3 (ACL-05570) RHI2 | 14 | 14 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 7,800,000.00 | $ 7,800,000.00 | $ - | Financial Commitments | 45.5302 | -73.569917 |
Montréal | Quebec | 8790 Lajeunesse RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 3,400,000.00 | $ 3,400,000.00 | $ - | Under Construction | 45.5472 | -73.640807 |
Montréal | Quebec | OBM - Pie-IX - 56e RHI2 | 27 | 27 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 6,100,000.00 | $ 6,100,000.00 | $ - | Financial Commitments | 45.5831 | -73.628495 |
Montréal | Quebec | Vilavi Montcalm Projet RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,500,000.00 | $ 2,500,000.00 | $ - | Financial Commitments | 45.5179 | -73.554953 |
Montréal | Quebec | Transitional Housing / Afrique au Féminin | 9 | 9 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 4,800,000.00 | $ 4,800,000.00 | $ - | Financial Commitments | 45.5251 | -73.621751 |
Montréal | Quebec | Maison l'Exode - Agrandissement Pavillon André-Dumont RHI2 | 5 | 5 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 955,000.00 | $ 955,000.00 | $ - | Under Construction | 45.5553 | -73.548577 |
Montréal | Quebec | Les Colocs de l'Ouest - Projet 16789 – Boulevard Pierrefonds RHI2 | 11 | 11 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,470,000.00 | $ 4,470,000.00 | $ - | Financial Commitments | 45.4700 | -73.874425 |
Montréal | Quebec | Maison des TAPAJEURs RHI2 | 22 | 22 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 6,210,000.00 | $ 6,210,000.00 | $ - | Financial Commitments | 45.5182 | -73.564221 |
Montréal | Quebec | Nouvelle-Étape - Phase 2 RHI2 | 9 | 9 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 382,332.00 | $ 382,332.00 | $ - | Built | 45.6090 | -73.626338 |
Montréal | Quebec | Transitional Housing / Agir en Amont | 28 | 28 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 10,300,000.00 | $ 10,300,000.00 | $ - | Under Construction | 45.5201 | -73.561543 |
Montréal | Quebec | Stream A Montréal - OSBL Habitation Montréal (Organisme Sans But Lucratif) | 28 | 28 | - | Rapid Housing Initiative | Ville de Montréal | 7/17/2023 | Renewals | Municipality | $ 820,912.00 | $ 820,912.00 | $ - | Built | 45.5377 | -73.562892 |
Montréal | Quebec | Stream A Montréal - Maison Shetty | 22 | 22 | - | Rapid Housing Initiative | Ville de Montréal | 6/27/2023 | Repairs | Municipality | $ 4,998,328.00 | $ 4,998,328.00 | $ - | Built | 45.5174 | -73.560041 |
Montréal | Quebec | Stream A Montréal - Projet de logements permanents PAQ (Projets Autochtones du Québec) | 22 | 18 | - | Rapid Housing Initiative | Ville de Montréal | 2/27/2023 | Repairs | Municipality | $ 4,699,816.00 | $ 4,699,816.00 | $ - | Built | 45.5137 | -73.5545907 |
Montréal | Quebec | OMHM - métro Rosemont | 193 | 193 | - | National Housing Co-Investment Fund | Office municipal d'habitation de Montréal | 1/16/2023 | New Construction | Municipality | $ 9,650,000.00 | $ 9,650,000.00 | $ - | Built | 45.5308 | -73.5986025 |
Montréal | Quebec | Coopérative Milieu de l'Île (MIL) | 91 | 91 | - | National Housing Co-Investment Fund | Coopérative Milieu de l'Île (MIL) | 11/25/2022 | New Construction | Not-for-profit housing org/Co-op | $ 4,700,000.00 | $ 4,700,000.00 | $ - | Built | 45.5123 | -73.5998489 |
Montréal | Quebec | Shelter | 4768 | 4,751 | 1,259 | National Housing Co-Investment Fund | Société d'habitation et de développement de Montréal (SHDM) | 10/24/2022 | Repairs | Not-for-profit housing org/Co-op | $ 69,000,000.00 | $ 27,600,000.00 | $ 41,400,000.00 | Under Construction | 45.5019 | -73.5674 |
Montréal | Quebec | Stream A Montréal - Maison Tangente | 6 | 6 | - | Rapid Housing Initiative | Ville de Montréal | 10/14/2022 | Renewals | Municipality | $ 1,779,597.80 | $ 1,779,597.80 | $ - | Built | 45.5501 | -73.5362677 |
Montréal | Quebec | Demain Montréal (C40 Lauréat) | 327 | 52 | 327 | Rental Construction Financing Initiative | Demain Montréal, s.e.c. | 6/14/2022 | New Construction | Private Enterprise/Builder/Developer | $ 135,000,000.00 | $ - | $ 135,000,000.00 | Under Construction | 45.4940 | -73.5534186 |
Montréal | Quebec | Coopérative d'habitation Laurentienne | 170 | 85 | 57 | National Housing Co-Investment Fund | Coopérative d'Habitation Laurentienne | 5/31/2022 | New Construction | Not-for-profit housing org/Co-op | $ 6,760,000.00 | $ 6,760,000.00 | $ - | Under Construction | 45.5205 | -73.7063611 |
Montréal | Quebec | Shelter | 20 | 20 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec | 4/29/2022 | New Construction | Province | $ 11,710,000.00 | $ 11,710,000.00 | $ - | Under Construction | 45.5019 | -73.5674 |
Montréal | Quebec | Stream A Montréal - Maison CROSS ROADS | 15 | 15 | - | Rapid Housing Initiative | Ville de Montréal | 3/11/2022 | New Construction | Municipality | $ 5,205,427.00 | $ 5,205,427.00 | $ - | Built | 45.4678 | -73.5933253 |
Montréal | Quebec | UTILE Angus | 123 | 37 | 26 | National Housing Co-Investment Fund | Utile Angus | 6/3/2021 | New Construction | Not-for-profit housing org/Co-op | $ 20,135,027.00 | $ - | $ 20,135,027.00 | Under Construction | 45.5446 | -73.5671779 |
Montréal | Quebec | Stream A Montréal - Vilavi 1610 Saint-André | 10 | 10 | - | Rapid Housing Initiative | Ville de Montréal | 5/11/2021 | Repairs | Municipality | $ 2,011,117.00 | $ 2,011,117.00 | $ - | Built | 45.5173 | -73.5605624 |
Montréal | Quebec | Stream A Montréal - Studios Mercier | 20 | 19 | - | Rapid Housing Initiative | Ville de Montréal | 4/15/2021 | New Construction | Municipality | $ 4,579,839.00 | $ 4,579,839.00 | $ - | Built | 45.5985 | -73.5217546 |
Montréal | Quebec | Shelter | 29 | 29 | - | Rapid Housing Initiative | Ville de Montréal | 4/2/2021 | New Construction | Municipality | $ 10,865,000.00 | $ 10,865,000.00 | $ - | Built | 45.5019 | -73.5674 |
Montréal | Quebec | Stream A Montréal - Projet Avenue du Parc | 31 | 24 | - | Rapid Housing Initiative | Ville de Montréal | 4/2/2021 | Repairs | Municipality | $ 6,597,203.00 | $ 6,597,203.00 | $ - | Built | 45.5170 | -73.5904189 |
Montréal | Quebec | Mission Old Brewery - 2801 de Rouen RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec | 2/4/2021 | New Construction | Province | $ 3,430,000.00 | $ 3,430,000.00 | $ - | Financial Commitments | 45.5372 | -73.5540973 |
Montréal | Quebec | SHQ - Centre NAHA - Maison Lacordaire | 27 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,721,000.00 | $ 1,721,000.00 | $ - | Built | 45.5709 | -73.5370839 |
Montréal | Quebec | SHQ - Jean Brien (RESAC - Phase VIII) | 20 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Renewals | Province | $ 3,373,000.00 | $ 3,373,000.00 | $ - | Under Construction | 45.5301 | -73.5680773 |
Montréal | Quebec | SHQ - La Maison Benoit Labre | 36 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 7,650,000.00 | $ 7,650,000.00 | $ - | Under Construction | 45.4806 | -73.5785921 |
Montréal | Quebec | SHQ - Loge Accès - Phase VI - Maison de chambres | 15 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Renewals | Province | $ 2,371,700.00 | $ 2,371,700.00 | $ - | Built | 45.5393 | -73.5412501 |
Montréal | Quebec | SHQ - Maison du Sac-à -Dos | 37 | 32 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 10,955,000.00 | $ 10,955,000.00 | $ - | Under Construction | 45.5120 | -73.5617014 |
Montréal | Quebec | SHQ - Maison Iberville | 10 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,399,100.00 | $ 1,399,100.00 | $ - | Built | 45.5578 | -73.6118366 |
Montréal | Quebec | SHQ - Maison Saint-Dominique / Maison Shelley | 40 | 37 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 7,013,552.00 | $ 7,013,552.00 | $ - | Under Construction | 45.5641 | -73.6086707 |
Montréal | Quebec | SHQ - Soleil d'Aoura (CFIQ) | 25 | 23 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 3,014,000.00 | $ 3,014,000.00 | $ - | Built | 45.6081 | -73.5110694 |
Montréal | Quebec | SHQ - Vilavi - Lespérance | 18 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,776,736.00 | $ 1,776,736.00 | $ - | Financial Commitments | 45.5383 | -73.5520377 |
Montréal | Quebec | UTILE | 175 | - | - | Innovation Fund | Services UTILE | 4/17/2019 | 0 | Private Enterprise/Builder/Developer | $ - | $ - | $ - | Under Construction | 45.5289 | -73.565533 |
Morley | Alberta | Wesley First Nation Stick built 2021 | 5 | 5 | - | Rapid Housing Initiative 2 | Wesley First Nation | 2/3/2023 | New Construction | Indigenous Governing Body | $ 858,407.00 | $ 858,407.00 | $ - | Built | 51.1615 | -114.850968 |
Muskoday First Nation | Saskatchewan | Muskoday First Nation | 6 | - | - | Rapid Housing Initiative | Muskoday First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 1,627,932.00 | $ 1,627,932.00 | $ - | Built | 53.0703 | -105.54084 |
Nakusp | British Columbia | Nakusp Affordable Housing Project | 10 | 3 | 3 | National Housing Co-Investment Fund | Arrow & Slocan Lakes Community Services | 12/17/2019 | New Construction | Not-for-profit housing org/Co-op | $ 841,061.00 | $ 841,061.00 | $ - | Built | 50.2396 | -117.797937 |
Nanaimo | British Columbia | Sunfield Manor | 62 | 62 | 12 | National Housing Co-Investment Fund | Woodgrove Senior Citizens Housing Society | 1/18/2023 | New Construction | Not-for-profit housing org/Co-op | $ 2,659,956.00 | $ 2,659,956.00 | $ - | Built | 49.1830 | -123.9670601 |
Naujaat | Nunavut | Nunavut portfolio - Naujaat 3 x 5-plex 2020-2021 | 15 | 15 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 5,618,284.64 | $ 5,618,284.64 | $ - | Built | 66.5262 | -86.23706 |
Neepawa | Manitoba | Kinsmen Kourts II | 48 | 15 | 48 | National Housing Co-Investment Fund | Neepawa Kinsmen Seniors Citizens Housing Inc. | 7/17/2020 | New Construction | Not-for-profit housing org/Co-op | $ 10,064,829.00 | $ 265,029.00 | $ 9,799,800.00 | Built | 50.2299 | -99.4644547 |
Nelson House 170 | Manitoba | Nisichawayasihk Cree Nation Housing Initiative | 2 | 2 | - | Rapid Housing Initiative 2 | Nisichawayasihk Cree Nation | 5/29/2023 | New Construction | Indigenous Governing Body | $ 535,114.00 | $ 535,114.00 | $ - | Built | 55.7919 | -98.884575 |
Nemaska | Quebec | Portfolio Cree - Nemaska | 5 | 10 | - | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,583,555.00 | $ 1,583,555.00 | $ - | Built | 51.6861 | -76.2598493 |
Nequatque | British Columbia | N'Quatqua Hunter Jack 10 unit On-reserve | 10 | 10 | - | National Housing Co-Investment Fund | N’Quatqua Social Housing Society | 5/25/2023 | New Construction | Indigenous Non-Profit Organization | $ 1,000,000.00 | $ 1,000,000.00 | $ - | Built | 50.3598 | -122.920455 |
New Hazelton | British Columbia | Shelter | 13 | 7 | 3 | National Housing Co-Investment Fund | Provincial Rental Housing Corporation (PRHC) | 3/9/2023 | New Construction | Province | $ 2,084,496.70 | $ 2,084,496.70 | $ - | Built | 55.2467 | -127.586446 |
New Westminster | British Columbia | Shelter | 13 | - | - | National Housing Co-Investment Fund | WOMEN IN NEED GAINING STRENGTH | 2/7/2023 | Repairs | Not-for-profit housing org/Co-op | $ 205,970.00 | $ 205,970.00 | $ - | Built | 49.2196 | -122.9084602 |
New Westminster | British Columbia | Shelter | 12 | - | - | National Housing Co-Investment Fund | WOMEN IN NEED GAINING STRENGTH | 2/7/2023 | Repairs | Not-for-profit housing org/Co-op | $ 138,715.00 | $ 138,715.00 | $ - | Built | 49.2196 | -122.9084602 |
New Westminster | British Columbia | Brewery District, Building 7 | 294 | 70 | 32 | Rental Construction Financing Initiative | The Brewery District Building 7 Limited Partnership | 7/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 135,000,000.00 | $ - | $ 135,000,000.00 | Under Construction | 49.2249 | -122.8905077 |
New Westminster | British Columbia | Wesgroup Properties - 100 Braid Street | 414 | 94 | 43 | Rental Construction Financing Initiative | Sapperton Rousseau Developments LP | 7/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 160,000,000.00 | $ - | $ 160,000,000.00 | Under Construction | 49.2312 | -122.885366 |
Newcastle | Ontario | Parkview Housing | 37 | 30 | 8 | National Housing Co-Investment Fund | Newcastle Lodge for Senior and Family Dwellings | 5/31/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,126,942.51 | $ 1,303,790.00 | $ 1,823,153.00 | Built | 43.9166 | -78.5922705 |
Newmarket | Ontario | Deerfield - Phase 3 | 175 | 106 | 27 | Rental Construction Financing Initiative | Deerfield 3 Limited Partnership | 8/10/2023 | New Construction | Private Enterprise/Builder/Developer | $ 77,000,000.00 | $ - | $ 77,000,000.00 | Under Construction | 44.0554 | -79.471783 |
Newmarket | Ontario | Deerfield, Newmarket Phase 1 | 216 | 19 | 22 | Rental Construction Financing Initiative | Deerfield 1 Limited Partnership | 8/4/2020 | New Construction | Private Enterprise/Builder/Developer | $ 79,000,000.00 | $ - | $ 79,000,000.00 | Under Construction | 44.0559 | -79.471553 |
Norfolk County | Ontario | Dogwood Suites | 50 | 50 | - | Rapid Housing Initiative 2 | Corporation of Norfolk County | 7/7/2022 | Repairs | Municipality | $ 10,118,742.00 | $ 10,118,742.00 | $ - | Built | 42.8364 | -80.3032445 |
North Saanich | British Columbia | Pauquachin RHI Project 2020 | 12 | - | - | Rapid Housing Initiative | Pauquachin First Nation | 5/9/2023 | New Construction | Indigenous Group | $ 5,018,146.00 | $ 5,018,146.00 | $ - | Built | 48.6276 | -123.4558026 |
North Vancouver | British Columbia | Emery Village Affordable Rental Building | 84 | 42 | 84 | Rental Construction Financing Initiative | Mosaic Lynn Living Limited Partnership | 8/16/2023 | New Construction | Private Enterprise/Builder/Developer | $ 39,800,000.00 | $ - | $ 39,800,000.00 | Built | 49.3304 | -123.038612 |
Norway House 17 | Manitoba | Norway House Container Home Development | 28 | - | - | Rapid Housing Initiative | Norway House Cree Nation | 5/18/2021 | New Construction | Indigenous Group | $ 3,929,614.80 | $ 3,929,614.80 | $ - | Built | 53.9821 | -97.832932 |
Oakville | Ontario | 263 Kerr Street Seniors Supportive Housing | 52 | - | - | Rapid Housing Initiative 3 | Halton Region | 9/11/2023 | New Construction | Municipality | $ 9,309,329.00 | $ 9,309,329.00 | $ - | Financial Commitments | 43.4425 | -79.679183 |
O'Chiese 203 | Alberta | O'Chiese First Nation - Renovation Application | 4 | 4 | - | Rapid Housing Initiative 2 | O'Chiese First Nation | 2/3/2023 | Repairs | Indigenous Governing Body | $ 496,355.15 | $ 496,355.15 | $ - | Built | 52.3708 | -114.917602 |
O'Chiese 203 | Alberta | O'Chiese First Nation - Rural New Build Application | 6 | 6 | - | Rapid Housing Initiative 2 | O'Chiese First Nation | 2/3/2023 | New Construction | Indigenous Governing Body | $ 1,891,208.10 | $ 1,891,208.10 | $ - | Built | 52.3708 | -114.917602 |
O'Chiese 203 | Alberta | O'Chiese First Nation - Townsite New Build Application | 8 | 8 | - | Rapid Housing Initiative 2 | O'Chiese First Nation | 2/3/2023 | New Construction | Indigenous Governing Body | $ 3,705,864.80 | $ 3,705,864.80 | $ - | Built | 52.3708 | -114.917602 |
O'Leary | Prince Edward Island | O'Leary Seniors Residence | 50 | 50 | 50 | National Housing Co-Investment Fund | Community Seniors Co-operative Limited | 5/26/2023 | New Construction | Not-for-profit housing org/Co-op | $ 9,574,319.00 | $ 2,871,146.00 | $ 6,703,173.00 | Under Construction | 46.7026 | -64.230457 |
Onion Lake 119-1 | Saskatchewan | OLCN RHI2 RTM | 20 | 20 | - | Rapid Housing Initiative 2 | Onion Lake Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 4,125,929.00 | $ 4,125,929.00 | $ - | Built | 53.6449 | -109.988714 |
Onion Lake 119-1 | Saskatchewan | OLCN RHI2 Single family stick built | 25 | 25 | - | Rapid Housing Initiative 2 | Onion Lake Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 5,288,056.00 | $ 5,288,056.00 | $ - | Built | 53.6449 | -109.988714 |
Opaskwayak Cree Nation 21E | Manitoba | OCN 50 Unit Affordable Housing Project | 50 | 50 | - | Rapid Housing Initiative 2 | Opaskwayak Cree Nation | 5/29/2023 | New Construction | Indigenous Governing Body | $ 4,839,285.00 | $ 4,839,285.00 | $ - | Under Construction | 53.8743 | -101.329323 |
Orillia | Ontario | Building Hope | 20 | 20 | 48 | National Housing Co-Investment Fund | Orillia Christian Centre | 4/26/2019 | New Construction | Not-for-profit housing org/Co-op | $ 5,693,000.00 | $ 5,693,000.00 | $ - | Built | 44.6057 | -79.4110846 |
Oromocto | New Brunswick | Oromocto First Nation Housing Initiative | 4 | 4 | - | Rapid Housing Initiative | Oromocto First Nation | 5/24/2023 | New Construction | Indigenous Group | $ 498,350.00 | $ 498,350.00 | $ - | Built | 45.8444 | -66.470646 |
Oshawa | Ontario | Shelter | 33 | - | 11 | National Housing Co-Investment Fund | Sedna Women's Shelter & Support Services Inc | 6/15/2023 | New Construction | Not-for-profit housing org/Co-op | $ 14,105,066.65 | $ 14,105,066.65 | $ - | Under Construction | 43.8971 | -78.8658 |
Oshawa | Ontario | Region of Durham - Oshawa Microhomes | 10 | 10 | - | Rapid Housing Initiative 2 | Regional Municipality of Durham | 3/2/2022 | New Construction | Municipality | $ 1,200,000.00 | $ 1,200,000.00 | $ - | Built | 43.8919 | -78.853188 |
Oshawa | Ontario | Region of Durham - DRNPHC Normandy Towns | 24 | - | - | Rapid Housing Initiative 2 | Regional Municipality of Durham | 1/6/2022 | New Construction | Municipality | $ 5,590,464.00 | $ 5,590,464.00 | $ - | Under Construction | 43.8878 | -78.8422731 |
Oshawa | Ontario | 440 Bloor Street East | 21 | 21 | 6 | National Housing Co-Investment Fund | Cornerstone Community Association Durham Incorporated | 4/21/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,151,272.00 | $ 351,272.00 | $ 1,800,000.00 | Built | 43.8842 | -78.840249 |
Osnaburgh 63B | Ontario | Mish Rapid Housing | 5 | - | - | Rapid Housing Initiative | Mishkeegogamang First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 764,048.00 | $ 764,048.00 | $ - | Built | 51.2186 | -90.2118178 |
Ottawa | Ontario | Salus - 56 Capilano | 54 | - | - | Rapid Housing Initiative 3 | City of Ottawa | 8/31/2023 | New Construction | Municipality | $ 18,553,914.00 | $ 18,553,914.00 | $ - | Financial Commitments | 45.3566 | -75.73367 |
Ottawa | Ontario | 93 Norman Street | 122 | 67 | 16 | Rental Construction Financing Initiative | Tamarack (Norman) Corporation | 11/22/2022 | New Construction | Private Enterprise/Builder/Developer | $ 48,100,000.00 | $ - | $ 48,100,000.00 | Under Construction | 45.4000 | -75.7097863 |
Ottawa | Ontario | Forward Avenue | 49 | 19 | 6 | National Housing Co-Investment Fund | Centretown Citizens Ottawa Corporation | 11/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 12,839,190.00 | $ 3,658,281.00 | $ 9,180,909.00 | Under Construction | 45.4076 | -75.7317427 |
Ottawa | Ontario | JHS Carling | 40 | 40 | 8 | National Housing Co-Investment Fund | John Howard Society of Ottawa | 11/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,913,000.00 | $ 2,439,000.00 | $ 1,474,000.00 | Built | 45.4005 | -75.7018974 |
Ottawa | Ontario | Stream A Ottawa - Jockvale Road - Phase 1 | 32 | 32 | - | Rapid Housing Initiative | City of Ottawa | 11/22/2022 | New Construction | Municipality | $ 5,855,626.00 | $ 5,855,626.00 | $ - | Under Construction | 45.2636 | -75.7368813 |
Ottawa | Ontario | Stream A Ottawa - Lisgar Street | 29 | 29 | - | Rapid Housing Initiative | City of Ottawa | 11/22/2022 | New Construction | Municipality | $ 13,916,362.29 | $ 13,916,362.29 | $ - | Under Construction | 45.4143 | -75.7026846 |
Ottawa | Ontario | 715 Mikinak Road (Wateridge Village) | 271 | 138 | 57 | National Housing Co-Investment Fund | Ottawa Community Housing Corporation | 11/14/2022 | New Construction | Municipality | $ 73,395,700.00 | $ 7,729,241.00 | $ 65,666,459.00 | Under Construction | 45.4519 | -75.631566 |
Ottawa | Ontario | 216 Murray Street Phase 2 | 8 | - | - | Rapid Housing Initiative 2 | City of Ottawa | 6/14/2022 | New Construction | Municipality | $ 2,521,390.00 | $ 2,521,390.00 | $ - | Under Construction | 45.4313 | -75.689242 |
Ottawa | Ontario | 256 St Denis St | 12 | - | - | Rapid Housing Initiative 2 | City of Ottawa | 6/14/2022 | New Construction | Municipality | $ 4,195,117.00 | $ 4,195,117.00 | $ - | Under Construction | 45.4405 | -75.663031 |
Ottawa | Ontario | 44 Eccles Street | 38 | - | - | Rapid Housing Initiative 2 | City of Ottawa | 6/14/2022 | Renewals | Municipality | $ 15,727,190.00 | $ 15,727,190.00 | $ - | Under Construction | 45.4086 | -75.70927 |
Ottawa | Ontario | Shelter | 35 | 23 | 7 | National Housing Co-Investment Fund | The Incorporated Synod of The Diocese of Ottawa | 6/6/2022 | New Construction | Not-for-profit housing org/Co-op | $ 6,640,279.00 | $ 1,000,000.00 | $ 5,640,279.00 | Under Construction | 45.4215 | -75.6972 |
Ottawa | Ontario | Claridge Royale | 489 | 300 | 75 | Rental Construction Financing Initiative | Claridge Homes (245 Rideau Phase 2) LP | 8/3/2021 | New Construction | Private Enterprise/Builder/Developer | $ 161,370,000.00 | $ - | $ 161,370,000.00 | Under Construction | 45.4286 | -75.6871819 |
Ottawa | Ontario | Greatwise Playfair Residences | 120 | 120 | 18 | Rental Construction Financing Initiative | Playfair Residences Limited | 7/12/2021 | New Construction | Private Enterprise/Builder/Developer | $ 33,772,500.00 | $ - | $ 33,772,500.00 | Built | 45.3885 | -75.650377 |
Ottawa | Ontario | Shelter | 698 | 211 | - | National Housing Co-Investment Fund | Ottawa Community Housing Corporation | 9/10/2020 | New Construction | Not-for-profit housing org/Co-op | $ 167,915,638.00 | $ 10,819,000.00 | $ 157,096,638.00 | Under Construction | 45.4215 | -75.6972 |
Ottawa | Ontario | SoHo Italia | 250 | 125 | 38 | Rental Construction Financing Initiative | Soho Preston Limited Partnership | 8/17/2020 | New Construction | Private Enterprise/Builder/Developer | $ 86,400,000.00 | $ - | $ 86,400,000.00 | Under Construction | 45.3984 | -75.7085067 |
Ottawa | Ontario | Claridge Homes | 321 | 321 | 33 | Rental Construction Financing Initiative | Claridge Homes (Albert) LP | 2/19/2020 | New Construction | Private Enterprise/Builder/Developer | $ 115,000,000.00 | $ - | $ 115,000,000.00 | Under Construction | 45.4181 | -75.7051208 |
Ottawa | Ontario | Shepherds of Good Hope | 42 | 42 | - | National Housing Co-Investment Fund | Shepherds of Good Hope | 10/6/2019 | New Construction | Not-for-profit housing org/Co-op | $ 5,264,605.00 | $ 764,670.00 | $ 4,499,935.00 | Built | 45.4451 | -75.6358458 |
Ottawa | Ontario | Veterans' House: The Andy Carswell Building | 40 | 40 | 9 | National Housing Co-Investment Fund | Multifaith Housing Initiative | 9/7/2019 | New Construction | Not-for-profit housing org/Co-op | $ 6,530,845.00 | $ 4,800,000.00 | $ 1,730,845.00 | Built | 45.4518 | -75.6302681 |
Ottawa | Ontario | King's Daughters and Sons Apartments | 58 | 58 | 10 | Rental Construction Financing Initiative | THE KING’S DAUGHTERS AND SONS APARTMENTS | 8/28/2019 | New Construction | Not-for-profit housing org/Co-op | $ 7,840,296.00 | $ - | $ 7,840,296.00 | Built | 45.3996 | -75.6999192 |
Ottawa | Ontario | 2887 Riverside Drive project | 39 | 39 | - | National Housing Co-Investment Fund | YOUTH SERVICES BUREAU OF OTTAWA | 3/7/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,125,000.00 | $ - | $ 3,125,000.00 | Under Construction | 45.3695 | -75.6895701 |
Ottawa | Ontario | Shelter | 271 | 271 | 55 | Federal Lands Initiative | City of Ottawa | 2/11/2019 | New Construction | Municipality | $ 4,633,965.00 | $ 4,633,965.00 | $ - | Under Construction | 45.4215 | -75.6972 |
Ottawa | Ontario | Centretown Citizens Ottawa Corporation project | 16 | 16 | 3 | Rental Construction Financing Initiative | Centretown Citizens Ottawa Corporation | 9/21/2018 | New Construction | Not-for-profit housing org/Co-op | $ 3,968,000.00 | $ - | $ 3,968,000.00 | Built | 45.4085 | -75.6968633 |
Ottawa | Ontario | Clarige Homes | 227 | 212 | 43 | Rental Construction Financing Initiative | Claridge Homes (70 Gloucester) Inc | 9/21/2018 | New Construction | Private Enterprise/Builder/Developer | $ 70,783,000.00 | $ - | $ 70,783,000.00 | Built | 45.4192 | -75.6949406 |
Oujé-Bougoumou | Quebec | Portfolio Cree - Ouje-Bougoumou | 5 | 10 | - | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,489,715.00 | $ 1,489,715.00 | $ - | Built | 49.9240 | -74.817467 |
Oxford House 24 | Manitoba | BCN 6-unit conversion | 6 | 6 | - | Rapid Housing Initiative 2 | Bunibonibee Cree Nation | 5/29/2023 | Repairs | Indigenous Governing Body | $ 900,000.00 | $ 900,000.00 | $ - | Built | 54.7168 | -96.27547 |
Paquetville | New Brunswick | Les Logements du Manoir EBP | 12 | 12 | 3 | National Housing Co-Investment Fund | Les Logements du Manoir EBP Inc. | 6/17/2019 | New Construction | Not-for-profit housing org/Co-op | $ 1,178,390.00 | $ 50,210.00 | $ 1,128,180.00 | Built | 47.6691 | -65.1001242 |
Parksville | British Columbia | 371 Alberni Highway Project | 87 | 58 | - | National Housing Co-Investment Fund | Nanaimo Affordable Housing Society | 7/11/2023 | New Construction | Not-for-profit housing org/Co-op | $ 19,859,840.00 | $ 752,121.00 | $ 19,107,719.00 | Under Construction | 49.3148 | -124.321843 |
Pasqua 79 | Saskatchewan | PFN Rapid Housing Project (Traditional Construction) | 20 | 20 | - | Rapid Housing Initiative 2 | Pasqua First Nation #79 | 5/31/2023 | New Construction | Indigenous Governing Body | $ 5,402,272.00 | $ 5,402,272.00 | $ - | Under Construction | 50.4137 | -105.429066 |
Pasqua 79 | Saskatchewan | PFN Rapid Housing Project (Modular Construction) | 20 | 20 | - | Rapid Housing Initiative 2 | Pasqua First Nation #79 | 5/31/2023 | New Construction | Indigenous Governing Body | $ 3,715,360.00 | $ 3,715,360.00 | $ - | Under Construction | 50.4137 | -105.429066 |
Peguis 1B | Manitoba | Peguis RHI Project | 18 | - | - | Rapid Housing Initiative | Peguis First Nation | 5/18/2021 | New Construction | Indigenous Group | $ 3,868,543.03 | $ 3,868,543.03 | $ - | Under Construction | 51.3172 | -97.554956 |
Pelican Narrows 184B | Saskatchewan | PBCN Pelican Narrows | 14 | 14 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 3,601,395.00 | $ 3,601,395.00 | $ - | Under Construction | 55.1737 | -102.920922 |
Pessamit | Quebec | Projet ICRL - Construction résidentielle 10 unités Pessamit | 10 | 10 | - | Rapid Housing Initiative | Bande des Innus de Pessamit | 1/22/2021 | New Construction | Indigenous Group | $ 1,812,901.00 | $ 1,812,901.00 | $ - | Built | 48.9475 | -68.651186 |
Peterborough | Ontario | 681 Monaghan Road | 53 | - | - | Rapid Housing Initiative 3 | The Corporation of the City of Peterborough | 10/11/2023 | New Construction | Municipality | $ 18,931,121.00 | $ 18,931,121.00 | $ - | Financial Commitments | 44.2794 | -78.326811 |
Calgary | Alberta | Sunalta Renovation | 85 | 33 | - | National Housing Co-Investment Fund | HomeSpace Society | 10/11/2023 | Repairs | Not-for-profit housing org/Co-op | $ 295,000.00 | $ 295,000.00 | $ - | Built | 51.0437 | -114.105406 |
Peterborough | Ontario | Peterborough housing corp repairs | 945 | 945 | 189 | National Housing Co-Investment Fund | Peterborough Housing Corporation | 10/11/2023 | Repairs | Municipality | $ 3,450,000.00 | $ 3,450,000.00 | $ - | Under Construction | 44.3000 | -78.317 |
Peterborough | Ontario | Affordable Living Village | 64 | 29 | 7 | Rental Construction Financing Initiative | RPM Holdings (2006) Inc. | 6/7/2021 | New Construction | Private Enterprise/Builder/Developer | $ 18,400,000.00 | $ - | $ 18,400,000.00 | Under Construction | 44.2957 | -78.3204909 |
Peterborough | Ontario | 3789 Water Street Apartments | 25 | 15 | 3 | Rental Construction Financing Initiative | Cor-Plan (2012) Inc. | 2/12/2021 | New Construction | Private Enterprise/Builder/Developer | $ 7,600,000.00 | $ - | $ 7,600,000.00 | Built | 44.3603 | -78.2996784 |
Peterborough | Ontario | 882 Whitefield Drive | 27 | 27 | 3 | Rental Construction Financing Initiative | Parkview Homes | 2/5/2021 | New Construction | Private Enterprise/Builder/Developer | $ 8,500,000.00 | $ - | $ 8,500,000.00 | Under Construction | 44.2844 | -78.3510507 |
Peterborough | Ontario | Water Street – Phase 2 | 46 | 32 | 5 | Rental Construction Financing Initiative | Cor-Plan (2012) Inc. | 8/25/2020 | New Construction | Private Enterprise/Builder/Developer | $ 14,000,000.00 | $ - | $ 14,000,000.00 | Under Construction | 44.3603 | -78.2996784 |
Peterborough | Ontario | Brock Street Mission Redevelopment | 45 | - | 12 | National Housing Co-Investment Fund | THE BROCK STREET MISSION PETERBOROUGH | 7/11/2019 | New Construction | Not-for-profit housing org/Co-op | $ 5,028,638.00 | $ 2,000,000.00 | $ 3,028,638.00 | Built | 44.3080 | -78.322789 |
Piapot 75 | Saskatchewan | Piapot RHI 2020 | 10 | 10 | - | Rapid Housing Initiative 2 | Piapot First Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 2,900,000.00 | $ 2,900,000.00 | $ - | Under Construction | 50.5085 | -104.332856 |
Pictou | Nova Scotia | Coady's Place (as in Father Moses Coady) | 36 | 36 | - | Rapid Housing Initiative 2 | Nova Scotia Co-operative Council Limited | 5/26/2022 | Repairs | Not-for-profit housing org/Co-op | $ 2,095,869.00 | $ 2,095,869.00 | $ - | Under Construction | 44.6425 | -63.594804 |
Pinehouse | Saskatchewan | Pinehouse Tiny Homes - Phase 2 | 6 | 6 | 3 | National Housing Co-Investment Fund | Pinehouse Housing Corporation | 6/22/2022 | New Construction | Indigenous Group | $ 380,200.00 | $ 380,200.00 | $ - | Built | 55.5195 | -106.573889 |
Pond Inlet | Nunavut | Qikiqtani - Pond Inlet Single Family - High Arctic Affordable Housing Project | 1 | 1 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,025,320.00 | $ 1,025,320.00 | $ - | Financial Commitments | 72.6967 | -77.948998 |
Pond Inlet | Nunavut | Qikiqtani - Pond Inlet Apts - High Arctic Affordable Housing Project | 4 | 4 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 3,214,938.00 | $ 3,214,938.00 | $ - | Financial Commitments | 72.6967 | -77.948998 |
Pond Inlet | Nunavut | Nunavut portfolio I Pond Inlet 3 x 5 Plex 2020-2021 | 15 | 15 | - | Rapid Housing Initiative 2 | Nunavut Housing Corporation | 4/3/2022 | New Construction | Territory | $ 5,841,669.96 | $ 5,841,669.96 | $ - | Built | 72.7001 | -77.958181 |
Port Coquitlam | British Columbia | Kingsway | 300 | 300 | 90 | Rental Construction Financing Initiative | Dogwood Holdings (Kingsway) Society | 10/11/2023 | New Construction | Not-for-profit housing org/Co-op | $ 96,000,000.00 | $ - | $ 96,000,000.00 | Under Construction | 49.2659 | -122.784727 |
Port Moody | British Columbia | 3131 St Johns | 142 | 133 | 17 | Rental Construction Financing Initiative | Woodbridge Living (St. John's) Ltd | 8/4/2021 | New Construction | Private Enterprise/Builder/Developer | $ 48,600,000.00 | $ - | $ 48,600,000.00 | Built | 49.2764 | -122.836162 |
Portage La Prairie | Manitoba | Dufferin Villa | 53 | 17 | 53 | National Housing Co-Investment Fund | Portage la Prairie Assisted Living Corp. | 4/1/2021 | New Construction | Not-for-profit housing org/Co-op | $ 16,792,720.00 | $ 1,442,484.00 | $ 15,350,236.00 | Built | 49.9705 | -98.2909275 |
Port-Daniel--Gascons | Quebec | SHQ - Les Habitations Port-Daniel-Gascons | 24 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 3,906,224.00 | $ 3,906,224.00 | $ - | Built | 48.1686 | -64.9776887 |
Prince Albert | Saskatchewan | Elders 11-unit Project (7th Street E & 20th Street E) | 11 | 11 | - | National Housing Co-Investment Fund | P.A. Community Housing Society Inc. | 4/28/2023 | New Construction | Indigenous Non-Profit Organization | $ 2,334,000.00 | $ 2,334,000.00 | $ - | Under Construction | 53.2034 | -105.706795 |
Prince Albert | Saskatchewan | 861 River Street West- Hard to House | 14 | 14 | 3 | National Housing Co-Investment Fund | The P.A. Community Housing Society Inc | 5/6/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,620,900.00 | $ 600,000.00 | $ 1,020,900.00 | Built | 53.2026 | -105.7770742 |
Pukatawagan 198 | Manitoba | Mathias Colomb Rapid Housing Initiative 2-4 Plexes | 8 | 8 | 8 | Rapid Housing Initiative | Mathias Colomb Cree Nation | 5/18/2021 | New Construction | Indigenous Group | $ 2,771,507.00 | $ 2,771,507.00 | $ - | Built | 55.7420 | -101.316876 |
Québec | Quebec | Maison Marie-Frédéric | 11 | 11 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 185,944.00 | $ 185,944.00 | $ - | Built | 46.8081 | -71.254393 |
Québec | Quebec | Résidence le Piolet / Hamel | 30 | 30 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 507,120.00 | $ 507,120.00 | $ - | Built | 46.8114 | -71.256834 |
Québec | Quebec | Shelter | 13 | 14 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | Repairs | Province | $ 2,300,000.00 | $ 2,300,000.00 | $ - | Under Construction | 46.8127 | -71.2199 |
Québec | Quebec | Triplex Hélène Voisard Projet RHI2 | 2 | 2 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 600,000.00 | $ 600,000.00 | $ - | Under Construction | 46.8215 | -71.223952 |
Québec | Quebec | L'amarrage Projet RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,100,000.00 | $ 2,100,000.00 | $ - | Financial Commitments | 46.8536 | -71.415767 |
Québec | Quebec | Groupe O'Drey | 79 | 40 | 44 | National Housing Co-Investment Fund | Groupe O'Drey | 6/21/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,272,479.00 | $ 3,272,479.00 | $ - | Under Construction | 46.8180 | -71.242509 |
Québec | Quebec | l’Ardoise | 204 | 104 | 45 | National Housing Co-Investment Fund | UTILE Québec | 8/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 30,827,430.00 | $ 2,500,000.00 | $ 28,327,430.00 | Under Construction | 46.7876 | -71.275745 |
Québec | Quebec | Un Toit Juste Pour Elles - inter'elle RHI2 | 22 | 19 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec | 4/22/2022 | New Construction | Province | $ 8,200,000.00 | $ 8,200,000.00 | $ - | Financial Commitments | 46.8144 | -71.2409046 |
Québec | Quebec | SHQ - RPQ - Pointe-de-Sainte-Foy - Phase II | 35 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 30,184.00 | $ 30,184.00 | $ - | Built | 46.7648 | -71.33264 |
Québec | Quebec | La maison de Lauberivière | 149 | - | 149 | National Housing Co-Investment Fund | Maison de Lauberivière, aides aux adultes en difficulté | 12/18/2018 | New Construction | Not-for-profit housing org/Co-op | $ 4,357,241.00 | $ 4,357,241.00 | $ - | Built | 46.8167 | -71.221582 |
Rat Portage 38A | Ontario | WON Indigenous Rapid Housing Project 2021 (Anishinabe of Wauzhushk Onigum Nation) | 10 | 10 | 10 | Rapid Housing Initiative | Anishinabe of Wauzhushk Onigum | 4/16/2021 | New Construction | Indigenous Group | $ 3,851,203.00 | $ 3,851,203.00 | $ - | Under Construction | 43.1052 | -79.0955392 |
Red Bank 4 | New Brunswick | NSMDC Portfolio - Red Bank | 4 | 4 | 4 | Rapid Housing Initiative | Metepenagiag Mi'kmaq Nation | 5/24/2023 | New Construction | Indigenous Group | $ 436,923.00 | $ 436,923.00 | $ - | Built | 46.8740 | -66.219549 |
Red Deer | Alberta | Shelter | 40 | 40 | 28 | National Housing Co-Investment Fund | The Central Alberta Women's Emergency Shelter Society | 6/16/2023 | New Construction | Not-for-profit housing org/Co-op | $ 29,870,298.50 | $ 29,870,298.50 | $ - | Under Construction | 52.2681 | -113.811241 |
Red Lake | Ontario | Shelter | 10 | 10 | 4 | National Housing Co-Investment Fund | Kenora District Services Board | 2/17/2021 | New Construction | Municipality | $ 4,204,388.00 | $ 846,388.00 | $ 3,358,000.00 | Built | 51.0146 | -93.8289 |
Regina | Saskatchewan | Shelter | 108 | 68 | 23 | National Housing Co-Investment Fund | YWCA Regina | 6/28/2022 | New Construction | Not-for-profit housing org/Co-op | $ 33,981,000.00 | $ 33,981,000.00 | $ - | Under Construction | 50.4452 | -104.6189 |
Regina | Saskatchewan | Shelter | 116 | 39 | 25 | National Housing Co-Investment Fund | Avana Foundation Inc. | 3/10/2022 | New Construction | Not-for-profit housing org/Co-op | $ 30,775,562.00 | $ 814,514.00 | $ 29,961,048.00 | Under Construction | 50.4452 | -104.6189 |
Regina | Saskatchewan | 120 Broad Street, Regina | 29 | 29 | - | Rapid Housing Initiative 2 | City of Regina | 7/28/2021 | New Construction | Municipality | $ 7,752,680.00 | $ 7,752,680.00 | $ - | Under Construction | 50.4766 | -104.607031 |
Resolute | Nunavut | Qikiqtani - Resolute Semi detached - High Arctic Affordable Housing Project | 2 | 2 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,607,469.00 | $ 1,607,469.00 | $ - | Financial Commitments | 74.6973 | -94.828619 |
Resolute | Nunavut | Qikiqtani - Resolute Single Family - High Arctic Affordable Housing Project | 1 | 1 | - | Rapid Housing Initiative 3 | Qikiqtani Inuit Association | 10/3/2023 | New Construction | Indigenous Governing Body | $ 1,025,320.00 | $ 1,025,320.00 | $ - | Financial Commitments | 74.6973 | -94.828619 |
Richibucto 15 | New Brunswick | Hollow Court - emergency housing | 20 | - | - | Rapid Housing Initiative | Elsipogtog First Nation | 5/24/2023 | New Construction | Indigenous Group | $ 3,000,000.00 | $ 3,000,000.00 | $ - | Built | 46.5864 | -64.986293 |
Richmond | British Columbia | 4831 Steveston Highway | 25 | - | - | Rapid Housing Initiative 3 | City of Richmond | 6/2/2023 | New Construction | Municipality | $ 9,117,138.00 | $ 9,117,138.00 | $ - | Financial Commitments | 49.1341 | -123.170334 |
Rivière-Rouge | Quebec | Arc-en-Toit RHI2 | 28 | 28 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,300,000.00 | $ 5,300,000.00 | $ - | Financial Commitments | 46.5467 | -74.959715 |
Rivière-Rouge | Quebec | Villa Cartier by Appartements du Quartier Rivière-Rouge | 38 | 38 | 38 | National Housing Co-Investment Fund | Appartement du Quartier Rivière Rouge | 3/15/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,808,983.00 | $ 3,808,983.00 | $ - | Built | 46.4023 | -74.867139 |
Roberval | Quebec | Mishtik RHI2 | 24 | 24 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,700,000.00 | $ 3,700,000.00 | $ - | Financial Commitments | 48.5138 | -72.222119 |
Rosedale | British Columbia | Cheam 20 Unit Conversion | 20 | 20 | 4 | National Housing Co-Investment Fund | Cheam First Nation | 1/9/2023 | New Construction | Indigenous Group | $ 928,045.00 | $ 928,045.00 | $ - | Under Construction | 49.1884 | -121.7872444 |
Rouyn-Noranda | Quebec | Hébergement adapté et supervisé des Chenaux RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | Repairs | Province | $ 3,000,000.00 | $ 3,000,000.00 | $ - | Financial Commitments | 46.5443 | -72.349299 |
Rouyn-Noranda | Quebec | Les Marginales RHI2 | 14 | 14 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | New Construction | Province | $ 3,500,000.00 | $ 3,500,000.00 | $ - | Financial Commitments | 48.2235 | -79.000586 |
Rouyn-Noranda | Quebec | SHQ - Maison Martin Bradley - Phase II | 25 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 950,000.00 | $ 950,000.00 | $ - | Built | 48.2236 | -79.0007303 |
Saanich | British Columbia | Nigel House Redevelopment | 47 | 15 | 10 | National Housing Co-Investment Fund | Broadmead Care Society | 6/30/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,200,000.00 | $ 3,200,000.00 | $ - | Built | 48.4576 | -123.3732613 |
Saanich | British Columbia | Linwood Court | 97 | 40 | - | National Housing Co-Investment Fund | The Baptist Housing Society of B.C. | 5/25/2022 | New Construction | Faith-based organization | $ 5,955,027.00 | $ 5,955,027.00 | $ - | Under Construction | 48.4496 | -123.3602123 |
Saguenay | Quebec | SHQ - Projet d'héb. Saguenay santé mentale et centre de crise | 48 | 56 | - | Rapid Housing Initiative | Société d'habitation du Québec SHQ | 1/22/2021 | New Construction | Province | $ 3,000,000.00 | $ 3,000,000.00 | $ - | Under Construction | 48.4252 | -71.061769 |
Saguenay | Quebec | Centre d'accueil Des Uniformes (C,A,D,U) - Révisé - RHI2 | 12 | - | - | Rapid Housing Initiative 2 | Société d'habitation du Québec | 2/22/2022 | Repairs | Province | $ 1,710,000.00 | $ 1,710,000.00 | $ - | Financial Commitments | 48.4245 | -70.994972 |
Saguenay | Quebec | SHQ - Projet d'héb. Saguenay sans-abris et autochtones | 43 | 36 | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Renewals | Province | $ 1,200,000.00 | $ 1,200,000.00 | $ - | Built | 48.4256 | -71.06246 |
Saint John | New Brunswick | The Wellington | 47 | 24 | 3 | National Housing Co-Investment Fund | Saint John Non Profit Housing Inc. | 12/21/2022 | New Construction | Not-for-profit housing org/Co-op | $ 11,514,800.00 | $ 1,746,838.00 | $ 9,767,962.00 | Under Construction | 45.2750 | -66.0613448 |
Saint John | New Brunswick | Transitional Housing | 12 | 12 | - | Rapid Housing Initiative 2 | Coverdale Centre for Women Inc. | 8/22/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,389,365.40 | $ 1,389,365.40 | $ - | Built | 45.2796 | -66.0628 |
Saint John | New Brunswick | USJ Victoria Commons | 14 | 12 | 5 | National Housing Co-Investment Fund | Unified Saint John Housing Co-operative Limited | 6/18/2021 | New Construction | Not-for-profit housing org/Co-op | $ 1,333,029.00 | $ 91,251.00 | $ 1,241,778.00 | Built | 45.2908 | -66.1815169 |
Saint-Adolphe-d'Howard | Quebec | Habitation Saint-Adolphe-d'Howard Projet RHI2 | 31 | 31 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 8,100,000.00 | $ 8,100,000.00 | $ - | Financial Commitments | 45.9754 | -74.357265 |
Saint-Charles-Borromée | Quebec | Maison Héritage Abénaki RHI2 | 30 | 30 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,500,000.00 | $ 5,500,000.00 | $ - | Financial Commitments | 46.2650 | -70.468086 |
Saint-Denis-de-Brompton | Quebec | SHQ - L'Oasis des lacs, Coop de solidarité | 20 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,609,000.00 | $ 2,609,000.00 | $ - | Built | 45.4554 | -72.081897 |
Saint-Donat | Quebec | Les résidences du parc naturel habité - Phase II RHI2 | 29 | 29 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,500,000.00 | $ 3,500,000.00 | $ - | Financial Commitments | 46.3446 | -74.059511 |
Sainte-Agathe-des-Monts | Quebec | L'Ombre-elle RHI2 | 8 | 10 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,600,000.00 | $ 3,600,000.00 | $ - | Under Construction | 46.0464 | -74.285454 |
Sainte-Anne-des-Monts | Quebec | Centre Louise-Amélie - 2e étape RHI2 | 12 | 13 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,800,000.00 | $ 5,800,000.00 | $ - | Financial Commitments | 49.1287 | -66.488637 |
Sainte-Barbe | Quebec | SHQ - Coop Solidarité | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec | 7/14/2023 | New Construction | Province | $ 1,735,600.00 | $ 1,735,600.00 | $ - | Built | 45.1762 | -74.254597 |
Sainte-Geneviève-de-Batiscan | Quebec | Milieu de vie communautaire pour familles autochtones RHI2 | 42 | 42 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | New Construction | Province | $ 12,000,000.00 | $ 12,000,000.00 | $ - | Under Construction | 46.3742 | -72.508797 |
Saint-Elzéar | Quebec | SHQ - La Résidence du verger inc. | 25 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,917,500.00 | $ 1,917,500.00 | $ - | Built | 46.4052 | -71.0607756 |
Saint-François-d'Assise | Quebec | Agrandissement Villa Rayon de Soleil Saint-François- D'Assise RHI2 | 14 | 14 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,900,000.00 | $ 2,900,000.00 | $ - | Financial Commitments | 47.9834 | -67.163972 |
Saint-Hyacinthe | Quebec | Projet MAMIK RHI2 | 10 | 10 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | New Construction | Province | $ 1,910,000.00 | $ 1,910,000.00 | $ - | Financial Commitments | 47.4384 | -72.784267 |
Saint-Hyacinthe | Quebec | SHQ - Habitations Maska | 21 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | Renewals | Province | $ 2,350,000.00 | $ 2,350,000.00 | $ - | Built | 45.6248 | -72.9466087 |
Saint-Isidore | Quebec | SHQ - Gîte St-Isidore - Phase II | 21 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,605,884.00 | $ 1,605,884.00 | $ - | Built | 46.5822 | -71.0946569 |
Saint-Jérôme | Quebec | Maison Oxygène Laurentides RHI2 | 4 | 4 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 700,000.00 | $ 700,000.00 | $ - | Built | 45.7800 | -74.011977 |
Saint-Jérôme | Quebec | La Maison d'Ariane Projet RHI2 | 10 | 10 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,000,000.00 | $ 2,000,000.00 | $ - | Financial Commitments | 45.7844 | -74.008585 |
Saint-Lambert-de-Lauzon | Quebec | Petit domicile de Saint-Lambert - Phase II RHI2 | 16 | 16 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 3,300,000.00 | $ 3,300,000.00 | $ - | Financial Commitments | 46.6049 | -71.251923 |
Saint-Paul | Quebec | SHQ - Le Havre Paulois | 20 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 713,080.00 | $ 713,080.00 | $ - | Built | 45.9439 | -73.420589 |
Saint-Siméon | Quebec | OMH de St-Siméon RHI2 | 24 | 24 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 6,700,000.00 | $ 6,700,000.00 | $ - | Under Construction | 48.0940 | -65.573941 |
Salaberry-de-Valleyfield | Quebec | SHQ - Defi-Logis | 8 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,422,300.00 | $ 1,422,300.00 | $ - | Under Construction | 45.2624 | -74.1154881 |
Samson 137 | Alberta | Project C - Rural Infills PL 138A and Project D Townsite Infills and Whoville | 22 | 22 | - | Rapid Housing Initiative 2 | Samson Cree Nation | 4/21/2023 | New Construction | Indigenous Governing Body | $ 7,309,507.40 | $ 7,309,507.40 | $ - | Under Construction | 52.9822 | -113.9469 |
Samson 137 | Alberta | Samson 137 RHI Application 1 | 18 | - | - | Rapid Housing Initiative | Samson Cree Nation | 4/21/2023 | New Construction | Indigenous Group | $ 2,949,454.70 | $ 2,949,454.70 | $ - | Under Construction | 52.8344 | -113.447207 |
Sandy Bay | Saskatchewan | PBCN Sandy Bay | 9 | 9 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 2,315,182.50 | $ 2,315,182.50 | $ - | Under Construction | 55.4664 | -102.299181 |
Saskatoon | Saskatchewan | YWCA Saskatoon Expansion | 33 | - | - | Rapid Housing Initiative 3 | City of Saskatoon | 9/7/2023 | New Construction | Municipality | $ 6,787,546.00 | $ 6,787,546.00 | $ - | Financial Commitments | 52.1325 | -106.65559 |
Saskatoon | Saskatchewan | Infinity House Structural Repairs | 14 | 10 | - | National Housing Co-Investment Fund | Central Urban Métis Federation (1993) Incorporated | 3/3/2023 | Repairs | Not-for-profit housing org/Co-op | $ 632,122.00 | $ 632,122.00 | $ - | Under Construction | 52.1283 | -106.696192 |
Saskatoon | Saskatchewan | CUMFI Elders Residence | 26 | 13 | 4 | National Housing Co-Investment Fund | Central Urban Metis Federation (1993) Inc. | 12/3/2021 | New Construction | Not-for-profit housing org/Co-op | $ 2,293,231.00 | $ 683,845.00 | $ 1,609,386.00 | Built | 52.1237 | -106.6935435 |
Saskatoon | Saskatchewan | City of Saskatoon - Cress Housing 1 | 18 | 18 | - | Rapid Housing Initiative 2 | City of Saskatoon | 3/12/2021 | New Construction | Municipality | $ 3,781,518.00 | $ 3,781,518.00 | $ - | Built | 52.1594 | -106.6357078 |
Saskatoon | Saskatchewan | City of Saskatoon - CUMFI 2 | 14 | 14 | - | Rapid Housing Initiative 2 | City of Saskatoon | 3/12/2021 | New Construction | Municipality | $ 3,781,518.00 | $ 3,781,518.00 | $ - | Built | 52.1249 | -106.6934807 |
Sault Ste. Marie | Ontario | OAHS - Portfolio | 276 | 276 | 55 | National Housing Co-Investment Fund | Ontario Aboriginal Housing Support Services Corporation | 1/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 86,160,196.00 | $ 34,464,078.00 | $ 51,696,118.00 | Under Construction | 48.7554 | -91.6262512 |
Sault Ste. Marie | Ontario | Royal Canadian Legion Branch 25 | 107 | 35 | 33 | National Housing Co-Investment Fund | The Royal Canadian Legion Branch 25 | 1/9/2023 | New Construction | Not-for-profit housing org/Co-op | $ 32,081,400.00 | $ 3,405,090.00 | $ 28,676,310.00 | Under Construction | 46.5284 | -84.3182715 |
Scotchfort 4 | Prince Edward Island | Abegweit- Healthy Rapid Homes 2021 | 5 | 5 | - | Rapid Housing Initiative | Abegweit First Nation | 4/4/2022 | New Construction | Indigenous Group | $ 1,353,621.38 | $ 1,353,621.38 | $ - | Built | 46.3702 | -63.012462 |
Seaichem 16 | British Columbia | Seaichem Rapid Modular Housing Project for Women and Children Fleeing Violence | 30 | 27 | - | Rapid Housing Initiative 2 | Squamish Nation | 2/22/2022 | New Construction | Indigenous Governing Body | $ 15,328,283.77 | $ 15,328,283.77 | $ - | Under Construction | 49.7638 | -123.14773 |
Sept-Îles | Quebec | SHQ - Projet pour familles autochtones étudiant à Sept-Îles | 32 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 6,119,616.00 | $ 6,119,616.00 | $ - | Under Construction | 50.2251 | -66.3448897 |
Shackan 11 | British Columbia | Shackan Band Rapid Housing Initiative 2021 (A Better Year) | 14 | 14 | - | Rapid Housing Initiative | Shackan Indian Band | 5/4/2021 | New Construction | Indigenous Group | $ 4,414,435.20 | $ 4,414,435.20 | $ - | Under Construction | 50.1112 | -120.788647 |
Shawinigan | Quebec | Villa Castonguay - Phase II - RHI2 | 20 | 20 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | New Construction | Province | $ 2,975,000.00 | $ 2,975,000.00 | $ - | Financial Commitments | 45.7700 | -71.932356 |
Shawinigan | Quebec | J'ai mon appart' | 12 | 12 | 6 | National Housing Co-Investment Fund | J'ai Mon Appart' | 8/13/2021 | New Construction | Not-for-profit housing org/Co-op | $ 850,000.00 | $ 850,000.00 | $ - | Built | 46.6090 | -72.707872 |
Sherbrooke | Quebec | Mon Shack et Mes Choix RHI2 | 22 | 22 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 5,968,537.00 | $ 5,968,537.00 | $ - | Under Construction | 45.3701 | -71.852 |
Sherbrooke | Quebec | Une Place pour Toutes Maison Margot Projet RHI2 | 12 | 12 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 1,900,000.00 | $ 1,900,000.00 | $ - | Under Construction | 45.4097 | -71.846019 |
Sherbrooke | Quebec | Le Chardonnay | 80 | 80 | 100 | Rental Construction Financing Initiative | Gestion Fauteaux Nadeau Inc. | 5/24/2023 | New Construction | Private Enterprise/Builder/Developer | $ 32,129,000.00 | $ - | $ 32,129,000.00 | Under Construction | 45.4017 | -71.962 |
Sherbrooke | Quebec | Habitations Équerre | 12 | 12 | - | Federal Lands Initiative | Habitations l'Équerre Inc. | 11/8/2021 | New Construction | Not-for-profit housing org/Co-op | $ 626,448.00 | $ 626,448.00 | $ - | Built | 45.3846 | -71.9049765 |
Sherbrooke | Quebec | SHQ - Lavigerie II - 2017 | 12 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 768,300.00 | $ 768,300.00 | $ - | Built | 45.3937 | -71.8643915 |
Sherbrooke | Quebec | SHQ - Logements Handi-Cité | 23 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,984,792.00 | $ 1,984,792.00 | $ - | Built | 45.4125 | -71.8418682 |
Shoal Lake (Part) 39A | Ontario | 6 Single Family Homes | 6 | - | - | Rapid Housing Initiative | Iskatewizaagegan #39 Independent First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 600,000.00 | $ 600,000.00 | $ - | Built | 49.6155 | -95.109549 |
Sik-e-dakh 2 | British Columbia | Sik-E-Dakh Gathering Place | 6 | - | - | Rapid Housing Initiative | Glen Vowell | 5/14/2021 | New Construction | Indigenous Group | $ 1,610,698.00 | $ 1,610,698.00 | $ - | Built | 55.3129 | -127.6793149 |
Siksika 146 | Alberta | 20 Unit Affordable Housing Project | 20 | 20 | - | Rapid Housing Initiative 2 | Siksika Nation | 4/21/2023 | New Construction | Indigenous Governing Body | $ 7,967,119.00 | $ 7,967,119.00 | $ - | Conditional Commitments | 50.7712 | -112.85713 |
Siksika 146 | Alberta | Transitional Housing | 10 | 10 | - | Rapid Housing Initiative 2 | Siksika Off Reserve Affordable Housing Project Ltd | 4/21/2023 | New Construction | Indigenous Governing Body | $ 2,214,628.00 | $ 2,214,628.00 | $ - | Under Construction | 50.7712 | -112.85713 |
Siksika 146 | Alberta | Transitional Housing | 8 | - | - | Rapid Housing Initiative 2 | Siksika Off Reserve Affordable Housing Project Ltd | 4/21/2023 | New Construction | Indigenous Governing Body | $ 925,897.00 | $ 925,897.00 | $ - | Under Construction | 50.7712 | -112.85713 |
Siksika 146 | Alberta | Transitional Housing | 64 | - | - | Rapid Housing Initiative 2 | Siksika Off Reserve Affordable Housing Project Ltd | 4/21/2023 | New Construction | Indigenous Governing Body | $ 9,715,044.00 | $ 9,715,044.00 | $ - | Under Construction | 50.7712 | -112.85713 |
Sioux Lookout | Ontario | First Step Second Stage Housing | 10 | 10 | 4 | National Housing Co-Investment Fund | First Step Women's Shelter | 6/15/2023 | New Construction | Not-for-profit housing org/Co-op | $ 3,500,000.00 | $ 3,500,000.00 | $ - | Under Construction | 50.1129 | -91.904187 |
Skweahm 10 | British Columbia | Shelter | 10 | - | - | Rapid Housing Initiative | Leq'á:mel First Nation | 4/9/2021 | New Construction | Indigenous Group | $ 2,615,126.00 | $ 2,615,126.00 | $ - | Built | 49.2140 | -122.8950713 |
Sooke | British Columbia | Sooke Drennan Housing | 170 | 170 | 18 | National Housing Co-Investment Fund | M'Akola Housing Society | 6/11/2021 | New Construction | Indigenous Non-Profit Organization | $ 6,900,000.00 | $ 6,900,000.00 | $ - | Built | 48.3834 | -123.710506 |
Sorel-Tracy | Quebec | SHQ - L'Héberge du Grand Héron | 14 | 14 | - | Rapid Housing Initiative | Société d'habitation du Québec SHQ | 1/22/2021 | New Construction | Province | $ 393,064.00 | $ 393,064.00 | $ - | Under Construction | 46.0411 | -73.112868 |
Southend No. 200A | Saskatchewan | PBCN Southend | 9 | 9 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 1,914,718.50 | $ 1,914,718.50 | $ - | Under Construction | 56.3211 | -103.232482 |
Sparwood | British Columbia | 400 Evergreen Crescent - Sparwood, BC | 30 | 21 | 7 | National Housing Co-Investment Fund | ELK VALLEY FAMILY SOCIETY | 7/27/2022 | New Construction | Not-for-profit housing org/Co-op | $ 1,999,271.00 | $ 1,999,271.00 | $ - | Built | 49.7285 | -114.893273 |
Spences Bridge | British Columbia | Cook's Ferry RHI Housing Project | 5 | - | - | Rapid Housing Initiative | Cook's Ferry Indian Band | 4/9/2021 | New Construction | Indigenous Group | $ 1,490,777.00 | $ 1,490,777.00 | $ - | Built | 50.4141 | -121.359529 |
Split Lake (Part) 171 | Manitoba | TCN (Tataskweyak Cree Nation) RHI Project No. 1 | 10 | 10 | 10 | Rapid Housing Initiative | Tataskweyak Cree Nation | 5/18/2021 | New Construction | Indigenous Group | $ 2,493,864.40 | $ 2,493,864.40 | $ - | Built | 56.2451 | -96.095057 |
Squamish | British Columbia | Squamish 3B | 105 | 105 | 11 | Rental Construction Financing Initiative | Bosa-Kingswood Rentals GP Inc. | 10/13/2023 | New Construction | Private Enterprise/Builder/Developer | $ 45,764,000.00 | $ - | $ 45,764,000.00 | Under Construction | 49.7407 | -123.134146 |
Squamish | British Columbia | Squamish Seniors | 232 | 232 | - | National Housing Co-Investment Fund | Squamish Senior Citizens Home Society | 3/2/2021 | New Construction | Not-for-profit housing org/Co-op | $ 40,550,000.00 | $ 1,600,000.00 | $ 38,950,000.00 | Built | 49.7032 | -123.1535902 |
St. Catharines | Ontario | Gillian's Place Facility Enhancement | 34 | - | 8 | National Housing Co-Investment Fund | Women's Place (St. Catharines & District) Inc. | 6/15/2023 | Repairs | Not-for-profit housing org/Co-op | $ 2,100,000.00 | $ 2,100,000.00 | $ - | Under Construction | 43.1711 | -79.234584 |
St. Catherines | Ontario | Oakdale Commons | 24 | 24 | 5 | National Housing Co-Investment Fund | The Young Womens Christian Association of St. Catharines | 7/6/2020 | New Construction | Faith-based organization | $ 3,022,000.00 | $ 3,022,000.00 | $ - | Built | 43.1494 | -79.2216855 |
St. John's | Newfoundland and Labrador | 41-57 Janeway Place | 8 | 8 | - | Rapid Housing Initiative 2 | Newfoundland and Labrador Housing Corporation | 12/9/2022 | New Construction | Province | $ 1,108,800.00 | $ 1,108,800.00 | $ - | Under Construction | 47.5902 | -52.689178 |
St. John's | Newfoundland and Labrador | City of St. John's Choices for Youth | 14 | - | - | Rapid Housing Initiative 2 | City of St. John's | 9/29/2023 | New Construction | Municipality | $ 3,875,388.00 | $ 3,875,388.00 | $ - | Under Construction | 47.5902 | -52.689178 |
St. John's | Newfoundland and Labrador | NL Housing Corporation Pleasantville 40 units | 40 | 40 | 8 | Federal Lands Initiative | Newfoundland and Labrador Housing Corporation | 11/25/2022 | New Construction | Province | $ 1,215,025.00 | $ 1,215,025.00 | $ - | Under Construction | 47.5843 | -52.6990005 |
St. John's | Newfoundland and Labrador | The Gathering Place | 56 | 24 | - | Rapid Housing Initiative 2 | Newfoundland and Labrador Housing Corporation | 4/29/2022 | Repairs | Province | $ 5,920,000.00 | $ 5,920,000.00 | $ - | Under Construction | 47.5676 | -52.7092721 |
St. John's | Newfoundland and Labrador | The Salvation Army Centre of Hope | 20 | 20 | 4 | National Housing Co-Investment Fund | The Governing Council of The Salvation Army in Canada | 9/6/2019 | New Construction | Not-for-profit housing org/Co-op | $ 1,150,066.00 | $ 1,150,066.00 | $ - | Built | 47.5576 | -52.713034 |
St. Marys | New Brunswick | SMFN AFFORDABLE HOUSING PROJECT | 2 | 24 | - | Rapid Housing Initiative | Saint Mary's First Nation | 5/24/2023 | Renewals | Indigenous Group | $ 380,540.60 | $ 380,540.60 | $ - | Built | 45.8348 | -66.60074 |
St. Mary's | New Brunswick | SMFN AFFORDABLE HOUSING PROJECT | 8 | 8 | - | Rapid Housing Initiative 2 | Saint Mary's First Nation | 5/24/2023 | New Construction | Indigenous Governing Body | $ 2,151,473.00 | $ 2,151,473.00 | $ - | Under Construction | 45.9719 | -66.632168 |
St. Thomas | Ontario | 614 Talbot | 16 | 16 | - | Rapid Housing Initiative | The Corporation of the City of St. Thomas | 4/13/2021 | New Construction | Municipality | $ 1,501,200.00 | $ 1,501,200.00 | $ - | Built | 42.7787 | -81.190081 |
Stoney 142 143 144 | Alberta | Chiniki First Nation Rapid Housing Initiative 2021 | 20 | 20 | - | Rapid Housing Initiative 2 | Wesley First Nation | 2/3/2023 | New Construction | Indigenous Governing Body | $ 5,197,891.00 | $ 5,197,891.00 | $ - | Built | 51.1615 | -114.850968 |
Stratford | Ontario | Shelter | 15 | - | 15 | National Housing Co-Investment Fund | Perth County Transition Home for Women | 9/29/2022 | New Construction | Not-for-profit housing org/Co-op | $ 3,393,031.00 | $ 3,393,031.00 | $ - | Under Construction | 43.3700 | -80.9822 |
Stratford | Prince Edward Island | Stratford Place Apt | 61 | 30 | 13 | National Housing Co-Investment Fund | Killam Investments (PEI) Inc. | 3/3/2020 | New Construction | Private Enterprise/Builder/Developer | $ 11,045,343.00 | $ 382,382.00 | $ 10,662,961.00 | Built | 46.2181 | -63.0811888 |
Sturgeon Falls | Ontario | West Nipissing Housing Development | 14 | 14 | 3 | National Housing Co-Investment Fund | Ontario Aboriginal Housing Support Services Corporation | 6/26/2019 | New Construction | Not-for-profit housing org/Co-op | $ 1,483,176.00 | $ 100,000.00 | $ 1,383,176.00 | Built | 46.3647 | -79.9178383 |
Sturgeon Weir 184F | Saskatchewan | PBCN Sturgeon Landing | 3 | 3 | - | Rapid Housing Initiative 2 | Peter Ballantyne Cree Nation | 9/7/2023 | New Construction | Indigenous Governing Body | $ 771,727.50 | $ 771,727.50 | $ - | Conditional Commitments | 54.2900 | -101.851529 |
Sudbury | Ontario | Greater Sudbury Housing Solution | 14 | 14 | 6 | Federal Lands Initiative | Greater Sudbury Housing Corporation | 11/23/2020 | New Construction | Municipality | $ 566,400.00 | $ 566,400.00 | $ - | Under Construction | 46.5231 | -80.947514 |
Sudbury | Ontario | Sudbury Wade Hampton House Expansion for People with Acquired Brain Injuries | 12 | 12 | 12 | National Housing Co-Investment Fund | March of Dimes Canada Non-Profit Housing Corporation | 4/16/2019 | New Construction | Not-for-profit housing org/Co-op | $ 1,125,636.00 | $ 1,125,636.00 | $ - | Built | 46.4850 | -80.9072326 |
Summerside | Prince Edward Island | Life House Phase 2 | 24 | 24 | - | Rapid Housing Initiative 3 | City of Summerside | 5/25/2023 | New Construction | Municipality | $ 5,000,000.00 | $ 5,000,000.00 | $ - | Financial Commitments | 46.4220 | -63.81103 |
Summerside | Prince Edward Island | MacEwen Rd 50 Unit | 60 | 60 | 8 | Rental Construction Financing Initiative | Blue Water Rentals Inc. & 102119 P.E.I. Inc | 12/19/2022 | New Construction | Private Enterprise/Builder/Developer | $ 14,910,000.00 | $ - | $ 14,910,000.00 | Under Construction | 46.4160 | -63.7717111 |
Summerside | Prince Edward Island | Shelter | 10 | 10 | 2 | National Housing Co-Investment Fund | Boys and Girls Club Of Summerside | 12/19/2022 | New Construction | Not-for-profit housing org/Co-op | $ 2,855,940.00 | $ 2,855,940.00 | $ - | Under Construction | 46.3934 | -63.7902 |
Summerside | Prince Edward Island | Community Connections Duplex Housing Project | 10 | - | 4 | National Housing Co-Investment Fund | Community Connections Incorporated | 7/14/2022 | New Construction | Not-for-profit housing org/Co-op | $ 243,533.00 | $ 243,533.00 | $ - | Built | 46.3954 | -63.7927452 |
Summerside | Prince Edward Island | Arsenault Bros. 160 Water Street | 70 | 30 | 8 | Rental Construction Financing Initiative | Arsenault Bros. Holdings Inc. | 3/9/2019 | New Construction | Private Enterprise/Builder/Developer | $ 15,185,000.00 | $ - | $ 15,185,000.00 | Built | 46.3908 | -63.7870141 |
Surrey | British Columbia | Kingston Gardens | 85 | 26 | 9 | National Housing Co-Investment Fund | Metro Vancouver Housing Corporation | 7/7/2022 | New Construction | Municipality | $ 29,411,377.00 | $ 1,454,194.00 | $ 27,957,183.00 | Under Construction | 49.1828 | -122.8000523 |
Surrey | British Columbia | 19179 64, Surrey | 30 | - | - | Rapid Housing Initiative 2 | City of Surrey | 12/2/2021 | New Construction | Municipality | $ 13,839,085.00 | $ 13,839,085.00 | $ - | Under Construction | 49.2068 | -122.858963 |
Surrey | British Columbia | Stream A Surrey - Little's Place | 44 | 44 | - | Rapid Housing Initiative | City of Surrey | 3/15/2021 | New Construction | Municipality | $ 16,358,986.00 | $ 16,358,986.00 | $ - | Under Construction | 49.1691 | -122.8462527 |
Surrey | British Columbia | Alden - 1881 152nd Street | 118 | 27 | 12 | Rental Construction Financing Initiative | Southmere Holdings Ltd. | 6/9/2019 | New Construction | Private Enterprise/Builder/Developer | $ 45,375,000.00 | $ - | $ 45,375,000.00 | Built | 49.0361 | -122.801494 |
Swan River 150E | Alberta | Swan River First Nation RHI | 5 | - | - | Rapid Housing Initiative | Swan River First Nation | 4/27/2023 | New Construction | Indigenous Group | $ 1,838,359.90 | $ 1,838,359.90 | $ - | Built | 55.3323 | -115.431371 |
Tecumseh | Ontario | Tecumseh Gateway Tower | 99 | 88 | 10 | Rental Construction Financing Initiative | Gateway Tower Inc. | 5/25/2021 | New Construction | Private Enterprise/Builder/Developer | $ 25,275,000.00 | $ - | $ 25,275,000.00 | Built | 42.3119 | -82.8957456 |
Temiskaming Shores | Ontario | Temiskaming Shores Seniors Housing Corp | 68 | 33 | 21 | National Housing Co-Investment Fund | Temiskaming Shores Seniors Housing Corporation | 3/31/2021 | New Construction | Not-for-profit housing org/Co-op | $ 13,680,844.00 | $ 861,688.00 | $ 12,819,156.00 | Built | 47.5155 | -79.6660097 |
Terrace | British Columbia | Kitsumkalum Modular Housing Development | 8 | - | - | Rapid Housing Initiative | Kitsumkalum | 5/14/2021 | New Construction | Indigenous Group | $ 3,344,101.78 | $ 3,344,101.78 | $ - | Built | 54.5234 | -128.662685 |
Terrebonne | Quebec | La Hutte 2.0 Projet RHI2 | 6 | 6 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 930,000.00 | $ 930,000.00 | $ - | Under Construction | 45.4097 | -71.846019 |
Terrebonne | Quebec | SHQ - Le Pas de Deux | 10 | - | - | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 1,764,000.00 | $ 1,764,000.00 | $ - | Under Construction | 45.6855 | -73.7270446 |
Thetford Mines | Quebec | OH des Appalaches - La Rive II RHI2 | 16 | 16 | - | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,500,000.00 | $ 4,500,000.00 | $ - | Under Construction | 45.4097 | -71.846019 |
Thorold | Ontario | 5 Baker Street, Thorold | 60 | 18 | 12 | National Housing Co-Investment Fund | Thorold Municipal Non-Profit Housing Corporation Site #2 | 8/8/2023 | New Construction | Municipality | $ 14,878,780.00 | $ - | $ 14,878,780.00 | Under Construction | 43.1147 | -79.205168 |
Thunder Bay | Ontario | The Salvation Army Journey to Life Centre | 46 | 46 | 16 | National Housing Co-Investment Fund | The Governing Council of The Salvation Army in Canada | 7/15/2019 | New Construction | Not-for-profit housing org/Co-op | $ 3,010,949.00 | $ 3,010,949.00 | $ - | Built | 48.4507 | -89.193794 |
Tillsonburg | Ontario | Sanders Street Project | 16 | 16 | 16 | Rental Construction Financing Initiative | Town of Tillsonburg Non-Profit Housing Corporation | 4/23/2019 | New Construction | Municipality | $ 1,430,557.66 | $ - | $ 1,430,558.00 | Built | 42.8694 | -80.7359576 |
Tobique | New Brunswick | 12 unit family homes | 12 | - | - | Rapid Housing Initiative | Tobique First Nation | 5/24/2023 | New Construction | Indigenous Group | $ 2,379,749.00 | $ 2,379,749.00 | $ - | Built | 46.7818 | -67.702855 |
Tofino | British Columbia | DL114 South Building Phase 2 | 37 | 25 | 8 | National Housing Co-Investment Fund | Catalyst Community Developments Society | 3/10/2023 | New Construction | Not-for-profit housing org/Co-op | $ 1,850,000.00 | $ 1,850,000.00 | $ - | Built | 49.1476 | -125.908655 |
Tofino | British Columbia | DL114 North Building Phase 1 | 35 | 24 | 8 | National Housing Co-Investment Fund | Catalyst Community Developments Society | 3/29/2022 | New Construction | Not-for-profit housing org/Co-op | $ 7,582,212.00 | $ 1,037,209.00 | $ 6,545,003.00 | Under Construction | 49.1476 | -125.908655 |
Toronto | Ontario | Stream A Toronto - Grand Motel | 21 | 21 | - | Rapid Housing Initiative | City of Toronto | 7/14/2022 | Repairs | Municipality | $ 7,077,553.00 | $ 7,077,553.00 | $ - | Built | 43.7747 | -79.180573 |
Toronto | Ontario | Scattered Housing Transfer and Renovation | 603 | 603 | - | National Housing Co-Investment Fund | Circle Community LandTrust Inc. | 12/2/2022 | Repairs | Not-for-profit housing org/Co-op | $ 72,232,386.00 | $ 12,000,000.00 | $ 60,232,386.00 | Under Construction | 43.6674 | -79.3703503 |
Toronto | Ontario | West End Community Weave | 153 | 153 | - | National Housing Co-Investment Fund | The Neighbourhood Land Trust | 12/2/2022 | Repairs | Not-for-profit housing org/Co-op | $ 17,927,288.00 | $ 6,935,682.00 | $ 10,991,606.00 | Under Construction | 43.6613 | -79.4551131 |
Toronto | Ontario | Stream A- Toronto - 4626 Kingston Rd | 33 | 64 | - | Rapid Housing Initiative | The City of Toronto | 7/14/2022 | New Construction | Municipality | $ 15,500,000.00 | $ 15,500,000.00 | $ - | Under Construction | 43.7747 | -79.180573 |
Toronto | Ontario | 1080 Queen St E | 9 | 9 | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | Repairs | Municipality | $ 1,610,207.00 | $ 1,610,207.00 | $ - | Under Construction | 44.2269 | -76.487328 |
Toronto | Ontario | 1120 Ossington Ave | 28 | - | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 4,480,000.00 | $ 4,480,000.00 | $ - | Under Construction | 44.2475 | -76.5271468 |
Toronto | Ontario | 136 Kingston Rd | 24 | 24 | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 9,505,726.00 | $ 9,505,726.00 | $ - | Under Construction | 43.6674 | -79.3703503 |
Toronto | Ontario | 150 Eighth Street | 56 | - | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 31,009,229.00 | $ 31,009,229.00 | $ - | Under Construction | 43.6022 | -79.507596 |
Toronto | Ontario | 525 Markham Rd | 62 | 62 | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 26,595,098.00 | $ 26,595,098.00 | $ - | Under Construction | 43.7560 | -79.2237766 |
Toronto | Ontario | 60 Bowden Street | 50 | - | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 19,792,500.00 | $ 19,792,500.00 | $ - | Under Construction | 43.6770 | -79.3540908 |
Toronto | Ontario | Shelter | 31 | 31 | - | Rapid Housing Initiative 2 | The City of Toronto | 7/8/2022 | New Construction | Municipality | $ 12,499,660.00 | $ 12,499,660.00 | $ - | Under Construction | 43.6532 | -79.3832 |
Toronto | Ontario | Stream A Toronto - Trenton & Cedarvale Ave | 31 | 31 | - | Rapid Housing Initiative | The City of Toronto | 4/28/2022 | New Construction | Municipality | $ 6,815,704.00 | $ 6,815,704.00 | $ - | Built | 43.6982 | -79.3165156 |
Toronto | Ontario | Shelter | 220 | 220 | 47 | National Housing Co-Investment Fund | Birchmount Green Inc. | 4/13/2022 | New Construction | Private Enterprise/Builder/Developer | $ 72,481,176.00 | $ 2,602,933.00 | $ 69,878,243.00 | Under Construction | 43.6532 | -79.3832 |
Toronto | Ontario | 100 Broadway | 412 | 374 | 65 | Rental Construction Financing Initiative | Reserve Properties and Westdale Properties | 8/6/2021 | New Construction | Private Enterprise/Builder/Developer | $ 178,950,000.00 | $ - | $ 178,950,000.00 | Under Construction | 43.7113 | -79.391996 |
Toronto | Ontario | 2346Weston.com Inc | 127 | 127 | 22 | Rental Construction Financing Initiative | 2346Weston.Com Inc | 7/9/2021 | New Construction | Private Enterprise/Builder/Developer | $ 35,000,000.00 | $ - | $ 35,000,000.00 | Under Construction | 43.7058 | -79.5312452 |
Toronto | Ontario | Stream A Toronto - 292 Parliament | 24 | 24 | - | Rapid Housing Initiative | The City of Toronto | 6/16/2021 | Repairs | Municipality | $ 1,213,429.00 | $ 1,213,429.00 | $ - | Built | 43.6576 | -79.365241 |
Toronto | Ontario | Stream A Toronto - 150 Dunn Ave. | 51 | 51 | - | Rapid Housing Initiative | The City of Toronto | 6/4/2021 | New Construction | Municipality | $ 14,060,700.00 | $ 14,060,700.00 | $ - | Under Construction | 43.6358 | -79.4329773 |
Toronto | Ontario | Ridgeford Charitable Foundation | 186 | 186 | 27 | Rental Construction Financing Initiative | Ridgeford Charitable Foundation | 5/21/2021 | New Construction | Not-for-profit housing org/Co-op | $ 42,000,000.00 | $ - | $ 42,000,000.00 | Built | 43.8089 | -79.2652823 |
Toronto | Ontario | Stream A Toronto - 877 Yonge Street | 244 | 244 | 0 | Rapid Housing Initiative | The City of Toronto | 4/15/2021 | Repairs | Municipality | $ 113,116,070.00 | 113116070 | 0 | Built | 43.6742575 | -79.3879758 |
Toronto | Ontario | Stream A Toronto - Super 8 - 222 Spadina | 84 | 84 | 0 | Rapid Housing Initiative | The City of Toronto | 4/15/2021 | Repairs | Municipality | $ 30,200,702.00 | 30200702 | 0 | Built | 43.6509372 | -79.397841 |
Toronto | Ontario | The Kip District | 233 | 50 | 54 | Rental Construction Financing Initiative | Concert Real Estate Corporation | 8/14/2020 | New Construction | Private Enterprise/Builder/Developer | $ 73,000,000.00 | 0 | 73000000 | Built | 43.6351949 | -79.540457 |
Toronto | Ontario | Medallion Developments | 514 | 114 | 77 | Rental Construction Financing Initiative | 3415 Weston Road Ltd. | 6/3/2020 | New Construction | Private Enterprise/Builder/Developer | $ 147,500,000.00 | 0 | 147500000 | Under Construction | 43.7502767 | -79.5416651 |
Toronto | Ontario | City of Toronto modular homes initiative | 250 | 0 | 0 | Innovation Fund | City of Toronto | 4/29/2020 | New Construction | Municipality | $ 18,750,000.00 | 12500000 | 6250000 | Under Construction | 43.653226 | -79.383184 |
Toronto | Ontario | Mirvish Village | 916 | 366 | 139 | Rental Construction Financing Initiative | 500 Bloor Street Commercial Partnership | 1/16/2020 | New Construction | Private Enterprise/Builder/Developer | $ 200,000,000.00 | 0 | 200000000 | Under Construction | 43.672522 | -79.3740595 |
Toronto | Ontario | 150 Longboat | 78 | 78 | 0 | National Housing Co-Investment Fund | Harmony B Housing Co-Operative | 8/29/2019 | Repairs | Not-for-profit housing org/Co-op | $ 2,234,714.00 | 56101 | 2178613 | Built | 42.309109 | -82.89289 |
Toronto | Ontario | DKT's Block 8 of the West Don Lands | 770 | 229 | 231 | Rental Construction Financing Initiative | WDL 8 LP | 6/27/2019 | New Construction | Private Enterprise/Builder/Developer | $ 357,000,000.00 | 0 | 357000000 | Under Construction | 43.6514574 | -79.3558347 |
Toronto | Ontario | Shelter | 30 | 17 | 16 | National Housing Co-Investment Fund | North York Women's Shelter | 5/31/2019 | New Construction | Not-for-profit housing org/Co-op | $ 4,961,250.00 | 4961250 | 0 | Under Construction | 43.6532 | -79.3832 |
Toronto | Ontario | Egale Centre | 35 | 35 | 5 | National Housing Co-Investment Fund | Friends of Ruby | 4/27/2019 | New Construction | Not-for-profit housing org/Co-op | $ 4,317,000.00 | 4317000 | 0 | Built | 43.6580304 | -79.3721057 |
Toronto | Ontario | Princess Management | 259 | 204 | 26 | Rental Construction Financing Initiative | Princess Apartment Construction | 3/14/2019 | New Construction | Private Enterprise/Builder/Developer | $ 89,000,000.00 | 0 | 89000000 | Built | 43.6760042 | -79.5535451 |
Toronto | Ontario | New Commons Development on behalf of WoodGreen Community Housing | 35 | 36 | 8 | National Housing Co-Investment Fund | Woodgreen Community Housing Inc | 2/22/2019 | New Construction | Not-for-profit housing org/Co-op | $ 7,938,000.00 | 1900867 | 6037133 | Built | 43.669462 | -79.3334876 |
Trenton | Nova Scotia | Pictou Landing Emergency Housing | 7 | 7 | 7 | Rapid Housing Initiative | Pictou Landing First Nation | 6/19/2021 | New Construction | Indigenous Group | $ 1,270,459.00 | 1270459 | 0 | Built | 45.616537 | -62.636322 |
Trois-Rivières | Quebec | Collectif des femmes immigrantes du Québec RHI2 | 18 | 16 | 0 | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2023 | Repairs | Province | $ 9,400,000.00 | 9400000 | 0 | Financial Commitments | 45.537399 | -73.601736 |
Trois-Rivières | Quebec | Maison de Connivence RHI2 | 2 | 2 | 0 | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | Repairs | Province | $ 520,000.00 | 520000 | 0 | Under Construction | 46.349091 | -72.5461 |
Trois-Rivières | Quebec | Habitations communautaires Mauricie Projet RHI2 | 12 | 12 | 0 | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 2,700,000.00 | 2700000 | 0 | Under Construction | 46.369723 | -72.504009 |
Trois-Rivières | Quebec | SHQ - ACL Saint-Philippe | 36 | 0 | 0 | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,486,000.00 | 2486000 | 0 | Built | 46.3337468 | -72.5511891 |
Burnaby | British Columbia | Sunset Court - Boiler | 8 | 48 | 0 | National Housing Co-Investment Fund | Affordable Housing Societies | 5/26/2021 | Repairs | Not-for-profit housing org/Co-op | $ 15,915.00 | 15915 | 0 | Built | 49.249252 | -122.979001 |
Val-d'Or | Quebec | Transitional Housing Anwatan-Miguam | 20 | 20 | 0 | Rapid Housing Initiative 2 | Société d'habitation du Québec SHQ | 2/22/2022 | New Construction | Province | $ 4,800,000.00 | 4800000 | 0 | Financial Commitments | 48.104357 | -77.787844 |
Vancouver | British Columbia | Shelter | 154 | 108 | 8 | National Housing Co-Investment Fund | CLT 0007 COMMUNITY SOCIETY | 9/29/2023 | New Construction | Not-for-profit housing org/Co-op | $ 15,400,000.00 | 15400000 | 0 | Under Construction | 49.2827 | -123.1207 |
Vancouver | British Columbia | 3600 Arbutus | 118 | 65 | 118 | Rental Construction Financing Initiative | PCI 3619 Arbutus Project Limited Partnership | 9/7/2023 | New Construction | Private Enterprise/Builder/Developer | $ 59,000,000.00 | 0 | 59000000 | Under Construction | 49.253946 | -123.153144 |
Vancouver | British Columbia | W42 | 215 | 154 | 22 | Rental Construction Financing Initiative | W42 Limited Partnership | 9/22/2023 | New Construction | Private Enterprise/Builder/Developer | $ 107,500,000.00 | 0 | 107500000 | Under Construction | 49.258203 | -123.110976 |
Vancouver | British Columbia | BCR 9 - 5728 Gray Avenue | 150 | 150 | 15 | Rental Construction Financing Initiative | UBC Properties Investments Ltd. | 8/16/2023 | New Construction | Private Enterprise/Builder/Developer | $ 61,500,000.00 | 0 | 61500000 | Under Construction | 49.252986 | -123.231955 |
Vancouver | British Columbia | Senakw - Phase 1 Tower 2 | 492 | 98 | 53 | Rental Construction Financing Initiative | Senakw (Building 2) LP | 9/6/2022 | New Construction | Other (Please specify) | $ 231,514,000.00 | 0 | 231514000 | Under Construction | 49.273044 | -123.146197 |
Vancouver | British Columbia | Senakw - Phase 1 Tower 1 | 333 | 67 | 37 | Rental Construction Financing Initiative | Senakw (Building 1) LP | 9/6/2022 | New Construction | Other (Please specify) | $ 155,401,000.00 | 0 | 155401000 | Under Construction | 49.273044 | -123.146197 |
Vancouver | British Columbia | Transitional Housing | 231 | 181 | 46 | National Housing Co-Investment Fund | Vancouver Chinatown Foundation for Community Revitalization | 7/28/2021 | New Construction | Not-for-profit housing org/Co-op | $ 18,500,000.00 | 18500000 | 0 | Built | 49.281825 | -123.105723 |
Vancouver | British Columbia | UBC Properties Investments Ltd | 110 | 44 | 14 | Rental Construction Financing Initiative | UBC Properties Investments Ltd. | 9/7/2023 | New Construction | Private Enterprise/Builder/Developer | $ 44,265,000.00 | 0 | 44265000 | Built | 49.245426 | -123.230265 |
Vancouver | British Columbia | Mundell House | 136 | 57 | 14 | Rental Construction Financing Initiative | UBC Properties Investments Ltd. | 9/7/2023 | New Construction | Private Enterprise/Builder/Developer | $ 46,450,000.00 | 0 | 46450000 | Built | 49.249542 | -123.237932 |
Vancouver | British Columbia | Wilkinson | 104 | 72 | 10 | Rental Construction Financing Initiative | Cressey (Wilkinson) Development LLP | 10/13/2023 | New Construction | Private Enterprise/Builder/Developer | $ 48,500,000.00 | 0 | 48500000 | Built | 49.26935 | -123.110496 |
Vancouver | British Columbia | Kelly Court | 45 | 41 | 0 | National Housing Co-Investment Fund | Metro Vancouver Housing Corporation | 4/16/2019 | Repairs | Municipality | $ 1,321,824.00 | 1321824 | 0 | Under Construction | 49.257879 | -123.041739 |
Vancouver | British Columbia | 1015 East Hasting Mixed Use (Vancouver Aboriginal Friendship Centre) | 192 | 112 | 10 | National Housing Co-Investment Fund | Provincial Rental Housing Corporation (PRHC) | 8/10/2023 | New Construction | Province | $ 19,250,627.00 | 19250627 | 0 | Under Construction | 49.281833 | -123.081848 |
Vancouver | British Columbia | 3572 Glen Dr | 139 | 39 | 139 | Rental Construction Financing Initiative | Peterson Kingsway Limited Partnership | 8/3/2023 | New Construction | Private Enterprise/Builder/Developer | $ 65,687,000.00 | 0 | 65687000 | Under Construction | 49.249591 | -123.07496 |
Vancouver | British Columbia | River District Parcel 14 | 178 | 47 | 20 | Rental Construction Financing Initiative | River District Parcel 14 LP | 8/3/2023 | New Construction | Private Enterprise/Builder/Developer | $ 79,350,000.00 | 0 | 79350000 | Under Construction | 49.2161 | -123.036 |
Vancouver | British Columbia | F19 | 104 | 32 | 104 | Rental Construction Financing Initiative | Rize Alliance Assets Inc. | 8/3/2023 | New Construction | Private Enterprise/Builder/Developer | $ 63,500,000.00 | 0 | 63500000 | Built | 49.254179 | -123.090095 |
Vancouver | British Columbia | Sen̓áḵw | 2978 | 117 | 62 | Rental Construction Financing Initiative | Senakw (Building 3) LP | 9/6/2022 | New Construction | Partnership | $ 281,081,000.00 | 0 | 281081000 | Under Construction | 49.2622776 | -123.1683392 |
Vancouver | British Columbia | ALT Hastings Housing Project | 111 | 111 | 16 | National Housing Co-Investment Fund | Aboriginal Land Trust Society | 6/29/2022 | New Construction | Not-for-profit housing org/Co-op | $ 8,367,000.00 | 8367000 | 0 | Built | 49.281088 | -123.1029031 |
Vancouver | British Columbia | Covenant House Vancouver Capital Expansion Phase II | 80 | 0 | 10 | National Housing Co-Investment Fund | Covenant House Vancouver | 6/16/2022 | New Construction | Not-for-profit housing org/Co-op | $ 7,843,827.00 | 7843827 | 0 | Built | 49.2753974 | -123.126338 |
Vancouver | British Columbia | 524-528 Powell St Vancouver | 114 | 114 | 25 | National Housing Co-Investment Fund | Lookout Housing and Health Soceity | 5/26/2022 | New Construction | Not-for-profit housing org/Co-op | $ 35,898,873.00 | 7321828 | 28577045 | Under Construction | 49.2827915 | -123.0925532 |
Vancouver | British Columbia | 1425 and 1451 East 12th Avenue Affordable Housing Redevelopment | 157 | 57 | 32 | National Housing Co-Investment Fund | Brightside Community Homes Foundation | 2/23/2022 | New Construction | Not-for-profit housing org/Co-op | $ 44,518,087.00 | 3000000 | 41518087 | Under Construction | 49.259884 | -123.075694 |
Vancouver | British Columbia | 162 Main St. | 68 | 0 | 0 | Rapid Housing Initiative 2 | City of Vancouver | 11/15/2021 | New Construction | Municipality | $ 23,771,737.00 | 23771737 | 0 | Under Construction | 49.282724 | -123.098596 |
Vancouver | British Columbia | 545 Cordova | 20 | 0 | 0 | Rapid Housing Initiative 2 | City of Vancouver | 11/15/2021 | New Construction | Municipality | $ 8,001,228.00 | 8001228 | 0 | Under Construction | 49.2824003 | -123.0923813 |
Vancouver | British Columbia | 2109 E Hasting Affordable Rental Building | 42 | 29 | 26 | Rental Construction Financing Initiative | Mosaic Homes | 8/11/2021 | New Construction | Private Enterprise/Builder/Developer | $ 22,750,000.00 | 0 | 22750000 | Built | 49.2814453 | -123.0614778 |
Vancouver | British Columbia | 3600 East Hastings Street | 94 | 19 | 94 | Rental Construction Financing Initiative | PCI Hastings Project Corp. and Hastings 3600 Ventures Corp. | 8/11/2021 | New Construction | Private Enterprise/Builder/Developer | $ 46,600,000.00 | 0 | 46600000 | Under Construction | 49.2808516 | -123.0252666 |
Vancouver | British Columbia | 3680 East Hastings Street | 118 | 24 | 118 | Rental Construction Financing Initiative | PCI Hastings Project Corp. and East Hastings 3680 Ventures Corp. | 8/11/2021 | New Construction | Private Enterprise/Builder/Developer | $ 58,000,000.00 | 0 | 58000000 | Under Construction | 49.2808501 | -123.024176 |
Vancouver | British Columbia | leləm̓ Village | 173 | 62 | 18 | Rental Construction Financing Initiative | Block F Limited Partnership | 8/4/2021 | New Construction | Indigenous Group | $ 88,000,000.00 | 0 | 88000000 | Built | 49.2636266 | -123.2267178 |
Vancouver | British Columbia | River District, Parcel 27 | 119 | 119 | 12 | Rental Construction Financing Initiative | River District Parcel 27 LP | 7/29/2021 | New Construction | Private Enterprise/Builder/Developer | $ 54,000,000.00 | 0 | 54000000 | Built | 49.2060328 | -123.0335015 |
Vancouver | British Columbia | Transitional Housing | 231 | 6 | 0 | National Housing Co-Investment Fund | Vancouver Chinatown Foundation for Community Revitalization | 7/28/2021 | New Construction | Not-for-profit housing org/Co-op | $ 700,000.00 | 700000 | 0 | Built | 49.282729 | -123.120738 |
Vancouver | British Columbia | Delux Hotel | 24 | 0 | 0 | Rapid Housing Initiative | BC Housing Management Commission | 6/25/2021 | Repairs | Province | $ 9,050,000.00 | 9050000 | 0 | Built | 49.236084 | -123.039492 |
Vancouver | British Columbia | 3625 Sawmill Cr | 119 | 85 | 18 | Rental Construction Financing Initiative | Catalyst Community Developments Society | 6/21/2021 | New Construction | Not-for-profit housing org/Co-op | $ 39,775,000.00 | 0 | 39775000 | Built | 49.2067946 | -123.0257524 |
Vancouver | British Columbia | LUMA Native BCH Housing Society | 23 | 23 | 3 | Rental Construction Financing Initiative | Lu'ma Native BCH Housing Society | 5/10/2021 | New Construction | Indigenous Group | $ 6,375,000.00 | 0 | 6375000 | Built | 49.2504004 | -123.0242489 |
Vancouver | British Columbia | Stream A Vancouver - Best Western | 68 | 68 | 0 | Rapid Housing Initiative | City of Vancouver | 4/16/2021 | Repairs | Municipality | $ 30,000,000.00 | 30000000 | 0 | Built | 49.2617877 | -123.0979675 |
Vancouver | British Columbia | BC HOUSING VANCOUVER - East Hastings | 33 | 33 | 0 | Rapid Housing Initiative | BC Housing Management Commission | 3/31/2021 | Renewals | Province | $ 4,544,000.00 | 4544000 | 0 | Built | 49.2816773 | -123.101876 |
Vancouver | British Columbia | BC HOUSING VANCOUVER - Granville | 75 | 76 | 0 | Rapid Housing Initiative | BC Housing Management Commission | 3/31/2021 | Renewals | Province | $ 12,442,900.00 | 12442900 | 0 | Built | 49.2791301 | -123.1237673 |
Vancouver | British Columbia | BC HOUSING VANCOUVER - West Pender | 80 | 0 | 0 | Rapid Housing Initiative | BC Housing Management Commission | 3/31/2021 | Renewals | Province | $ 36,157,830.00 | 36157830 | 0 | Built | 49.2833719 | -123.1123444 |
Vancouver | British Columbia | Stream A Vancouver - Days Inn (2075 Kingsway) | 65 | 65 | 0 | Rapid Housing Initiative | City of Vancouver | 3/1/2021 | Repairs | Municipality | $ 21,525,275.00 | 21525275 | 0 | Under Construction | 49.2451583 | -123.063206 |
Vancouver | British Columbia | Vancity initiative | 2584 | 2646 | 0 | Innovation Fund | KIRA GERWING | 11/2/2019 | 0 | Private Enterprise/Builder/Developer | $ 6,000,000.00 | 6000000 | 0 | Under Construction | 49.279946 | -123.111237 |
Vancouver | British Columbia | Covenant House Vancouver Capital Expansion (Phase 1) | 54 | 14 | 4 | National Housing Co-Investment Fund | Covenant House Vancouver | 8/26/2019 | New Construction | Not-for-profit housing org/Co-op | $ 5,089,232.00 | 5089232 | 0 | Built | 49.2751271 | -123.1267389 |
Vancouver | British Columbia | Community Land Trust | 140 | 102 | 14 | Rental Construction Financing Initiative | CLT 0009 Community Society | 8/7/2019 | New Construction | Not-for-profit housing org/Co-op | $ 53,000,000.00 | 0 | 53000000 | Built | 49.2076703 | -123.039755 |
Vancouver | British Columbia | Shelter | 68 | 68 | 4 | National Housing Co-Investment Fund | Provincial Rental Housing Corporation | 8/7/2019 | New Construction | Province | $ 5,879,232.00 | 5879232 | 0 | Built | 49.2827 | -123.1207 |
Vancouver | British Columbia | Shelter | 1500 | 1500 | 75 | National Housing Co-Investment Fund | Financial Solutions - Portfolio Account | 8/6/2019 | New Construction | Province | $ 75,000,000.00 | 75000000 | 0 | Under Construction | 49.2827 | -123.1207 |
Vancouver | British Columbia | VAHA 188 East 6th Avenue | 145 | 44 | 24 | Rental Construction Financing Initiative | Catalyst Community Developments Society | 8/2/2019 | New Construction | Not-for-profit housing org/Co-op | $ 48,500,000.00 | 0 | 48500000 | Built | 49.265353 | -123.101354 |
Vancouver | British Columbia | Women & Families Centre | 63 | 63 | 13 | National Housing Co-Investment Fund | Union Gospel Mission | 2/11/2019 | New Construction | Not-for-profit housing org/Co-op | $ 11,375,000.00 | 11375000 | 0 | Built | 49.2818717 | -123.090986 |
Vancouver | British Columbia | Conrad by Cressey Development | 115 | 71 | 11 | Rental Construction Financing Initiative | Cressey (Wilkinson) Development LLP | 11/19/2018 | New Construction | Private Enterprise/Builder/Developer | $ 40,239,000.00 | 0 | 40239000 | Built | 49.2543616 | -123.0682241 |
Various | Ontario | Indwell | 326 | 328 | 0 | Innovation Fund | Indwell Community Homes | 7/20/2021 | New Construction | Not-for-profit housing org/Co-op | $ 5,000,000.00 | 0 | 5000000 | Under Construction | 43.2600089 | -79.8524157 |
Various | Quebec | Fonds social d'investissement immobilier | 1500 | 1500 | 150 | Innovation Fund | Fonds Immobilier de Solidarité FTQ | 5/4/2021 | Repairs | Private Enterprise/Builder/Developer | $ 30,000,000.00 | 0 | 30000000 | Under Construction | 46.8131 | -71.2075 |
Various | Quebec | Entente Canada-Quebec | 1203 | 1201 | 0 | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | 0 | Province | $ 115,944,917.00 | 115944917 | 0 | Under Construction | 46.8131 | -71.2075 |
Various | Ontario | United Church of Canada | 5000 | 60 | 0 | Innovation Fund | United Property Resource Corporation | 9/18/2020 | New Construction | Faith-based organization | $ 20,000,000.00 | 0 | 20000000 | Under Construction | 45.42153 | -75.697193 |
Various | British Columbia | CRD | 1580 | 541 | 73 | Innovation Fund | Capital Regional District | 11/2/2019 | New Construction | Municipality | $ 40,000,000.00 | 40000000 | 0 | Under Construction | 49.2651026 | -117.6512294 |
Various | British Columbia | HPC Housing Investment Corporation (HI-C) | 2500 | 5095 | 0 | Innovation Fund | Shayne Ramsay | 8/21/2019 | 0 | Province | $ 20,000,000.00 | 20000000 | 0 | Under Construction | 49.282729 | -123.120738 |
Various | Various | Habitat for Humanity Canada | 916 | 1010 | 183 | National Housing Co-Investment Fund | Habitat for Humanity Canada | 8/13/2019 | New Construction | Not-for-profit housing org/Co-op | $ 60,814,425.00 | 60814425 | 0 | Under Construction | 44.3199237 | -78.3084174 |
Various | Alberta | ARDN | 63 | 0 | 0 | Innovation Fund | Rural Development Network | 10/23/2018 | 0 | Not-for-profit housing org/Co-op | $ 335,000.00 | 0 | 335000 | Under Construction | 53.564725 | -113.567173 |
Vaudreuil-Dorion | Quebec | Projet Racine Vaudreuil | 81 | 78 | 81 | Rental Construction Financing Initiative | Projet Racine Vaudreuil | 2/28/2023 | New Construction | Private Enterprise/Builder/Developer | $ 28,065,000.00 | 0 | 28065000 | Under Construction | 45.3813097 | -74.0135846 |
Vaughan | Ontario | Lou Fruitman Reena Residence | 79 | 65 | 30 | National Housing Co-Investment Fund | Reena | 7/7/2021 | New Construction | Not-for-profit housing org/Co-op | $ 17,669,030.83 | 3684269 | 13984762 | Built | 43.8021489 | -79.4523729 |
Vernon | British Columbia | Okanagan Indian Band Community Housing Fund | 16 | 16 | 4 | National Housing Co-Investment Fund | Okanagan Indian Band | 4/5/2023 | New Construction | Indigenous Group | $ 339,595.00 | 339595 | 0 | Built | 50.3479756 | -119.307327 |
Vernon | British Columbia | VNHS 27th Avenue Project | 38 | 19 | 8 | National Housing Co-Investment Fund | Vernon Native Housing Society | 2/14/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,273,000.00 | 2273000 | 0 | Built | 50.2547814 | -119.3118802 |
Vernon | British Columbia | Vernon Native Housing Society | 38 | 13 | 8 | National Housing Co-Investment Fund | Vernon Native Housing Society | 2/14/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,451,773.00 | 2451773 | 0 | Under Construction | 50.2544956 | -119.3109032 |
Victoria | British Columbia | Catherine St. Supportive Housing | 45 | 0 | 0 | Rapid Housing Initiative 2 | Capital Regional District | 11/5/2021 | New Construction | Municipality | $ 11,290,921.00 | 11290921 | 0 | Built | 48.4344152 | -123.3845402 |
Victoria | British Columbia | Hudson Place Two | 245 | 180 | 39 | Rental Construction Financing Initiative | Hudson Place Limited Partnership | 3/31/2021 | New Construction | Private Enterprise/Builder/Developer | $ 100,000,000.00 | 0 | 100000000 | Built | 48.4298619 | -123.3622854 |
Victoria | British Columbia | Stream A Victoria - Albina | 52 | 52 | 0 | Rapid Housing Initiative | Capital Regional District | 3/24/2021 | New Construction | Municipality | $ 6,930,035.00 | 6930035 | 0 | Built | 48.4483616 | -123.3975908 |
Victoria | British Columbia | Stream A Victoria - Prosser | 40 | 40 | 0 | Rapid Housing Initiative | Capital Regional District | 3/24/2021 | New Construction | Municipality | $ 6,126,467.00 | 6126467 | 0 | Built | 48.5882552 | -123.4197382 |
Victoria | British Columbia | The Sawyer Block | 60 | 60 | 6 | Rental Construction Financing Initiative | Salient Projects (2016) Ltd | 8/20/2019 | New Construction | Private Enterprise/Builder/Developer | $ 13,250,000.00 | 0 | 13250000 | Built | 48.424489 | -123.361631 |
Victoria | British Columbia | Vancouver Island Investment Corporation project | 47 | 28 | 5 | Rental Construction Financing Initiative | Vancouver Island Investment Corp. | 9/14/2018 | New Construction | Private Enterprise/Builder/Developer | $ 21,144,000.00 | 0 | 21144000 | Built | 48.4135137 | -123.3574371 |
Wagmatcook 1 | Nova Scotia | Wagmatcook Emergency Housing Project | 15 | 15 | 0 | Rapid Housing Initiative 2 | Wagmatcook First Nation | 5/23/2023 | New Construction | Indigenous Governing Body | $ 3,765,123.00 | 3765123 | 0 | Under Construction | 46.077188 | -60.918206 |
Wasagamack | Manitoba | Wasagamack First Nation 3-Bedroom 5 Unit Project | 5 | 5 | 0 | Rapid Housing Initiative 2 | Wasagamack First Nation | 5/29/2023 | New Construction | Indigenous Governing Body | $ 1,169,312.29 | 1169312.29 | 0 | Built | 53.884871 | -94.920753 |
Waskaganish | Quebec | Portfolio Cree - Waskaganish | 5 | 30 | 0 | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,693,715.00 | 1693715 | 0 | Built | 51.483668 | -78.749399 |
Waswanipi | Quebec | Portfolio Cree - Waswanipi | 5 | 20 | 0 | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,489,715.00 | 1489715 | 0 | Built | 49.696662 | -75.960142 |
Waterhen 130 | Saskatchewan | WLFN RHI 2021 | 7 | 0 | 0 | Rapid Housing Initiative | Waterhen Lake First Nation | 4/15/2021 | New Construction | Indigenous Group | $ 1,439,124.00 | 1439124 | 0 | Built | 54.515483 | -108.413915 |
Waterloo | Ontario | Water Street House | 9 | 9 | 3 | National Housing Co-Investment Fund | K-W Working Centre for the Unemployed | 8/22/2019 | New Construction | Not-for-profit housing org/Co-op | $ 576,000.00 | 576000 | 0 | Built | 43.4485371 | -80.4962059 |
Watson Lake | Yukon | Rapid Housing for Liard's Vulnerable | 15 | 15 | 0 | Rapid Housing Initiative 2 | Liard First Nation | 5/6/2022 | New Construction | Indigenous Governing Body | $ 5,552,870.00 | 5552870 | 0 | Conditional Commitments | 60.062806 | -128.710913 |
Watson Lake | Yukon | Affordable Housing Projects | 9 | 0 | 0 | Rapid Housing Initiative | Yukon Housing Corporation | 6/25/2021 | New Construction | Territory | $ 3,000,000.00 | 3000000 | 0 | Under Construction | 60.774944 | -135.140096 |
Webequie | Ontario | Webequie FN RHI - Row Housing Development | 14 | 0 | 0 | Rapid Housing Initiative | Webequie First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 3,735,800.00 | 3735800 | 0 | Built | 52.948835 | -87.368495 |
Weedon | Quebec | SHQ - Moulin des Cèdres - Phase II | 26 | 0 | 0 | Rapid Housing Initiative | Société d'habitation du Québec | 1/22/2021 | New Construction | Province | $ 2,301,500.00 | 2301500 | 0 | Built | 45.6980275 | -71.460306 |
Welland | Ontario | Shelter | 42 | 0 | 0 | Rapid Housing Initiative 2 | The Regional Municipality of Niagara | 7/9/2021 | New Construction | Municipality | $ 10,515,033.00 | 10515033 | 0 | Under Construction | 42.9922 | -79.2483 |
Welland | Ontario | 867962 Ontario Ltd. | 50 | 50 | 5 | Rental Construction Financing Initiative | James Terrence Duffy | 3/15/2019 | New Construction | Private Enterprise/Builder/Developer | $ 5,980,000.00 | 0 | 5980000 | Built | 42.978124 | -79.250746 |
Wemindji | Quebec | Portfolio Cree - Wemindji | 5 | 20 | 0 | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,583,555.00 | 1583555 | 0 | Built | 53.000622 | -78.808592 |
Wendake | Quebec | Projets ICRL -Wendake | 8 | 0 | 0 | Rapid Housing Initiative | La Première Nation Huronne Wendat | 1/22/2021 | New Construction | Indigenous Group | $ 1,878,510.00 | 1878510 | 0 | Built | 46.856583 | -71.3547718 |
West Kelowna | British Columbia | HARBOUR RIDGE APARTMENTS | 120 | 120 | 12 | Rental Construction Financing Initiative | Harbour Ridge Apartments LLP | 8/9/2021 | New Construction | Partnership | $ 34,475,000.00 | 0 | 34475000 | Built | 50.20539 | -119.644987 |
Wetaskiwin | Alberta | Quantum Apartments | 36 | 7 | 5 | Rental Construction Financing Initiative | Quantum Apartments and Josan Properties | 2/2/2021 | New Construction | Private Enterprise/Builder/Developer | $ 5,800,000.00 | 0 | 5800000 | Built | 52.972029 | -113.625803 |
Whapmagoostui | Quebec | Portfolio Cree - Whapmagoostui | 5 | 10 | 0 | Rapid Housing Initiative | Cree Nation Government | 3/17/2021 | New Construction | Indigenous Group | $ 1,840,035.00 | 1840035 | 0 | Built | 55.281591 | -77.756345 |
Whatì | Northwest Territories | Providing 18 affordable housing units in the Tlicho Region | 18 | 0 | 0 | Rapid Housing Initiative | Tlicho Government | 7/26/2021 | New Construction | Indigenous Group | $ 3,929,597.36 | 3929597.36 | 0 | Built | 62.7774571 | -116.0399863 |
Whistler | British Columbia | 1450 Mount Fee Road, Whistler | 48 | 48 | 5 | Rental Construction Financing Initiative | Whistler Housing Authority Ltd | 10/13/2023 | New Construction | Municipality | $ 15,200,000.00 | 0 | 15200000 | Financial Commitments | 50.079945 | -123.040671 |
Whistler | British Columbia | 1315 Cloudburst | 58 | 58 | 6 | Rental Construction Financing Initiative | Whistler Sport Legacies | 10/13/2023 | New Construction | Not-for-profit housing org/Co-op | $ 19,800,000.00 | 0 | 19800000 | Built | 50.077674 | -123.044326 |
Whistler | British Columbia | WHA | 24 | 0 | 0 | Innovation Fund | Whistler Housing Authority Ltd | 7/15/2019 | 0 | Municipality | $ 1,725,000.00 | 0 | 1725000 | Under Construction | 50.1208 | -122.954 |
Whistler | British Columbia | 1330 Cloudburst Drive | 45 | 45 | 4 | National Housing Co-Investment Fund | Whistler Housing Authority Ltd | 3/26/2021 | New Construction | Municipality | $ 8,317,389.83 | 393968.13 | 7923422 | Built | 50.077848 | -123.043316 |
Whistler | British Columbia | 1020 Legacy Way - Whistler Housing Authority | 24 | 17 | 4 | Rental Construction Financing Initiative | Whistler Housing Authority Ltd | 7/15/2019 | New Construction | Municipality | $ 7,300,000.00 | 0 | 7300000 | Built | 50.080286 | -123.040422 |
Whitby | Ontario | Region of Durham - Muslim Welfare Residences | 26 | 26 | 0 | Rapid Housing Initiative 2 | Regional Municipality of Durham | 3/2/2022 | Repairs | Municipality | $ 2,879,473.00 | 2879473 | 0 | Built | 43.882678 | -78.93036 |
Whitby | Ontario | Region of Durham - Otter Creek Co-op | 18 | 0 | 0 | Rapid Housing Initiative 2 | Regional Municipality of Durham | 1/6/2022 | New Construction | Municipality | $ 4,749,285.00 | 4749285 | 0 | Under Construction | 43.887739 | -78.968923 |
Whitefish Lake 6 | Alberta | Whitefish Lake First Nation 459 Affordable Housing Project | 20 | 20 | 0 | Rapid Housing Initiative 2 | Whitefish Lake First Nation #459 | 4/28/2023 | New Construction | Indigenous Governing Body | $ 5,554,391.65 | 5554391.65 | 0 | Built | 55.908325 | -115.638719 |
Whitehorse | Yukon | CYFN Shelter for Women & Children - NHCF | 47 | 15 | 6 | National Housing Co-Investment Fund | Council of Yukon First Nations | 5/29/2020 | New Construction | Indigenous Group | $ 2,736,602.00 | 2736602 | 0 | Under Construction | 60.7197 | -135.0523 |
Whitehorse | Yukon | Kaushee's Place Upgrades | 23 | 5 | 2 | National Housing Co-Investment Fund | Kaushee’s Place Housing Society | 8/30/2023 | Repairs | Not-for-profit housing org/Co-op | $ 2,899,725.00 | 2899725 | 0 | Under Construction | 60.713018 | -135.054973 |
Whitehorse | Yukon | Bringing Citizens Home | 20 | 0 | 0 | Rapid Housing Initiative | Champagne and Aishihik First Nations | 6/25/2021 | New Construction | Indigenous Group | $ 6,070,693.00 | 6070693 | 0 | Built | 60.7239 | -135.107 |
Whitehorse | Yukon | Shelter | 45 | 45 | 9 | National Housing Co-Investment Fund | Challenge Disability Resource Groupo | 7/20/2022 | New Construction | Not-for-profit housing org/Co-op | $ 15,100,000.00 | 10000000 | 5100000 | Built | 60.7197 | -135.0523 |
Whitehorse | Yukon | 4051 4th avenue | 55 | 55 | 6 | National Housing Co-Investment Fund | SAFE AT HOME SOCIETY | 1/31/2022 | New Construction | Indigenous Group | $ 10,000,000.00 | 10000000 | 0 | Under Construction | 60.714718 | -135.051689 |
Whitehorse | Yukon | 4051 4th Avenue | 55 | 55 | 0 | Rapid Housing Initiative 2 | Yukon Housing Corporation | 1/31/2022 | Renewals | Territory | $ 5,000,000.00 | 5000000 | 0 | Financial Commitments | 60.714718 | -135.051689 |
Whitehorse | Yukon | Boreal Commons | 87 | 81 | 18 | Rental Construction Financing Initiative | SHVT Inc | 7/22/2021 | New Construction | Private Enterprise/Builder/Developer | $ 22,200,000.00 | 0 | 22200000 | Built | 60.7724126 | -135.1055143 |
Whitehorse | Yukon | Normandy Manor | 84 | 26 | 0 | National Housing Co-Investment Fund | KBC Developments Inc. | 3/2/2021 | New Construction | Private Enterprise/Builder/Developer | $ 34,500,000.00 | 5000000 | 29500000 | Built | 60.739035 | -135.091584 |
Whitehorse | Yukon | TKC Mobile Homes | 11 | 0 | 0 | Rapid Housing Initiative | Ta'an Kwäch'än Council | 6/25/2021 | New Construction | Indigenous Group | $ 1,325,000.00 | 1325000 | 0 | Built | 60.735927 | -135.076832 |
Whycocomagh 2 | Nova Scotia | We'koqma'q Housing Initiative | 12 | 0 | 0 | Rapid Housing Initiative | We'koqma'q First Nation | 4/16/2021 | New Construction | Indigenous Group | $ 2,142,937.23 | 2142937.23 | 0 | Built | 46.137774 | -61.143158 |
Windsor | Ontario | 3100 Meadowbrook Lane Development | 145 | 76 | 46 | National Housing Co-Investment Fund | Windsor Essex Community Housing Corporation | 9/11/2023 | New Construction | Municipality | $ 33,841,000.00 | 13341000 | 20500000 | Under Construction | 42.305594 | -82.9315 |
Windsor | Ontario | WECHC Regeneration Plan - Capital Backlog Repair and Renewal (M) | 4707 | 4707 | 1255 | National Housing Co-Investment Fund | Windsor Essex Community Housing Corporation | 8/4/2022 | Repairs | Municipality | $ 90,000,000.00 | 36000000 | 54000000 | Under Construction | 42.309109 | -82.89289 |
Windsor | Ontario | City of Windsor- 462 Crawford | 15 | 0 | 0 | Rapid Housing Initiative 2 | The Corporation of the City of Windsor | 3/17/2022 | New Construction | Municipality | $ 2,671,113.00 | 2671113 | 0 | Built | 42.3127018 | -83.0479387 |
Windsor | Ontario | Shelter | 12 | 0 | 0 | Rapid Housing Initiative 2 | The Corporation of the City of Windsor | 3/17/2022 | New Construction | Municipality | $ 4,808,004.00 | 4808004 | 0 | Under Construction | 42.3149 | -83.0364 |
Winnipeg | Manitoba | Edmonton Transitional Housing for Women and Children who have experienced Gender-based violence (UWCRC 2.0 Inc.) | 11 | 0 | 0 | Rapid Housing Initiative 3 | City of Winnipeg | 6/12/2023 | New Construction | Municipality | $ 4,686,937.19 | 4686937.19 | 0 | Financial Commitments | 49.89676 | -97.149576 |
Winnipeg | Manitoba | Wahbung Abinoonjiaag | 26 | 0 | 0 | Rapid Housing Initiative 3 | City of Winnipeg | 6/12/2023 | New Construction | Municipality | $ 1,366,303.22 | 1366303.22 | 0 | Financial Commitments | 49.909911 | -97.103063 |
Winnipeg | Manitoba | Manitoba Metis Federation | 14 | 0 | 0 | Rapid Housing Initiative 3 | City of Winnipeg | 6/12/2023 | New Construction | Municipality | $ 4,158,915.54 | 4158915.54 | 0 | Financial Commitments | 49.940452 | -97.086828 |
Winnipeg | Manitoba | Spence Neighbourhood Association | 6 | 6 | 0 | Rapid Housing Initiative 3 | City of Winnipeg | 6/8/2023 | New Construction | Municipality | $ 1,419,760.26 | 1419760.26 | 0 | Financial Commitments | 49.891718 | -97.15607 |
Winnipeg | Manitoba | 390 Ross | 47 | 47 | 15 | National Housing Co-Investment Fund | Home First Winnipeg Inc. | 11/21/2021 | New Construction | Not-for-profit housing org/Co-op | $ 2,220,035.00 | 2220035 | 0 | Built | 49.899426 | -97.146198 |
Winnipeg | Manitoba | The Village | 22 | 22 | 4 | National Housing Co-Investment Fund | Ma Mawi Wi Chi Itata Centre Inc. | 4/18/2023 | New Construction | Indigenous Group | $ 4,350,000.00 | 4350000 | 0 | Under Construction | 49.9039532 | -97.1341452 |
Winnipeg | Manitoba | 388 Young | 69 | 29 | 0 | National Housing Co-Investment Fund | Paskwayak Construction Limited Partnership | 1/11/2023 | New Construction | Partnership | $ 15,620,050.00 | 4500000 | 11120050 | Under Construction | 49.8918886 | -97.1553544 |
Winnipeg | Manitoba | Columbus House Riverbank Stabilization | 70 | 70 | 7 | National Housing Co-Investment Fund | Columbus Centennial Seniors Cooperative Housing Ltd | 8/24/2022 | Repairs | Not-for-profit housing org/Co-op | $ 585,022.00 | 322000 | 263022 | Built | 49.9043014 | -97.1073853 |
Winnipeg | Manitoba | Westboine Park Housing Co-Op | 188 | 122 | 0 | National Housing Co-Investment Fund | Westboine Park Housing Co-op Ltd | 3/14/2022 | Repairs | Not-for-profit housing org/Co-op | $ 11,450,000.00 | 2573455.08 | 8876545 | Built | 49.8616738 | -97.2936852 |
Winnipeg | Manitoba | Manitoba Metis Federation | 22 | 0 | 0 | Rapid Housing Initiative 2 | The City of Winnipeg | 1/11/2022 | Repairs | Municipality | $ 3,417,708.00 | 3417708 | 0 | Built | 49.9040148 | -97.1351898 |
Winnipeg | Manitoba | Shelter | 16 | 0 | 0 | Rapid Housing Initiative 2 | The City of Winnipeg | 1/11/2022 | Repairs | Municipality | $ 4,309,035.00 | 4309035 | 0 | Under Construction | 49.8954 | -97.1385 |
Winnipeg | Manitoba | Westminster Housing Society | 21 | 21 | 0 | Rapid Housing Initiative 2 | The City of Winnipeg | 1/11/2022 | New Construction | Municipality | $ 5,049,000.00 | 5049000 | 0 | Under Construction | 49.8857949 | -97.1516377 |
Winnipeg | Manitoba | Misericordia Assisted Living Housing | 99 | 31 | 97 | National Housing Co-Investment Fund | Misericordia Corporation | 8/10/2021 | New Construction | Not-for-profit housing org/Co-op | $ 25,792,978.00 | 3865000 | 21927978 | Under Construction | 49.8805259 | -97.1601118 |
Winnipeg | Manitoba | CentreVenture | 102 | 52 | 11 | Innovation Fund | CentreVenture Development Corporation | 7/30/2021 | New Construction | Not-for-profit housing org/Co-op | $ 2,600,000.00 | 2600000 | 0 | Under Construction | 49.89986 | -97.14056 |
Winnipeg | Manitoba | Riverwood House | 40 | 40 | 9 | National Housing Co-Investment Fund | Riverwood Church Community Inc. | 6/24/2021 | New Construction | Not-for-profit housing org/Co-op | $ 4,996,824.00 | 2523764 | 2473060 | Built | 49.9079914 | -97.110478 |
Winnipeg | Manitoba | 10 Houses for Hollow Water | 10 | 0 | 0 | Rapid Housing Initiative | Hollow Water First Nation | 5/18/2021 | New Construction | Indigenous Group | $ 2,216,300.00 | 2216300 | 0 | Built | 51.17772877 | -96.29202247 |
Winnipeg | Manitoba | Park City Commons (Building O) | 87 | 87 | 9 | Rental Construction Financing Initiative | EdgeCorp Developments Ltd | 3/5/2021 | New Construction | Private Enterprise/Builder/Developer | $ 22,850,000.00 | 0 | 22850000 | Built | 49.8998588 | -97.0301214 |
Winnipeg | Manitoba | Stream A Winnipeg - New Directions | 9 | 9 | 0 | Rapid Housing Initiative | The City of Winnipeg | 12/18/2020 | Repairs | Municipality | $ 1,450,281.00 | 1450281 | 0 | Built | 49.9108194 | -97.1333797 |
Winnipeg | Manitoba | Stream A Winnipeg - Shawenim Abinoojii Inc. (SAI) | 18 | 18 | 0 | Rapid Housing Initiative | The City of Winnipeg | 12/18/2020 | Renewals | Municipality | $ 2,838,577.00 | 2838577 | 0 | Built | 49.9144367 | -97.1286735 |
Winnipeg | Manitoba | Stream A Winnipeg - Siloam Mission | 20 | 20 | 0 | Rapid Housing Initiative | The City of Winnipeg | 12/18/2020 | Repairs | Municipality | $ 1,538,578.00 | 1538578 | 0 | Built | 49.904338 | -97.138244 |
Winnipeg | Manitoba | Stream A Winnipeg - Winnipeg Housing Rehabilitation Corporation (WHRC) - subsidized rental | 17 | 17 | 0 | Rapid Housing Initiative | The City of Winnipeg | 12/18/2020 | New Construction | Municipality | $ 4,330,993.00 | 4330993 | 0 | Under Construction | 49.8878281 | -97.1649227 |
Winnipeg | Manitoba | Stream A Winnipeg - Women's Housing Salvation Army | 13 | 13 | 0 | Rapid Housing Initiative | The City of Winnipeg | 12/18/2020 | Repairs | Municipality | $ 2,338,578.00 | 2338578 | 0 | Built | 49.9018852 | -97.1349665 |
Winnipeg | Manitoba | Shelter | 120 | 0 | 120 | National Housing Co-Investment Fund | Main Street Project Inc. | 12/14/2020 | New Construction | Not-for-profit housing org/Co-op | $ 2,000,000.00 | 2000000 | 0 | Built | 49.8954 | -97.1385 |
Winnipeg | Manitoba | Shelter | 160 | 0 | 9 | National Housing Co-Investment Fund | Siloam Mission | 8/12/2020 | New Construction | Not-for-profit housing org/Co-op | $ 2,200,000.00 | 2200000 | 0 | Built | 49.8954 | -97.1385 |
Winnipeg | Manitoba | West Broadway Commons Development | 110 | 56 | 33 | National Housing Co-Investment Fund | UWCRC 2.0 Inc. | 7/8/2019 | New Construction | Not-for-profit housing org/Co-op | $ 25,555,202.00 | 7865338 | 17689864 | Built | 49.8858575 | -97.1510415 |
Winnipeg | Manitoba | Arts District | 119 | 119 | 119 | Rental Construction Financing Initiative | The University of Winnipeg CRC | 1/23/2019 | New Construction | Not-for-profit housing org/Co-op | $ 26,162,000.00 | 0 | 26162000 | Built | 49.8892899 | -97.1513174 |
Winnipeg | Manitoba | EdgeCorp Developments Ltd. | 74 | 74 | 11 | Rental Construction Financing Initiative | EdgeCorp Developments Ltd | 11/20/2018 | New Construction | Private Enterprise/Builder/Developer | $ 18,380,000.00 | 0 | 18380000 | Built | 49.8989028 | -97.0283606 |
Witchekan Lake 117 | Saskatchewan | Witchekan Lake 4 Plex | 4 | 0 | 0 | Rapid Housing Initiative | Witchekan Lake First Nation | 4/15/2021 | Renewals | Indigenous Group | $ 478,588.57 | 478588.57 | 0 | Built | 53.363742 | -107.519276 |
Wolfville | Nova Scotia | Woodman’s Grove Residences | 48 | 48 | 6 | Rental Construction Financing Initiative | Polycorp Properties Inc. | 11/15/2018 | New Construction | Private Enterprise/Builder/Developer | $ 8,170,000.00 | 0 | 8170000 | Built | 45.0970062 | -64.3374567 |
Wôlinak | Quebec | Abénakis de Wolinak | 6 | 0 | 0 | Rapid Housing Initiative | Abénakis de Wôlinak | 6/10/2021 | New Construction | Indigenous Group | $ 900,000.00 | 900000 | 0 | Under Construction | 46.3282548 | -72.4215372 |
Woodland Cree 226 | Alberta | Woodland Cree First Nation Homeless Response | 20 | 0 | 0 | Rapid Housing Initiative | Woodland Cree First Nation | 4/27/2023 | New Construction | Indigenous Group | $ 4,357,584.00 | 4357584 | 0 | Financial Commitments | 55.212242 | -119.20395 |
Woodstock | Ontario | Blossom Park | 34 | 34 | 7 | National Housing Co-Investment Fund | Indwell Community Homes | 2/11/2019 | New Construction | Not-for-profit housing org/Co-op | $ 2,907,000.00 | 2907000 | 0 | Built | 43.1450144 | -80.7452184 |
Yarmouth 33 | Nova Scotia | Acadia First Nation 2021 Housing Project | 14 | 14 | 0 | Rapid Housing Initiative 2 | Acadia First Nation | 7/18/2022 | New Construction | Indigenous Governing Body | $ 4,468,145.00 | 4468145 | 0 | Under Construction | 43.829329 | -66.077352 |
Yellowknife | Northwest Territories | Housing NWT's Affordable Seniors and Public Housing 50-plex, Yellowknife | 50 | 50 | 25 | Rapid Housing Initiative 3 | Northwest Territories Housing Corporation (NWTHC) | 10/12/2023 | New Construction | Territory | $ 20,802,091.00 | 20802091 | 0 | Financial Commitments | 62.454501 | -114.373113 |
Yellowknife | Northwest Territories | Aspen Apartments Retrofit, Yellowknife | 36 | 36 | 0 | Rapid Housing Initiative 3 | Northwest Territories Housing Corporation (NWTHC) | 6/30/2023 | New Construction | Municipality | $ 5,000,000.00 | 5000000 | 0 | Financial Commitments | 62.450015 | -114.364881 |
Yellowknife | Northwest Territories | Aspen Apartments -retrofit, Yellowknife, NWT | 36 | 36 | 0 | Federal Lands Initiative | Northwest Territories Housing Corporation (NWTHC) | 6/30/2023 | Repairs | Province | $ 2,939,999.00 | 2939999 | 0 | Under Construction | 62.450478 | -114.366662 |
Yellowknife | Northwest Territories | Supported Housing for Homeless Adults | 42 | 42 | 17 | National Housing Co-Investment Fund | Yellowknife Women's Society | 11/7/2022 | New Construction | Not-for-profit housing org/Co-op | $ 6,081,797.00 | 6081797 | 0 | Under Construction | 62.4591703 | -114.3590906 |
Yellowknife | Northwest Territories | YWCA Lynn's Place Expansion II RHI | 21 | 21 | 12 | National Housing Co-Investment Fund | YWCA NWT | 11/7/2022 | New Construction | Not-for-profit housing org/Co-op | $ 12,520,858.00 | 12520858 | 0 | Under Construction | 62.4515175 | -114.375864 |
Yellowknife | Northwest Territories | YWCA NWT Lynn's Place II | 21 | 0 | 0 | Rapid Housing Initiative 2 | YWCA NWT | 11/7/2022 | New Construction | Territory | $ 5,000,000.00 | 5000000 | 0 | Under Construction | 62.4514674 | -114.3750795 |
Yellowknife | Northwest Territories | Public Housing Expansion | 60 | 60 | 0 | National Housing Co-Investment Fund | Northwest Territories Housing Corporation | 3/22/2021 | New Construction | Territory | $ 25,500,000.00 | 25500000 | 0 | Built | 67.0389 | -126.09 |
Yellowknife | Northwest Territories | Borealis Housing Cooperative 2019 | 50 | 50 | 0 | National Housing Co-Investment Fund | Borealis Housing Co-operative Ltd | 1/18/2021 | Repairs | Not-for-profit housing org/Co-op | $ 9,052,000.00 | 1427000 | 7625000 | Built | 62.4380685 | -114.4103363 |
Yellowknife | Northwest Territories | AVENS Pavilion | 102 | 102 | 28 | National Housing Co-Investment Fund | Avens - A Community For Seniors | 10/28/2020 | New Construction | Not-for-profit housing org/Co-op | $ 38,967,838.00 | 31753794 | 7214044 | Under Construction | 62.4489604 | -114.3817215 |
York | Ontario | Elevator Modernization | 248 | 248 | 18 | National Housing Co-Investment Fund | Project Esperance/Project Hope Corporation | 7/9/2021 | Repairs | Not-for-profit housing org/Co-op | $ 514,380.00 | 232560 | 281820 | Built | 43.6931197 | -79.4688639 |
Toronto | Ontario | 58861 | 53,538 | 0 | National Housing Co-Investment Fund | Toronto Community Housing Corporation | 5/5/2019 | Repairs | Municipality | $1,341,058,079 | $527,511,843 | $813,546,236 | Under Construction | 43.6532 | -79.3832 |
What level of government is responsible for housing?
Housing is provincial jurisdiction in all provinces except Ontario. For example, BC Housing is a Crown Corporation that supports social housing, affordable housing, emergency shelters and out reach for homeless people and regulates residential construction. It also administers rent supplements.
Ontario is the only province to have passed the responsibility for funding and administering social housing to municipalities.
The Housing Accelerator Fund program skips over the provinces and is applied for by, and goes directly to, municipalities.
Provincial performance
- British Columbia took initiative and engages with the federal government, getting $2B.
- Alberta continues the age old tradition of conflict. Gets less money ($175M + $13.8M for rural).
Programs to create new supply
Apartment Construction Loan Program (Rental Construction Financing Initiative (RCFi))
- Description: Low-cost loans encouraging the construction of sustainable rental apartment projects across Canada. The minimum loan is $1,000,000, and a maximum of up to 100% of Loan to Cost (for residential loan component).
- Funding: $25.75B in loans
Major part of the Strategy. Provides low-cost, long-term loans for constructing purpose-built rental housing. The interest rate is higher than the rate the federal government pays on long-term bonds. For renters, purpose-built rental housing owned by a pension fund or REIT is more secure than renting a condo or secondary suite from an individual landlord, who can always reclaim the space for personal use.
The program was renamed from Rental Construction Finance Initiative (RCFI) to Apartment Construction Loan Program in the 2023 Fall Economic Statement on November 21, 2023, adding $15B in funding for new loans to build more rental apartments, faster starting 2025-26.
Affordable Housing Fund: New Construction (National Housing Co-Investment Fund)
- Description: Low-interest and forgivable loans to build new affordable housing.
- Funding: $4.7B in grants and $11B in loans ($15.9 billion total)
Build up 60,000 units of new social housing over 10 years to developers that meet certain criteria including ensuring that:
- 30% of units in a development will rent for less than 80 per cent of median market rents for at least 20 years.
- 25%+ reduction in energy consumption and greenhouse gas emissions over national building and energy codes.
- 20% of units meet accessibility standards.
Projects can now get up to:
- $75,000 per unit for exceeding affordability and energy efficiency standards
- $25,000 per unit for meeting minimum social outcome requirements
The program was renamed from National Housing Co-Investment Fund (NHCF) to the Affordable Housing Fund in the 2023 Fall Economic Statement on November 21, 2023, adding $1B in funding over 3 years for new loans to build more affordable housing, starting 2025-26.
Rapid Housing Initiative (RHI)
- Description: Create 4,500 new units of permanent affordable housing for people and populations who are vulnerable and targeted under the National Housing Strategy (NHS), 25% of investments going towards women-focused affordable housing projects.
- Funding: $1.5 billion: $1 billion to Projects Stream and $500 million to Cities Stream.
Announced in Budget 2022 focuses on immediate housing needs with the goal to commit all funds by March 31, 2024. Capital contributions for the rapid construction of new housing and/or acquisition of existing buildings for rehabilitation or conversion to permanent affordable housing.
Affordable Housing Innovation Fund
- Description: Funding for unique ideas and innovative building techniques that revolutionize the affordable housing sector.
- Funding: $550.8 million over 6 years
Housing Accelerator Fund
- Description: Encourage local initiatives to build more homes, faster.
Programs to renovate existing affordable housing
Affordable Housing Fund: Renovation (National Housing Co-Investment Fund (NHCF))
- Description: Low-interest loans and contributions to renovate and repair existing buildings for affordable housing. Prioritizes partnerships between governments, non-profits, private sector and other partners.
- Funding: $13.17B (includes Affordable Housing Fund: New)
Major part of the Strategy. Repair 240,000 units over 10 years to developers that meet certain criteria including ensuring that:
- 30% of units in a development will rent for less than 80 per cent of median market rents for at least 20 years.
- 25%+ reduction in energy consumption and greenhouse gas emissions over national building and energy codes.
- 20% of units meet accessibility standards.
The program was renamed from National Housing Co-Investment Fund (NHCF) to the Affordable Housing Fund in the 2023 Fall Economic Statement on November 21, 2023, adding $1B in funding over 3 years for new loans to build more affordable housing, starting 2025-26.
Canada Community Housing Initiative
- Description: Replacing federal funding for social housing that had been scheduled to expire over the next decade to sustain the 500,000 existing units of provincially administered social housing, as well as social housing directly administered by Ottawa. Cost-matched and delivered by provinces/territories.
- Funding: $4.3B matched by provinces for total of $8.6B
Provincial cost-matching program examples (Ontario)
- Canada-Ontario Housing Benefit (COHB)
- Canada-Ontario Community Housing Initiative (COCHI)
- Ontario Priorities Housing Initiative (OPHI)
Affordable Housing Innovation Fund
- Description: Funding for unique ideas and innovative building techniques that revolutionize the affordable housing sector.
- Funding: $550.8 million over 6 years
Other funding and financing opportunities
Programs for community housing providers
Canada Housing Benefit
- Description: Provide low-income renter households with financial assistance through an average annual rent subsidy of $2500 through provincial and territorial rent support programs.
- Funding: $2B matched by provinces for total of $4B to provide support for 300,000 households by 2027-28
- Period: April 2020 to 2028
Federal Community Housing Initiative
- Description: Support federally administered community housing projects reaching the end of their operating agreements from past social and affordable housing programs.
- Funding: $618.2 million in rent assistance
Community Housing Transformation Centre
- Description: Increasing the capacity and supporting efficient community housing.
- Funding: Non-repayable contributions to support the longer-term evolution of community housing providers’ business models. These contributions aim to encourage the development of more efficient and resilient business models without displacing low-income households.
Community-Based Tenant Initiative
- Description: Local organizations that assist people in housing need to access resources and information about their housing options.
- Funding: $10 million in funding over 5 years
Critic response
Contributions and loans are fundamentally different in their cost to government and ability to influence behaviour. Because loans must be repaid, they provide less of a financial incentive than a direct contribution of the same face value. The budgetary costs associated with loan programs arises from provisions for credit risks or insurance, interest timing mismatch and operating costs. For example, the budgetary cost of the $3.75 billion in loans available under the Rental Construction Financing Initiative (prior to Budget 2019) is only $0.3 billion.
Parliamentary Budget Officer (PBO) 2019 report
At best, we can say that the NHS maintains previous federal effort on housing supports, has spurred some new market rental housing, and is slowly rolling out a modest amount of new social housing.
Marc Lee, Policy Note
Arguably, the RCFI is arguably clearly a program for the middle class rather than those most in need of affordable housing.
Marc Lee, Policy Note
As housing analyst Steve Pomeroy notes, the lowest rents under the RCFI would still be far in excess of what most renter households can afford.
Sources
- Federal Program Spending on Housing Affordability in 2021 – Parliamentary Budget Officer (PBO)
- Toward Evidence Based Policy: Assessing the CMHC Rental Housing Finance Initiative (RCFI) – Centre for Urban Research and Education (CURE)
- What happened to the National Housing Strategy? – Policy Note
- $15B in new funding for social housing – Russil Wvong
Leave a comment
All comments are reviewed prior to appearing on the site.
Rules: